Question 2 of 7: Webster signal design for a four-approach intersection
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Examinations, December 2019, 16-Civ-B10 Traffic Engineering. Three-hour duration, OPEN BOOK (any non-communicating calculator permitted). Seven questions on four pages, all of equal value at 20 marks each; the paper requires five solutions and marks only the first five as they appear in the answer book. Because the set is a study resource, all seven questions are solved here. The paper’s own Note 1 invites a clear statement of any assumptions made and Note 2 permits any required-but-not-given data to be assumed; every assumption used below is stated explicitly where it is introduced. Page 2 reproduces the AASHTO 2001 metric stopping-sight-distance table, whose footnote fixes the brake-reaction time at 2.5 s and the deceleration at 3.4 m/s2; Question 1 is built around it.
Reference texts.
Garber, N.J. and Hoel, L.A., Traffic and Highway Engineering, 5th ed., Cengage — Ch. 4 (traffic-engineering studies, moving-vehicle method), Ch. 6 (fundamental principles of traffic flow and deterministic queueing), Ch. 8 (intersection control and signal timing), Ch. 15 (geometric design of highways, crest vertical curves).
Transportation Research Board, Highway Capacity Manual — signalised-intersection capacity, saturation flow, lane-group definition and the pedestrian-interval (minimum green) method.
AASHTO, A Policy on Geometric Design of Highways and Streets, 2001 metric edition — stopping sight distance and crest vertical curves; the table printed on page 2 of this paper is AASHTO 2001, Table 3-1.
Transportation Association of Canada, Geometric Design Guide for Canadian Roads — the Canadian design-controls document, and the governing reference for Canadian practice.
Transportation Association of Canada, Manual of Uniform Traffic Control Devices for Canada (MUTCDC) — signal displays, actuated control and pedestrian intervals.
Webster, F.V. and Cobbe, B.M., Traffic Signals, Road Research Technical Paper No. 56, HMSO — the optimum-cycle and average-delay relations used in Questions 2 and 5.
Hillier, F.S. and Lieberman, G.J., Introduction to Operations Research — the M/M/1 birth-and-death results used in Question 4.
Canadian context. These are Engineers Canada national examinations, so the answers are framed for Canadian practice: the TAC Geometric Design Guide for Canadian Roads and the MUTCDC are the governing documents and metric design controls are used throughout. Question 1 supplies the AASHTO 2001 metric table directly, so that table is used as printed — the TAC guide adopts the same 2.5 s / 3.4 m/s2 stopping model, so the two agree here. Lane widths, walking speed and crosswalk geometry follow TAC and MUTCDC practice.
Question 2: Webster signal design for a four-approach intersection (20 marks)
Given. Peak-hour approach volumes, conflicting pedestrian volumes and the peak-hour factor are tabulated on page 2; the saturation flows by lane type are tabulated on page 3. Every approach is 15 m wide curb to curb.
Approach (width)
North (15 m)
South (15 m)
East (15 m)
West (15 m)
Left turn (veh/h)
200
185
200
175
Through movement (veh/h)
800
750
600
550
Right turn (veh/h)
120
150
120
120
Conflicting pedestrians (ped/h)
235
235
100
100
Peak-hour factor
0.75
0.75
0.75
0.75
Lane type
Saturation flow (vphpl)
Through
3075
Through-right
2250
Left
1995
Left-through
2015
Left-through-right
2500
Find. An appropriate phasing system with its justification, the intersection geometry it implies, the optimum and adopted cycle length, and the green time given to each phase.
Question 2: adopted intersection geometry. Each 15 m approach is four 3.5 m lanes plus a 1.0 m median, i.e. two lanes per approach — an inner left-through lane and an outer through-right lane. Left turns are permitted (unprotected).
Approach. Convert the hourly volumes to peak-flow rates, settle the geometry from the stated width, price the candidate phasing plans against the sum of flow ratios before choosing one, balance the two lanes on each approach so both carry the same flow ratio, form Webster’s optimum cycle, test it against the pedestrian requirement of each phase, adopt the larger, and split the available green in proportion to the critical flow ratios.
Peak-flow rates. The peak-hour factor converts an hourly volume to the
flow rate that the signal must actually serve within the peak fifteen minutes,
$$q = \frac{V}{\text{PHF}}$$
With PHF = 0.75 throughout, every movement is divided by 0.75. The north approach, for example,
becomes 266.67 left, 1066.67 through and 160.00 right, a total of 1493.33 veh/h; south, east and
west come to 1446.67, 1226.67 and 1126.67 veh/h respectively. All subsequent arithmetic uses these
flow rates, never the raw volumes.
Geometry implied by the 15 m width. The "(Width)" entry in the volume
table is the full curb-to-curb width shared by both directions. At the TAC standard 3.5 m lane,
15 m is four lanes plus a 1.0 m median, i.e. two lanes per approach. Reading 15 m
as a one-direction width would imply four lanes each way carrying only about 300 veh/h per lane,
which no signal design would ever produce. This is declared as an assumption under the
paper’s Note 1.
Price the candidate phasing plans before choosing one. "Determine an
appropriate phasing system" asks for the justification, not just the plan, so each option is tested
against the sum of critical flow ratios \(Y = \sum y_i\), which must stay below 1 for any timing to
exist. A four-phase plan with exclusive left-turn bays leaves one through-right lane per
approach carrying the whole through-plus-right demand, giving
$$Y_{4} = 0.1337 + 0.5452 + 0.1337 + 0.4267 = 1.2392 \gt 1$$
A two-phase plan with one shared left-through-right lane per approach (s = 2500) gives
$$Y_{1\text{-lane}} = 0.5973 + 0.4907 = 1.0880 \gt 1$$
Both are infeasible: no cycle length whatever can serve them. The remaining option — two
phases, two lanes per approach, permitted left turns — is therefore forced by the geometry
and the demand together, not merely preferred.
