NivaarExam PrepOfficial exam papers ↗

16-Civ-B4 Engineering Hydrology: May 2016

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

  1. Question 1 Hydrologic cycle processes, groundwater flow and surface runoff
  2. Question 2 Runoff hydrographs, unit hydrographs and conceptual models
  3. Question 3 Point and areal precipitation, and stream flow measurement
  4. Question 4 Hydrologic modelling, and reservoir and lake routing
  5. Question 5 Channel or river routing and flood wave behaviour
  6. Question 6 Frequency and probability analysis of precipitation and floods
  7. Question 7 The hydrologic equation, energy budget and infiltration simulation

Start with Question 1 →

Paper format. 98-Civ-B4 Engineering Hydrology, May 2016 — a three-hour closed-book examination; a candidate-prepared two-sided aid sheet and one approved Casio or Sharp calculator are permitted. The cover page states that “any five(5) questions constitute a complete paper” and that “each question is equally weighted at twenty (20) points”, so the seven printed Problems each carry 20 marks towards a 100-mark paper. The page-6 Marking Scheme confirms the sub-part split for all seven. Note 1 invites the candidate to state any assumptions made where a question is open to interpretation; this sitting needs that licence twice, and both places are flagged in a callout below. All seven Problems are worked here, because this set is a study resource rather than a timed sitting.

Reference texts. V. T. Chow, D. R. Maidment and L. W. Mays, Applied Hydrology (hydrologic cycle, unit hydrograph theory, Horton infiltration, level-pool and Muskingum routing, frequency analysis); W. Viessman and G. L. Lewis, Introduction to Hydrology, 5th ed. (areal precipitation, hydrograph analysis, conceptual watershed models); P. B. Bedient, W. C. Huber and B. E. Vieux, Hydrology and Floodplain Analysis, 5th ed. (rating curves, reservoir and river routing, urban design storms); R. S. Gupta, Hydrology and Hydraulic Systems, 4th ed. (groundwater recharge and discharge areas, streamflow measurement); L. W. Mays, Water Resources Engineering, 3rd ed. (Rational Method, IDF design practice). For the Canadian frame: Environment and Climate Change Canada IDF curve files, the Water Survey of Canada Hydrometric Manual (mid-section gauging to ISO 748), and the Transportation Association of Canada Drainage Manual for design-storm and runoff-coefficient practice.

Check — two source-data issues and one declared convention.

(1) Problem 1(iii) gives the IDF relation as i = 6.0 − 0.3 td without stating the units of i. The paper's own Problem 6(iii) figure plots rainfall on an axis labelled “Rainfall and Infiltration, mm/h” with a peak near 13, so mm/h is adopted and the alternative reading is carried through in the answer as a sensitivity.

(2) Problem 7(i) as printed cannot be satisfied: the stated area and river discharge fix the runoff depth at 5045.76 mm/a, which is 63 times the 80 mm/a of rain the question supplies, so the residual evapotranspiration comes out large and negative. The answer boxes the runoff depth, demonstrates that the balance cannot close, and then adopts a declared corrected precipitation. This is the response Note 1 asks for.

(3) Problems 3(iii), 5(iii), 6(i) and 7(iii) ask for method, not arithmetic; each is worked on a small dataset that is the solver's own representative example, clearly labelled as illustrative. Every number in those examples, and every number taken from the real source data.