Question 3 of 7: Webster signal design for a four-approach intersection
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Examinations, December 2017 — 16-Civ-B10 Traffic Engineering, 3-hour duration, OPEN BOOK (any non-communicating calculator permitted). Seven questions of equal value (20 marks each); the paper requires five solutions and marks only the first five as they appear in the answer book. Because the set is a study resource, all seven questions are solved here. The paper's own Note 1 invites a clear statement of any assumptions made and Note 2 permits any required-but-not-given data to be assumed; every assumption used below is stated explicitly where it is introduced.
Reference texts.
Garber, N.J. and Hoel, L.A., Traffic and Highway Engineering, 5th ed., Cengage — Ch. 5 (traffic-engineering studies), Ch. 6 (fundamental principles of traffic flow and queueing), Ch. 8 (intersection control and signal timing), Ch. 15 (geometric design of highway facilities).
Transportation Research Board, Highway Capacity Manual — signalized-intersection capacity, saturation flow and pedestrian-interval methods.
AASHTO, A Policy on Geometric Design of Highways and Streets, 2001 metric edition — stopping sight distance and crest/sag vertical curves (the SSD table reproduced on page 4 of this paper is AASHTO 2001, Table 3-1).
Transportation Association of Canada, Geometric Design Guide for Canadian Roads — the Canadian design-controls equivalent of the AASHTO Green Book, and the governing document for Canadian practice.
Transportation Association of Canada, Manual of Uniform Traffic Control Devices for Canada (MUTCDC) — signal displays, pedestrian intervals and clearance timing.
Webster, F.V. and Cobbe, B.M., Traffic Signals, Road Research Technical Paper No. 56, HMSO — the optimum-cycle and delay relations used in Questions 3 and 4.
Question 3 — Webster signal design for a four-approach intersection 20 marks
Lost time per phase from acceleration and deceleration $\ell = 3.5$ s; all-red interval per phase $AR = 1.5$ s.
Find. An appropriate phasing system with its justification, the intersection lane geometry it requires, the optimum cycle length by the Webster method, and the phase (green) lengths.
Figure 3.1 — Lane geometry adopted for the four approaches (left) and the resulting two-phase sequence with its ring timing and pedestrian check (right).
Approach. Establish the lane geometry implied by the stated approach widths, convert the peak-hour volumes to peak-flow rates with the PHF, assign movements to lanes and balance the through movement so both lanes on an approach carry the same degree of saturation, take the critical flow ratio on each street, apply Webster's optimum-cycle formula, then test the resulting green times against the pedestrian minimum-green requirement and adopt whichever control governs.
Interpret the approach widths and fix the lane geometry. The widths in the volume table are curb-to-curb widths shared by both directions of travel. With 3.5 m lanes,
so every approach has two lanes. Reading 18 m as a one-direction width would imply five lanes per approach at about 250 veh/h/lane, which is not a credible loading for a peak-hour intersection carrying 1200–1500 veh/h per approach. Since 20 m will not take six 3.5 m lanes, the East and West approaches also have two lanes each despite being wider. With three movements sharing two lanes the natural assignment is lane 1 = left + through ($s = 1900$ vphpl) and lane 2 = through + right ($s = 2080$ vphpl), which is the geometry drawn in Figure 3.1(i).
Convert peak-hour volumes to peak 15-minute flow rates. Design must be for the peak rate within the hour, so every movement is divided by the PHF:
$$v = \frac{V}{\text{PHF}} = \frac{V}{0.95}$$
Approach
Left (v)
Through (v)
Right (v)
Total (v)
North
247.4
774.7
228.4
1250.5
South
215.8
688.4
327.4
1231.6
East
231.6
815.8
360.0
1407.4
West
231.6
894.7
369.5
1495.8
Balance the through movement across the two lanes and obtain each approach flow ratio. Drivers distribute themselves so that the two lanes on an approach reach the same degree of saturation. Letting $x$ be the through volume choosing lane 1,
and the check on lane 2 returns the same number, $653.5/2080 = 0.3142$. Repeating for the other three approaches:
Approach
Lane 1 flow (L + part T)
Lane 2 flow (rest of T + R)
Flow ratio $y$
North
597.0
653.5
0.3142
South
587.9
643.6
0.3094
East
671.9
735.5
0.3536
West
714.1
781.7
0.3758
Note that the flow ratio, not the volume, decides which movement is critical: West is critical on the E–W street and North on the N–S street even though South carries more right turns than North.
