NivaarExam PrepOfficial exam papers ↗

16-Civ-B10 Traffic Engineering · December 2019

Question 2 of 7: Webster signal design for a four-approach intersection

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Examinations, December 2019, 16-Civ-B10 Traffic Engineering. Three-hour duration, OPEN BOOK (any non-communicating calculator permitted). Seven questions on four pages, all of equal value at 20 marks each; the paper requires five solutions and marks only the first five as they appear in the answer book. Because the set is a study resource, all seven questions are solved here. The paper’s own Note 1 invites a clear statement of any assumptions made and Note 2 permits any required-but-not-given data to be assumed; every assumption used below is stated explicitly where it is introduced. Page 2 reproduces the AASHTO 2001 metric stopping-sight-distance table, whose footnote fixes the brake-reaction time at 2.5 s and the deceleration at 3.4 m/s2; Question 1 is built around it.

Reference texts.

Canadian context. These are Engineers Canada national examinations, so the answers are framed for Canadian practice: the TAC Geometric Design Guide for Canadian Roads and the MUTCDC are the governing documents and metric design controls are used throughout. Question 1 supplies the AASHTO 2001 metric table directly, so that table is used as printed — the TAC guide adopts the same 2.5 s / 3.4 m/s2 stopping model, so the two agree here. Lane widths, walking speed and crosswalk geometry follow TAC and MUTCDC practice.

Question 2: Webster signal design for a four-approach intersection (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Peak-hour approach volumes, conflicting pedestrian volumes and the peak-hour factor are tabulated on page 2; the saturation flows by lane type are tabulated on page 3. Every approach is 15 m wide curb to curb.

Approach (width)North (15 m)South (15 m)East (15 m)West (15 m)
Left turn (veh/h)200185200175
Through movement (veh/h)800750600550
Right turn (veh/h)120150120120
Conflicting pedestrians (ped/h)235235100100
Peak-hour factor0.750.750.750.75
Lane typeSaturation flow (vphpl)
Through3075
Through-right2250
Left1995
Left-through2015
Left-through-right2500

Find. An appropriate phasing system with its justification, the intersection geometry it implies, the optimum and adopted cycle length, and the green time given to each phase.

NORTH approach SOUTH approach WEST approach EAST approach 15 m (4 at 3.5 m + 1.0 m median) 15 m (4 at 3.5 m + 1.0 m median) Conflicting pedestrian volumes N leg: 235 ped/h across 15 m S leg: 235 ped/h across 15 m E leg: 100 ped/h across 15 m W leg: 100 ped/h across 15 m Each approach: 2 lanes inner = left + through (s = 2015) outer = through + right (s = 2250)
Question 2: adopted intersection geometry. Each 15 m approach is four 3.5 m lanes plus a 1.0 m median, i.e. two lanes per approach — an inner left-through lane and an outer through-right lane. Left turns are permitted (unprotected).

Approach. Convert the hourly volumes to peak-flow rates, settle the geometry from the stated width, price the candidate phasing plans against the sum of flow ratios before choosing one, balance the two lanes on each approach so both carry the same flow ratio, form Webster’s optimum cycle, test it against the pedestrian requirement of each phase, adopt the larger, and split the available green in proportion to the critical flow ratios.

