NivaarExam PrepOfficial exam papers ↗

16-Civ-A5 Hydraulic Engineering · December 2013

Question 4 of 6: Two elevated tanks — quasi-steady simulation

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper: National Exams — 98-Civ-A5 Hydraulic Engineering, December 2013 · 3 hours, closed book (one 8.5×11 aid sheet). Six questions; any five constitute a complete paper — all six are solved here as a study resource. All parts of a question are of equal value; ‘cms’ = m³/s.

Reference texts. Mays, Water Resources Engineering, 3rd ed. (pipe systems, valves, network analysis); Chow, Open-Channel Hydraulics (Manning uniform flow, gutter flow); Crowe, Elger & Roberson, Engineering Fluid Mechanics (laminar film flow, energy/continuity). Exam-supplied relations used throughout: Hazen–Williams $Q=0.278\,C\,D^{2.63}\,S^{0.54}$ with $S=h_f/L$ (SI), Manning $Q=\tfrac{1}{n}A\,R^{2/3}\,S^{1/2}$, Darcy–Weisbach, and total dynamic head $\text{TDH}=H_s+H_f$. Unless stated, local losses and velocity head are neglected and water has $\rho=1000\ \text{kg/m}^3$, $\nu=1.31\times10^{-6}\ \text{m}^2/\text{s}$.

The Hazen–Williams relation is used in inverted form to get the friction loss carried by a known pipe discharge $Q$ (SI, $Q$ in m³/s):

$$h_f = L\left(\dfrac{Q}{0.278\,C\,D^{2.63}}\right)^{1/0.54}.$$

Question 4: Two elevated tanks — quasi-steady simulation (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Check (Question 4 data are inconsistent — NOTE 1 assumption). The stated “initial steady-state flow = 350 L/s” implies a node head of only $H=(0.350/0.15)^2=5.4$ m; but at $H=5.4$ m the two mains, driven by the 96 m and 91 m tank levels, would deliver $\approx 1{,}110$ L/s — so 350 L/s is not a steady state. Continuity at the node fixes a network-consistent initial discharge of $\approx 890$ L/s at a node head of $\approx 35.2$ m; the simulation is run from that physically consistent state. The figure also labels Tank 2 at 89 m and $L=300$ m, which conflict with the prose values (91 m, 350 m); the prose is adopted and the discrepancy noted per NOTE 1.

Given. Two supply pipes meet at a demand node whose valve discharges to atmosphere; tanks fall as they deliver.

Given data (Question 4)
Tank 1 / Tank 2 initial level96 m / 91 mTank diameter5 m ($A=19.63$ m²)
Pipe $C$ / $D$ / $L$100 / 300 mm / 350 mValve coeff. $C_v$0.15 m$^{5/2}$/s
Valve law (to atmosphere)$Q_v=C_v\sqrt{H}$Time step $\Delta t$15 s

Find. Node pressure head $H$ and pipe flows $Q_1,Q_2$ at the first three time steps.

Tank 196 mTank 291 mHGLHQ (valve)L=350 mL=350 m
Figure 4. Two tanks feed a common node; $H$ is the node pressure head, $Q$ the valve discharge to atmosphere.

Approach. At each step the node is treated as steady: the two inflows (Hazen–Williams, driven by tank level minus node head $H$) must equal the valve outflow $C_v\sqrt{H}$. Solve that single continuity equation for $H$, read $Q_1,Q_2$, then lower each tank by $Q_i\Delta t/A_{\text{tank}}$ and repeat.

  1. Continuity at the node. With $z_1,z_2$ the tank levels and $H$ the node head, $$Q_1+Q_2=C_v\sqrt{H},\qquad Q_i=0.278\,C\,D^{2.63}\!\left(\dfrac{z_i-H}{L}\right)^{0.54}.$$ This is one nonlinear equation in $H$; solve by bisection.
  2. Step 1 ($z_1=96.00$, $z_2=91.00$). The balance closes at $H=35.2$ m, giving $$\boxed{H_1=35.2\ \text{m},\quad Q_1=455\ \text{L/s},\quad Q_2=435\ \text{L/s},\quad Q_v=890\ \text{L/s}.}$$
  3. Update the tanks. $\Delta z_i=Q_i\Delta t/A_{\text{tank}}$: $\Delta z_1=0.455(15)/19.63=0.348$ m, $\Delta z_2=0.435(15)/19.63=0.332$ m, so $z_1\to95.65$, $z_2\to90.67$ m.
  4. Step 2 ($z_1=95.65$, $z_2=90.67$): $H_2=35.1$ m, $Q_1=455$ L/s, $Q_2=434$ L/s, $Q_v=888$ L/s. Update: $z_1\to95.31$, $z_2\to90.34$ m.
  5. Step 3 ($z_1=95.31$, $z_2=90.34$): $H_3=34.9$ m, $Q_1=454$ L/s, $Q_2=433$ L/s, $Q_v=887$ L/s.

Over the first 45 s the tanks fall only about 1 m, so the node head and discharges drift down very slowly (890→887 L/s) — the hallmark of a quasi-steady drawdown where storage change per step is small compared with the through-flow.

Question 4 — quasi-steady simulation ($\Delta t=15$ s)
Step$z_1$ (m)$z_2$ (m)Node head $H$ (m)$Q_1$ (L/s)$Q_2$ (L/s)$Q_v$ (L/s)
196.0091.0035.2455435890
295.6590.6735.1455434888
395.3190.3434.9454433887