Determine an appropriate phasing system — and price the alternative before rejecting it. The question asks for a phasing system and its justification, so the four-phase option (exclusive protected left turns on each street) must be tested rather than dismissed. With only two lanes per approach, an exclusive left bay forces the entire through-plus-right demand onto one through-right lane, and the critical flow ratios become
A four-phase plan cannot be timed at any cycle length. Two further arguments point the same way: each additional phase costs another 5.0 s of lost time and another full pedestrian minimum green, and the pedestrian volumes here (985–1345 per hour on every leg) are already the binding constraint. A two-phase plan with permitted left turns is therefore adopted — Phase A serving North and South, Phase B serving East and West, as drawn in Figure 3.1(ii).
Sum the critical flow ratios and the lost time. The critical approach in each phase governs:
On vehicular grounds alone a cycle of about 65 s would minimise delay. This value must not be adopted before the pedestrians are checked, because the table's "conflicting pedestrian volumes" row signals a pedestrian-controlled design.
Write the pedestrian minimum-green requirement for each phase. The HCM pedestrian green-time requirement for a crosswalk wider than 3.0 m is
with $S_p = 1.2$ m/s. The crosswalks a phase must clear are those on which pedestrians walk parallel to that phase's vehicles: the N–S phase releases pedestrians across the East and West legs, and those legs span the E–W carriageway, so $L_c = 20$ m with $v_{ped} = \max(1200, 1345) = 1345$/h. Symmetrically the E–W phase clears the North and South legs, $L_c = 18$ m and $v_{ped} = \max(1000, 985) = 1000$/h. Taking $W_E = 4.0$ m (see the assumption callout),
and because the green is split in proportion to the flow ratios this same value must reappear as $q/c$ on both critical approaches, which validates the lane assignment, the flow ratios and the split in one line:
$$\text{North lane 1: } \frac{597.0}{1900(52.4/125)} = 0.750, \qquad \text{West lane 1: } \frac{714.1}{1900(62.6/125)} = 0.750 \;\checkmark$$
A critical degree of saturation of 0.75 is comfortable — the low value is itself the signature of a pedestrian-controlled design, in which the vehicles receive far more green than their demand requires.
Quantity
Result
Lane geometry
2 lanes per approach on all four legs; lane 1 = left + through, lane 2 = through + right
Phasing system adopted
Two phases, permitted left turns (Phase A = N–S, Phase B = E–W)
$G_A = 55.9$ s, $G_B = 66.1$ s, plus 1.5 s all-red at each change
Critical degree of saturation
$x_{crit} = 0.750$
Check — assumed data (paper Note 2: "any data required, but not given, can be assumed")
Crosswalk width $W_E = 4.0$ m. This value is not supplied and it swings the answer hard, because the pedestrian term is $2.7\,N_{ped}/W_E$: at $W_E = 3.0$ m the governing cycle rises to about 220 s, at 5.0 m it falls to about 105 s. A 4.0 m crosswalk is chosen as the value a designer would actually select for legs carrying 1000–1345 pedestrians per hour. Note that the HCM changes branch at exactly $W_E = 3.0$ m, where the coefficient becomes $0.27\,N_{ped}$ rather than $2.7\,N_{ped}/W_E$ — a factor-of-3.3 discontinuity — so a narrow-crosswalk design would give a much shorter governing cycle (about 75 s). Any answer must therefore name the branch it is on.
Other assumptions: lane width 3.5 m; walking speed $S_p = 1.2$ m/s (MUTCDC general population); permitted left turns operate within the shared lane at the tabulated left-through saturation flow; no start-up lost time beyond the stated 3.5 s per phase; cycle rounded up to the nearest 5 s. Rounding up is deliberate — rounding down would fail the pedestrian check.