  1. Peak-flow rates. The peak-hour factor converts an hourly volume to the flow rate that the signal must actually serve within the peak fifteen minutes, $$q = \frac{V}{\text{PHF}}$$ With PHF = 0.75 throughout, every movement is divided by 0.75. The north approach, for example, becomes 266.67 left, 1066.67 through and 160.00 right, a total of 1493.33 veh/h; south, east and west come to 1446.67, 1226.67 and 1126.67 veh/h respectively. All subsequent arithmetic uses these flow rates, never the raw volumes.
  2. Geometry implied by the 15 m width. The "(Width)" entry in the volume table is the full curb-to-curb width shared by both directions. At the TAC standard 3.5 m lane, 15 m is four lanes plus a 1.0 m median, i.e. two lanes per approach. Reading 15 m as a one-direction width would imply four lanes each way carrying only about 300 veh/h per lane, which no signal design would ever produce. This is declared as an assumption under the paper’s Note 1.
  3. Price the candidate phasing plans before choosing one. "Determine an appropriate phasing system" asks for the justification, not just the plan, so each option is tested against the sum of critical flow ratios \(Y = \sum y_i\), which must stay below 1 for any timing to exist. A four-phase plan with exclusive left-turn bays leaves one through-right lane per approach carrying the whole through-plus-right demand, giving $$Y_{4} = 0.1337 + 0.5452 + 0.1337 + 0.4267 = 1.2392 \gt 1$$ A two-phase plan with one shared left-through-right lane per approach (s = 2500) gives $$Y_{1\text{-lane}} = 0.5973 + 0.4907 = 1.0880 \gt 1$$ Both are infeasible: no cycle length whatever can serve them. The remaining option — two phases, two lanes per approach, permitted left turns — is therefore forced by the geometry and the demand together, not merely preferred.
  4. Balance the two lanes on each approach. With an inner left-through lane (s = 2015) and an outer through-right lane (s = 2250), drivers distribute the through movement so that both lanes are equally loaded in flow-ratio terms. Writing \(x\) for the through flow that uses the inner lane, $$\frac{q_L + x}{s_{LT}} = \frac{q_T - x + q_R}{s_{TR}} \;\Longrightarrow\; x = \frac{s_{LT}(q_T+q_R) - s_{TR}\,q_L}{s_{LT}+s_{TR}}$$ On the north approach \(x = 438.86\) veh/h, so the inner lane carries 705.53 veh/h and the outer 787.81 veh/h, and both give the same flow ratio \(y_N = 0.3501\). Repeating for the other three approaches gives \(y_S = 0.3392\), \(y_E = 0.2876\) and \(y_W = 0.2642\).
  5. Critical movements and the sum of flow ratios. Each phase is governed by its heavier approach — and it is the flow ratio, not the volume, that decides: $$Y = \max(y_N, y_S) + \max(y_E, y_W) = 0.3501 + 0.2876 = \boxed{0.6378}$$ so the north and east approaches are critical. The total lost time is \(L = n(\ell + R) = 2(3.5 + 1.5) = 10.0\) s.
  6. Webster’s optimum cycle. Substituting into $$C_{o} = \frac{1.5L + 5}{1 - Y} = \frac{1.5(10.0)+5}{1-0.6378} = 55.21\ \text{s}$$ This is the cycle that minimises total intersection delay for the vehicle demand alone.
  7. Pedestrian minimum — solved as an inequality, not evaluated once. The table gives conflicting pedestrian volumes, so the design may be pedestrian-controlled. Each phase must supply $$G_{p} = 3.2 + \frac{L_{c}}{S_{p}} + 2.7\,\frac{N_{ped}}{W_{E}}, \qquad N_{ped} = \frac{v_{ped}\,C}{3600}$$ Because \(N_{ped}\) itself grows with the cycle, a one-shot check at \(C_o\) always passes and always under-designs. Writing each phase’s green as its share of the available green, \((y_i/Y)(C-L)\), and requiring that to cover \(G_p\) gives a linear inequality in C. Two assumptions are declared under Note 2: a walking speed \(S_p = 1.2\) m/s (TAC/MUTCDC practice) and an effective crosswalk width \(W_E = 4.0\) m, which places the calculation on the HCM wide-crosswalk branch. The crosswalk each phase must clear is the one whose pedestrians walk parallel to that phase’s vehicles, so the north–south phase clears the east and west legs across the 15 m east–west carriageway at 100 ped/h, and the east–west phase clears the north and south legs at 235 ped/h. Solving gives \(C \ge 39.96\) s for the north–south phase and \(C \ge 49.67\) s for the east–west phase, so the binding pedestrian cycle is 49.67 s.
