NivaarExam PrepOfficial exam papers ↗

16-Civ-B2 Advanced Structural Design · December 2013

Question 5 of 7: Plastic design of the steel frame and the welded corner at B

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Examinations, December 2013 — 98-Civ-B2 Advanced Structural Design, 3 hours, closed book (handbooks and textbooks permitted). Seven design questions of equal value; any five constitute a complete paper.

Reference texts. CSA S16:19 Design of Steel Structures; CISC Handbook of Steel Construction; CSA A23.3:19 Design of Concrete Structures (Clause 18 for prestressed concrete, Clause 17 of S16 for composite members); National Building Code of Canada 2020 for load combinations; Hibbeler, Structural Analysis, for the frame and continuous-beam analysis.

Design data printed on page 1. Concrete $f_c' = 30\ \text{MPa}$; structural steel $F_y = 350\ \text{MPa}$; reinforcing steel $f_y = 400\ \text{MPa}$. Prestressed concrete: $f_{ci}' = 35\ \text{MPa}$ at transfer, $f_c' = 50\ \text{MPa}$, modular ratio $n = 6$, $f_{ult} = 1750\ \text{MPa}$, $f_y = 1450\ \text{MPa}$, $f_{initial} = 1200\ \text{MPa}$, losses $= 240\ \text{MPa}$. Design in SI. All loads shown are unfactored.

Check: load factors. Page 1 states only that the printed loads are unfactored; it gives no dead/live split, so no code load combination can be assembled uniquely. Every load printed on Figures 1–4 is therefore factored by 1.5, and any self weight the solver itself introduces (the concrete frame, the prestressed girder, the steel sections) by 1.25, consistent with NBCC 2020 Table 4.1.3.2. State this assumption on the answer paper as page-1 Note 1 invites. The choice scales the magnitudes only — the collapse mechanisms, section classifications and interaction equations below are unaffected.

Check: section properties. Rolled-shape properties cannot be reproduced from first principles, so every steel member selected here is a welded three-plate I-section whose area, $I$, $Z$, $J$ and $C_w$ are computed from its plate dimensions and are therefore fully checkable. A candidate with the CISC Handbook would instead take the lightest rolled W-shape whose $Z_x$ (or $M_r$, $C_r$) exceeds the value derived in each question; the design logic is identical.

Question 5: Plastic design of the steel frame and the welded corner at B (12 + 8 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

QuantityValue
Framepinned bases A and D, height $h = 10\ \text{m}$, span $L = 15\ \text{m}$
Factored loads$H = 120\ \text{kN}$ at B; $900\ \text{kN}$ at B, $750\ \text{kN}$ at mid-span, $900\ \text{kN}$ at C
Steel$F_y = 350\ \text{MPa}$, $\phi = 0.90$
Uniformityall members share one $M_p$
Lateral supportat B, mid-span and C only — a 7.5 m unbraced length

Find. The required plastic moment, a section that supplies it, and the details of the welded knee at B.

Approach. Enumerate the independent mechanisms, combine them to find the least upper bound, confirm the answer by a lower-bound equilibrium check, then size a Class 1 welded I-section and design the corner to transfer the member plastic moment.