Balance the two lanes on each approach. With an inner left-through lane
(s = 2015) and an outer through-right lane (s = 2250), drivers distribute the through movement so
that both lanes are equally loaded in flow-ratio terms. Writing \(x\) for the through flow that uses
the inner lane,
$$\frac{q_L + x}{s_{LT}} = \frac{q_T - x + q_R}{s_{TR}} \;\Longrightarrow\;
x = \frac{s_{LT}(q_T+q_R) - s_{TR}\,q_L}{s_{LT}+s_{TR}}$$
On the north approach \(x = 438.86\) veh/h, so the inner lane carries 705.53 veh/h and the outer
787.81 veh/h, and both give the same flow ratio \(y_N = 0.3501\). Repeating for the other three
approaches gives \(y_S = 0.3392\), \(y_E = 0.2876\) and \(y_W = 0.2642\).
Critical movements and the sum of flow ratios. Each phase is governed by
its heavier approach — and it is the flow ratio, not the volume, that decides:
$$Y = \max(y_N, y_S) + \max(y_E, y_W) = 0.3501 + 0.2876 = \boxed{0.6378}$$
so the north and east approaches are critical. The total lost time is
\(L = n(\ell + R) = 2(3.5 + 1.5) = 10.0\) s.
Webster’s optimum cycle. Substituting into
$$C_{o} = \frac{1.5L + 5}{1 - Y} = \frac{1.5(10.0)+5}{1-0.6378} = 55.21\ \text{s}$$
This is the cycle that minimises total intersection delay for the vehicle demand alone.
Pedestrian minimum — solved as an inequality, not evaluated once.
The table gives conflicting pedestrian volumes, so the design may be pedestrian-controlled. Each
phase must supply
$$G_{p} = 3.2 + \frac{L_{c}}{S_{p}} + 2.7\,\frac{N_{ped}}{W_{E}},
\qquad N_{ped} = \frac{v_{ped}\,C}{3600}$$
Because \(N_{ped}\) itself grows with the cycle, a one-shot check at \(C_o\) always passes and
always under-designs. Writing each phase’s green as its share of the available green,
\((y_i/Y)(C-L)\), and requiring that to cover \(G_p\) gives a linear inequality in C. Two
assumptions are declared under Note 2: a walking speed \(S_p = 1.2\) m/s (TAC/MUTCDC practice) and
an effective crosswalk width \(W_E = 4.0\) m, which places the calculation on the HCM wide-crosswalk
branch. The crosswalk each phase must clear is the one whose pedestrians walk parallel to
that phase’s vehicles, so the north–south phase clears the east and west legs across the
15 m east–west carriageway at 100 ped/h, and the east–west phase clears the north and
south legs at 235 ped/h. Solving gives \(C \ge 39.96\) s for the north–south phase and
\(C \ge 49.67\) s for the east–west phase, so the binding pedestrian cycle is 49.67 s.
Adopt the cycle. The design cycle is the larger of the two controls,
rounded up to the nearest 5 s:
$$C = 5\left\lceil \frac{\max(55.21,\ 49.67)}{5} \right\rceil = \boxed{60\ \text{s}}$$
The vehicle optimum governs here; the pedestrians are comfortably accommodated
inside a cycle chosen for the traffic.
Split the green. The green available for movement is
\(g_{tot} = C - L = 60 - 10 = 50.0\) s, divided in proportion to the critical flow ratios:
$$g_i = \frac{y_i}{Y}\,(C-L)
\;\Longrightarrow\; g_{NS} = \frac{0.3501}{0.6378}(50.0) = 27.45\ \text{s},
\quad g_{EW} = 22.55\ \text{s}$$
Adding back the 3.5 s of acceleration/deceleration lost time that is displayed as green gives
displayed greens of 30.95 s and 26.05 s, each followed by a 1.5 s all-red. The
timing closes exactly: \(27.45 + 22.55 + 2(3.5) + 2(1.5) = 60.0\) s.
Check the adopted timing against the pedestrians and against capacity.
At \(C = 60\) s the pedestrian intervals actually required are 16.83 s (north–south phase) and
18.34 s (east–west phase), against 27.45 s and 22.55 s of effective green: both pass, with
10.63 s and 4.21 s of slack. The critical degree of saturation is
$$x_{crit} = \frac{Y\,C}{C-L} = \frac{0.6378(60)}{50} = 0.7653$$
and this must reappear as q/c on both critical approaches — the critical north lane
has capacity \(s\,g/C = 2015(27.45)/60 = 921.9\) veh/h against 705.5 veh/h of demand, and the
critical east lane 757.3 against 579.5, giving \(q/c = 0.7653\) in both cases. That one line
validates the lane assignment, the flow ratios and the split together. Webster’s delay
formula gives 17.6 s/veh on the critical north lane and 21.1 s/veh on the critical east lane,
comfortably within the range expected of a well-timed two-phase signal.
Question 2: the adopted two-phase plan. Through movements are protected; left turns are permitted and filter through gaps in the opposing through stream. Each phase is followed by a 1.5 s all-red.
Question 2: the 60 s cycle. The pedestrian interval each phase must supply is shown against the effective green it actually receives; both clear with slack.
Question 2 — final results
Quantity
Value
Phasing system adopted
Two phases, permitted left turns, two lanes per approach (inner left-through, outer through-right)
Why not four phases / one shared lane
Y = 1.2392 and 1.0880 respectively, both > 1 — infeasible