23-Chem-A5 Chemical Plant Design and Economics · May 2014
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Exams — May 2014 — 04-Chem-A5 Chemical Plant Design and Economics. Three-hour, closed-book exam; any non-communicating calculator permitted. Six equally weighted (20-mark) questions are posed and the candidate answers any five; only the first five are marked. All six are answered below for completeness. Questions 1, 5 and 6 are conceptual design / management / safety questions answered as organised prose; questions 2, 3(i) and 4 contain the numerical work (cost–capacity scaling of a heat exchanger, sinking-fund depreciation, and simple/compound loan interest), and every boxed figure.
Reference texts: M.S. Peters, K.D. Timmerhaus & R.E. West, Plant Design and Economics for Chemical Engineers (5th ed., McGraw-Hill) — the exam's named primary text (cost estimation Ch. 6, interest and investment Ch. 7, depreciation Ch. 9, profitability Ch. 10, optimum design Ch. 11, plant safety and loss prevention); R. Turton et al., Analysis, Synthesis, and Design of Chemical Processes (4th ed., Prentice Hall) — flowsheet synthesis and process development; T.M. Duncan & J.A. Reimer, Chemical Engineering Design and Analysis (Cambridge, 1998) — the source of the boiling-point data used in Question 1; supporting Canadian tax practice from the Canada Revenue Agency Capital Cost Allowance classes and the half-year rule.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
The question has two layers that a good answer must keep distinct: (a) the process flow sheet — the physical sequence of unit operations that turns air and water into pure ammonia — and (b) the project-development flow sheet — the sequence of engineering stages that carries the venture from a conceptual idea to a fully operational plant. Both are addressed below.
The stoichiometry $\mathrm{N_2+3H_2\rightarrow 2NH_3}$ says the plant must first manufacture the two reactant gases from the given feedstocks, react them, and then separate the product. The boiling-point table is the key to the separations, because every split in this process is a difference-in-volatility split:
The project flow sheet is the ordered set of engineering stages, each with its own decision points, that P&T Ch. 1 calls the development of a design project. Written as a sequence:
| Development stage | Key points to be considered |
|---|---|
| 1. Conceptual idea / market survey | Product demand and price, plant capacity, competing routes, siting near feedstock/market; go / no-go on order-of-magnitude economics. |
| 2. Laboratory & thermodynamic feasibility | Reaction equilibrium and kinetics, catalyst selection, yield, physical-property and phase-behaviour data (the boiling points here). |
| 3. Process synthesis / flow-sheet development | Choose and sequence unit operations (ASU, electrolysis, converter, condenser, recycle); fix the block flow diagram. |
| 4. Material & energy balances | Close the mass and energy balances around every unit; set stream flows, compositions, temperatures and pressures. |
| 5. Equipment sizing & mechanical design | Size reactors, columns, compressors, exchangers; select materials of construction; apply codes (ASME BPVC for the high-pressure loop). |
| 6. Cost estimation & profitability | Capital (fixed + working) and operating cost estimates; return on investment, payout, discounted-cash-flow analysis. |
| 7. Detailed engineering (PFD → P&ID) | Piping, instrumentation and control, plot plan, utilities, electrical; issue for-construction drawings. |
| 8. Safety, loss-prevention & environmental review | HAZOP, relief-system design, emissions and effluent permits (Canadian CEPA / provincial approvals). |
| 9. Procurement & construction | Purchase long-lead equipment, fabricate, erect, inspect and test. |
| 10. Commissioning, start-up & operation | Pre-commissioning checks, catalyst loading, controlled start-up, performance test, then steady operation and continual optimization. |