16-Civ-B19 Foundation Engineering · December 2018
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Exams, December 2018 — 16-Civ-B19 Foundation Engineering. Three hours, OPEN BOOK (one textbook plus one hand-written 8.5″ × 11″ aid sheet, both sides). Five questions, all to be answered, all of equal weight (20 marks each, 100 marks total). Any non-communicating calculator is permitted. The paper mixes SI and US customary units question by question, so each answer below stays in the units the question is posed in.
Check: three conflicts in the printed paper, resolved as follows.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Piles are used whenever a shallow foundation cannot deliver adequate capacity, acceptable settlement, or adequate restraint at a reasonable depth. Six conditions cover almost all cases in practice.
Weak or compressible near-surface soil. When the upper strata are soft clay, loose silt, peat or fill, a spread footing large enough to keep the bearing pressure tolerable would be uneconomic or would still settle excessively. Piles transfer the load through the weak material to a competent bearing stratum — dense sand, till or bedrock — as end-bearing piles, or distribute it into deeper, stronger soil by shaft friction as friction piles. This is the dominant reason in the soft marine clays of the Fraser and St. Lawrence lowlands.
Large or concentrated structural loads. Heavily loaded columns of bridges, tall buildings and industrial plant deliver loads that would require footings so large they overlap. Piles concentrate the required resistance into a small plan area.
Horizontal, inclined or uplift loading. Retaining structures, transmission towers, anchor blocks, sheet-pile bulkheads and bridge abutments carry lateral thrust or net tension. Vertical and battered piles resist horizontal load in bending and pull-out in shaft friction; a spread footing resists these only through base friction and self-weight.
Expansive, collapsible or frost-susceptible soils. Where the active zone of a swelling clay, a collapsible loess or the seasonal frost zone would move a shallow footing, piles carry the structure below that zone. In much of Canada the design frost depth and, in the North, the permafrost active layer set that requirement directly.
Scour and erosion. Bridge piers and marine structures must remain supported after the design scour event has removed several metres of bed material, so the foundation must be embedded well below the predicted scour line — a depth only piles or caissons reach economically.
Fluctuating water table, buoyancy and dynamic loading. Structures subject to uplift from a rising groundwater table, or to vibration and machine or seismic loading, benefit from the tension capacity and the stiffness that piles provide; piles also allow construction over water without dewatering. A related case is compaction piling, where the piles are driven principally to densify a loose granular deposit.
Given.
| Quantity | Symbol | Value |
|---|---|---|
| Outside diameter of pipe pile | $D$ | 400 mm = 0.400 m |
| Wall thickness | $t$ | 6.25 mm |
| Embedded length | $L$ | 20 m |
| Upper clay, 0–10 m | $c_{u(1)}$ | 30 kN/m² ($\gamma = 18$ kN/m³) |
| Lower clay, 10–20 m | $c_{u(2)}$ | 100 kN/m² ($\gamma_{sat} = 19.6$ kN/m³) |
| Water table | — | 5 m below ground |
| Factor of safety | $FS$ | 4 |
Find. (I) the net point bearing capacity $Q_p$, (II) the skin (shaft) resistance $Q_s$, and (III) the net allowable pile capacity at $FS = 4$.
Approach. This is an undrained, total-stress problem in clay, so use $N_c^{*} = 9$ for the point and the $\alpha$-method for the shaft, with $\alpha$ read from the chart of adhesion factor against undrained cohesion supplied on the last page of the exam.
| Result | Value |
|---|---|
| Point area (plugged, outside diameter) | $A_p = 0.1257$ m² |
| Perimeter | $p = 1.2566$ m |
| I — net point bearing capacity, $Q_p$ | 113.1 kN |
| Shaft, 0–10 m ($\alpha_1 = 1.00$) | 377.0 kN |
| Shaft, 10–20 m ($\alpha_2 = 0.50$) | 628.3 kN |
| II — skin resistance, $Q_s$ | 1 005.3 kN |
| Ultimate capacity, $Q_u$ | 1 118.4 kN |
| III — net allowable capacity, $FS = 4$ | 279.6 kN |
Check: the pile is assumed to plug. A driven closed-end or plugged pipe pile mobilises the full circular toe area, which is the standard assumption for this problem and the one used above. If the pile were driven open-ended and did not plug, only the steel annulus would bear: $A_{p} = \frac{\pi}{4}\left[0.400^2 - 0.3875^2\right] = 0.0077\ \text{m}^2$, giving $Q_p = 7.0$ kN and $Q_{all} = 253.1$ kN — a 9 % reduction. Because the shaft dominates, the plugging assumption is not critical here, but it must be stated.