  8. Adopt the cycle. The design cycle is the larger of the two controls, rounded up to the nearest 5 s: $$C = 5\left\lceil \frac{\max(55.21,\ 49.67)}{5} \right\rceil = \boxed{60\ \text{s}}$$ The vehicle optimum governs here; the pedestrians are comfortably accommodated inside a cycle chosen for the traffic.
  9. Split the green. The green available for movement is \(g_{tot} = C - L = 60 - 10 = 50.0\) s, divided in proportion to the critical flow ratios: $$g_i = \frac{y_i}{Y}\,(C-L) \;\Longrightarrow\; g_{NS} = \frac{0.3501}{0.6378}(50.0) = 27.45\ \text{s}, \quad g_{EW} = 22.55\ \text{s}$$ Adding back the 3.5 s of acceleration/deceleration lost time that is displayed as green gives displayed greens of 30.95 s and 26.05 s, each followed by a 1.5 s all-red. The timing closes exactly: \(27.45 + 22.55 + 2(3.5) + 2(1.5) = 60.0\) s.
  10. Check the adopted timing against the pedestrians and against capacity. At \(C = 60\) s the pedestrian intervals actually required are 16.83 s (north–south phase) and 18.34 s (east–west phase), against 27.45 s and 22.55 s of effective green: both pass, with 10.63 s and 4.21 s of slack. The critical degree of saturation is $$x_{crit} = \frac{Y\,C}{C-L} = \frac{0.6378(60)}{50} = 0.7653$$ and this must reappear as q/c on both critical approaches — the critical north lane has capacity \(s\,g/C = 2015(27.45)/60 = 921.9\) veh/h against 705.5 veh/h of demand, and the critical east lane 757.3 against 579.5, giving \(q/c = 0.7653\) in both cases. That one line validates the lane assignment, the flow ratios and the split together. Webster’s delay formula gives 17.6 s/veh on the critical north lane and 21.1 s/veh on the critical east lane, comfortably within the range expected of a well-timed two-phase signal.
Phase A — North / South g = 27.5 s, displayed green 31.0 s, all-red 1.5 s pedestrians cross the 15 m E–W street Phase B — East / West g = 22.5 s, displayed green 26.0 s, all-red 1.5 s pedestrians cross the 15 m N–S street solid = protected through movement  dashed = permitted (unprotected) left turn
Question 2: the adopted two-phase plan. Through movements are protected; left turns are permitted and filter through gaps in the opposing through stream. Each phase is followed by a 1.5 s all-red.
Question 2: adopted timing, C = 60 s (vehicle-governed) green 31.0 s green 26.0 s phase A (N/S) = 32.5 s phase B (E/W) = 27.5 s narrow red bands = 1.5 s all-red phase A clears the E–W street: 15 m crosswalk, 100 ped/h — interval needed 16.8 s, effective green available 27.5 s phase B clears the N–S street: 15 m crosswalk, 235 ped/h — interval needed 18.3 s, effective green available 22.5 s 0 10 20 30 40 50 60 time into the cycle (s)
Question 2: the 60 s cycle. The pedestrian interval each phase must supply is shown against the effective green it actually receives; both clear with slack.
Question 2 — final results
QuantityValue
Phasing system adoptedTwo phases, permitted left turns, two lanes per approach (inner left-through, outer through-right)
Why not four phases / one shared laneY = 1.2392 and 1.0880 respectively, both > 1 — infeasible
Critical flow ratiosNorth 0.3501, East 0.2876
Sum of critical flow ratios Y0.6378
Total lost time L10.0 s
Webster optimum cycle Co55.21 s
Pedestrian minimum cycle49.67 s (east–west phase governs)
Adopted cycle60 s (vehicle-governed)
Effective green, north–south / east–west27.45 s / 22.55 s
Displayed green, north–south / east–west30.95 s / 26.05 s, each + 1.5 s all-red
Critical degree of saturation xcrit0.7653
Average delay, critical north / east lane17.6 s/veh / 21.1 s/veh