NivaarExam PrepOfficial exam papers ↗

16-Civ-A6 Highway Design, Construction, and Maintenance · May 2018

Question 5 of 7: Asphalt Institute redesign of a Northern Ontario pavement

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Examinations, May 2018, 16-Civ-A6 — Highway Design, Construction, and Maintenance. Seven questions of equal value (20 marks each), three hours, closed book, with a ten-page appendix of design charts and tables. Only the first five solutions are marked, but because this set is a study resource all seven questions are solved here.

Unless a question states otherwise the perception–reaction time is taken as $t_{pr}=2.5\ \text{s}$ (the AASHTO design value) under NOTE 2 on page 1, and $g=9.81\ \text{m/s}^{2}$. Stopping and side friction coefficients are read from the “Friction Coefficients to be used in questions” table on appendix page 9; clear-zone widths and their horizontal-curve correction factors come from the two tables on the same page.

Reference texts.

Question 5: Asphalt Institute redesign of a Northern Ontario pavement (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. An Asphalt Institute design already completed as a full-depth section, together with the constraints the supervisor has added:

Design inputs and constraints
QuantityValue
Mean annual air temperature7 °C (Design Charts A-1 to A-6)
Subgrade resilient modulus$M_{r}=70\ \text{MPa}$
Initial full-depth asphalt concrete design225 mm
Frost depth1.2 m
Minimum structure thickness70 % of the frost depth
Base course materialcold mix from local silty sand, mobile plant
Layer order (Figure 2)asphalt concrete / cold asphalt mix / granular base / subgrade
Cost driversasphalt plant 70 km away; good aggregates scarce

Find. A revised three-layer section — asphalt concrete, cold mix and unbound granular base — that carries the same traffic, satisfies the frost-depth rule, and minimises both the asphalt concrete and the granular base.

Asphalt concrete90 mmTable VI-2 minimumCold mix, Type III emulsified260 mmlocal silty sandUnbound granular base490 mmfrost protectionSubgrade840 mmRevised section: 840 mm is 70 per cent of the 1.2 m frost depth
Figure 5.1 — the revised three-layer section. The total thickness is set by frost protection; the cheap on-site cold mix carries the structure.

Approach. Recover the design traffic from the full-depth chart, identify the correct emulsified-mix type for a local silty sand, read the equivalent thickness from its design chart, set the asphalt concrete to the tabulated minimum over that base, and let the granular layer make up the balance to the frost-protection thickness.

  1. Recover the design traffic. The full-depth design fixes the traffic implicitly. Entering Design Chart A-1 (Full Depth Asphalt Concrete, MAAT 7 °C) at $M_{r}=70\ \text{MPa}$ and following the 225 mm curve gives$$EAL\approx 2.3\times 10^{6}\ \text{equivalent }80\ \text{kN single axle loads}$$Every subsequent chart is entered at this same traffic level, which is what makes the layers comparable.
  2. Frost protection sets the total thickness. The supervisor’s rule is explicit:$$T_{\text{total}}\ge 0.70\times 1\,200\ \text{mm}=\boxed{840\ \text{mm}}$$The initial 225 mm full-depth section fails this test by a factor of nearly four — which is precisely the omission the supervisor identified. Structural adequacy and frost adequacy are separate requirements, and here frost governs the total by a wide margin.
  3. Classify the cold mix. The Asphalt Institute divides emulsified asphalt mixes by the aggregate they are made from: Type I from processed, dense-graded aggregate; Type II from semi-processed crusher-run, pit-run or bank-run aggregate; Type III from sands and silty sands. The material here is local silty sand from the excavation, so it is an emulsified asphalt mix Type III and Design Chart A-4 governs. This is also the economically correct choice: it is made on site with a mobile plant and consumes the excavation spoil rather than imported aggregate.
  4. Thickness of the emulsified-asphalt pavement. Entering Chart A-4 at $M_{r}=70\ \text{MPa}$ and $EAL=2.3\times 10^{6}$ gives a required total thickness of about 335 mm, and rounding up to the chart’s 25 mm increment,$$T_{\text{III}}=\boxed{350\ \text{mm}}$$The implied substitution ratio is $350/225=1.56$, i.e. about 1.6 mm of Type III cold mix replaces 1 mm of hot-mix asphalt concrete — the expected penalty for a sand-based, emulsion-bound material.
  5. Minimum asphalt concrete over the cold mix. A Type III base cannot be exposed to traffic, so Table VI-2 requires an asphalt concrete surface: 75 mm at $10^{6}$ EAL and 100 mm at $10^{7}$. Interpolating logarithmically at $2.3\times 10^{6}$,$$t_{AC,\min}=75+25\log_{10}\!\left(\dfrac{2.3\times 10^{6}}{10^{6}}\right)=75+25(0.362)=84\ \text{mm}$$Because the supervisor wants the hot mix minimised, specify the smallest practical thickness that clears this: $$t_{AC}=\boxed{90\ \text{mm}}$$placed as a 50 mm binder and a 40 mm surface course, which is also the minimum that allows two compacted lifts.
  6. Cold-mix base thickness. The asphalt concrete is part of the 350 mm bound structure, so the balance is made up in cold mix:$$t_{\text{cold mix}}=T_{\text{III}}-t_{AC}=350-90=\boxed{260\ \text{mm}}$$placed in two lifts of 130 mm, cured before the surfacing is laid.
  7. Granular base thickness. The unbound layer is now needed only to complete the frost-protection thickness and to give a working platform and drainage blanket over the subgrade:$$t_{\text{granular}}=T_{\text{total}}-T_{\text{III}}=840-350=\boxed{490\ \text{mm}}$$This is the minimum consistent with the frost rule, which is exactly what the supervisor asked for. Ignoring its structural contribution is conservative: Charts A-5 and A-6 show that 150 mm and 300 mm of untreated aggregate base each reduce the required bound thickness, so the 490 mm provided is a genuine reserve rather than dead thickness.
  8. Assemble and check.$$90+260+490=\boxed{840\ \text{mm}}=0.70\times 1\,200\ \text{mm}\quad\checkmark$$The section satisfies the traffic through the 350 mm bound structure, satisfies frost through the 840 mm total, uses only 90 mm of imported hot mix, and takes 490 mm of the total from an unbound layer whose thickness is the minimum the frost rule permits.

Check: chart reads and the thickness-accounting convention. The two design charts were read from the printed figure of appendix pages 5 and 6; a reasonable reading tolerance is about ±10 % on EAL and one 25 mm curve interval on thickness, neither of which changes the design because frost, not traffic, sets the total. The asphalt concrete is taken to be part of the 350 mm emulsified-pavement thickness, following the Asphalt Institute convention that hot mix substitutes for an equal thickness of the emulsified mix; if instead it were placed on top of a full 350 mm of cold mix the bound structure would be 440 mm and the granular layer would shrink to 400 mm, with the same 840 mm total.

Question 5 — proposed section
LayerMaterialThicknessBasis
SurfaceAsphalt concrete (hot mix)90 mmTable VI-2 minimum (84 mm interpolated)
BaseCold mix, Type III emulsified asphalt260 mmChart A-4 total 350 mm less the 90 mm surface
SubbaseUnbound granular base490 mmbalance to the frost-protection thickness
Total structure—840 mm70 % of the 1.2 m frost depth
Design traffic—2.3 × 106 EALChart A-1 at $M_r=70$ MPa, 225 mm
Substitution ratio, Type III to hot mix—1.56350 mm / 225 mm