23-Chem-A2 Unit Operations and Separation Processes · December 2015
Question 6 of 6: Sizing a Tubular (Water-to-Water) Heat Exchanger
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams — 04-CHEM-A2 Mechanical and Thermal Operations, December 2015. 3 hours, open book (one text). Six problems (Section A Mechanical Operations: A1–A3; Section B Thermal Operations: B1–B3), each 25 marks; candidates attempt at least two from each section. All six are worked below for completeness.
Reference texts. Coulson & Richardson, Chemical Engineering Vol. 1 (fluid flow, heat transfer) and Vol. 2 (particle technology, filtration, evaporation); McCabe, Smith & Harriott, Unit Operations of Chemical Engineering (7th ed.); Incropera & DeWitt, Fundamentals of Heat and Mass Transfer (8th ed.); Perry's Chemical Engineers' Handbook (9th ed.).
Note on the figureThe only figure in the paper is the LMTD correction-factor chart on page 5 (used in B3). It is read at the plotted parameters $P=0.25$, $R=2.0$; the value obtained ($F\approx0.94$) is confirmed analytically from the closed-form 1-outer-pass / 2-tube-pass expression.
Question B3: Sizing a Tubular (Water-to-Water) Heat Exchanger (25 marks)
Given. A 1-outer-pass, multi-tube-pass water-to-water exchanger sized inside-out from the tube-side duty, the tube-side design velocity, and a length limit.
Quantity
Value
Tube-side water: $\dot m$, $30\to45$ °C
14,400 kg/h = 4 kg/s
Outer-vessel water: $\dot m$, in 90 °C
120 kg/min = 2 kg/s
$U_i$ (inside-area basis)
1390 W/m²·°C
Tube inside diameter $d_i$
1.875 cm
Design tube velocity
37.7 cm/s = 0.377 m/s
Maximum tube length
1.75 m
Water $\rho$ / $c_p$
993 kg/m³ / 4174 J/kg·K
Find. (a) total number of tubes, (b) tubes per pass, (c) length of each tube.
Figure B3 — 1-outer-pass / 2-tube-pass exchanger: cold tube water heated $30\to45$ °C by outer water cooling $90\to60$ °C; the design velocity sets tubes-per-pass, the area sets total tubes and length.
Approach. Two nearly independent constraints size the bundle: the thermal duty fixes the total inside area (via $UF\Delta T_{\text{lm}}$), while the tube-side velocity fixes tubes-per-pass; the length limit then sets the number of passes.
LMTD and correction factor. Counter-current terminal differences $90\to45$ and $60\to30$: $$\Delta T_{\text{lm}}=\frac{45-30}{\ln(45/30)}=37.0\ \text{K}.$$ With $P=(45-30)/(90-30)=0.25$ and $R=(90-60)/(45-30)=2.0$, the 1-outer / 2-tube-pass factor (chart, confirmed in closed form) is $F=0.94$, so $$A_i=\frac{Q}{U_iF\Delta T_{\text{lm}}}=\frac{2.504\times10^{5}}{1390(0.94)(37.0)}=5.17\ \text{m}^2.$$
Part (b): tubes per pass from the velocity. Tube bore area $\tfrac{\pi}{4}(0.01875)^2=2.761\times10^{-4}$ m², so flow per tube $=0.377\times2.761\times10^{-4}=1.041\times10^{-4}$ m³/s. Total flow $\dot m_t/\rho=4/993=4.028\times10^{-3}$ m³/s: $$n_{\text{pass}}=\frac{4.028\times10^{-3}}{1.041\times10^{-4}}=38.7.$$ $n_{\text{pass}} = 39\ \text{tubes per pass}$
Parts (a) and (c): passes, total tubes, length. Spreading $A_i$ over $39\,n_p$ tubes, $A_i=(39n_p)\pi d_iL$ gives $n_pL=A_i/(39\pi d_i)=2.25$ m. One pass would need $L=2.25>1.75$ m, so use two tube passes: $$n_p=2\;\Rightarrow\;L=\frac{2.25}{2}=1.13\ \text{m}\ (\le1.75),\quad N=39\times2.$$ $N = 78\ \text{tubes},\quad L = 1.13\ \text{m}$ Check: $78\pi(0.01875)(1.13)=5.17$ m², matching $A_i$; two tube passes is exactly the geometry the $F$-chart was drawn for.