  1. Part (a) — independent mechanisms. A pin-based portal has four reaction components and three equations of equilibrium, so it is indeterminate to the first degree and collapses when two hinges form. The two independent mechanisms are$$\text{beam: } P_f\frac{L}{2}\theta = 4M_p\theta \Rightarrow M_p = \frac{750(7.5)}{4} = 1406.25\ \text{kN}\cdot\text{m}$$$$\text{sway: } Hh\theta = 2M_p\theta \Rightarrow M_p = \frac{120(10)}{2} = 600\ \text{kN}\cdot\text{m}$$The 900 kN loads at B and C do no work in either mechanism — they sit directly over the columns and translate horizontally in the sway mechanism, vertically not at all in the beam mechanism.
  2. Combine and cancel the hinge at B. Adding the two mechanisms makes the hinge rotations at B equal and opposite, so that hinge disappears and $2M_p\theta$ of internal work is recovered. The remaining hinges are at mid-span and at C, each rotating $2\theta$:$$P_f\frac{L}{2}\theta + Hh\theta = 4M_p\theta \Rightarrow \boxed{M_p = \frac{750(7.5) + 120(10)}{4} = 1706.25\ \text{kN}\cdot\text{m}}$$This is 21 % above the beam mechanism alone and nearly three times the sway mechanism; stopping at the independent mechanisms would under-design the frame badly.
  3. ADBCO900 kN750 kN900 kN120 kN10 m7.5 m7.5 m15 mhingehingecombined beam + sway mechanism (2 hinges)Question 5 — governing collapse mechanism
    The governing combined mechanism. The hinge at B cancels, leaving hinges at mid-span and at the top of the leeward column.
  4. Confirm by the lower-bound theorem. An upper-bound mechanism is only a bound until a statically admissible moment field is exhibited. Vertical equilibrium and moments about A give $V_D = 1355$ and $V_A = 1195\ \text{kN}$ (these are determinate). Setting the moment at C equal to $M_p$ fixes $H_D = -M_p/h = -170.6\ \text{kN}$, hence $H_A = -120 - H_D = 50.6\ \text{kN}$, and$$M_{mid} = 7.5V_A - hH_A - 900(7.5) = 1706.25\ \text{kN}\cdot\text{m} = M_p\ \checkmark$$$$M_B = |hH_A| = 506.25\ \text{kN}\cdot\text{m} < M_p\ \checkmark$$Both hinge sections reach $M_p$, nowhere is $M_p$ exceeded, and equilibrium holds, so $1706.25\ \text{kN}\cdot\text{m}$ is the exact collapse value, not merely an upper bound.
  5. Select the section. The requirement is $Z \ge M_p/(\phi F_y) = 1706.25\times10^6/(0.9 \times 350) = 5.42\times10^6\ \text{mm}^3$. A welded I with a $710 \times 14$ web and $280 \times 20$ flanges ($d = 750\ \text{mm}$) gives$$Z = b t_f(d - t_f) + \frac{t_wh_w^2}{4} = 5.852\times10^6\ \text{mm}^3, \qquad \boxed{M_r = \phi ZF_y = 1843.5 > 1706.25\ \text{kN}\cdot\text{m}}$$Both elements are Class 1, as plastic design requires: the flange ratio is $(280-14)/2/20 = 6.65 < 145/\sqrt{350} = 7.75$ and the web ratio is $710/14 = 50.7 < 1100/\sqrt{350} = 58.8$. The member weighs $166\ \text{kg/m}$.
  6. 750280web 710 × 14, flanges 280 × 20 (mm)Z = 5.85 × 10⁶ mm³  •  Class 1  •  166 kg/mPlastic-design member — welded I
    Welded section supplying the required plastic moment.
  7. Bracing at the plastic hinges (S16 Cl 13.7). A hinge must be able to rotate without buckling laterally, so the code limits the laterally unsupported length adjacent to it to $L_{cr} = (25\,000 + 15\,000\kappa)r_y/F_y$. With $r_y = \sqrt{I_y/A} = 58.9\ \text{mm}$ and $\kappa = 0$ at the mid-span hinge,$$L_{cr} = \frac{25\,000(58.9)}{350} = 4207\ \text{mm}$$The stated bracing at load points and joints leaves $7500\ \text{mm}$ unbraced, which is not enough. Add lateral bracing at the quarter points of BC, reducing the unbraced length to $3750\ \text{mm} < 4207\ \text{mm}$. This is a real design finding, not a formality: without it the frame would fail by lateral torsional buckling before the assumed mechanism could develop, and the plastic analysis above would be invalid.
  8. Part (b) — forces at the welded corner. A plastic-design connection must develop the member rather than merely the applied moment, because the hinge is expected to rotate. The flange force at full yield is$$T_f = b t_f F_y = 280(20)(350) = 1960\ \text{kN}$$Take the flanges continuous through the joint with complete-joint-penetration groove welds: a CJP weld with matching electrode develops the full plate, so no weld sizing calculation is needed, and it is the only detail that reliably survives hinge rotation. The web is joined by fillet welds sized for the web shear.
  9. Web panel shear and the diagonal stiffener. The knee panel must carry the whole member moment as a shear couple across a panel of depth $d - t_f = 730\ \text{mm}$:$$V_{panel} = \frac{M_p}{d - t_f} = \frac{2048.3\times10^3}{730} = 2805.9\ \text{kN}$$while the unstiffened panel resists only$$V_r = 0.55\phi d_c w F_y = 0.55(0.9)(730)(14)(350) = 1770.6\ \text{kN}$$The panel is 58 % short, so a diagonal stiffener is required. Across a square panel the diagonal runs at $45^{\circ}$, so it carries$$F_{diag} = \frac{2805.9 - 1770.6}{\cos 45^{\circ}} = 1464.1\ \text{kN}, \qquad A_{req} = \frac{F_{diag}}{\phi F_y} = 4648\ \text{mm}^2$$$$\boxed{\text{provide two }200 \times 12\ \text{plates } (4800\ \text{mm}^2), \text{ one each side of the web}}$$Add horizontal continuity plates opposite each beam flange to carry the 1960 kN flange force into the column web, groove welded to the column flanges.
beam BCcolumn ABdiagonal stiffener2 – 200 × 12 plates, one each sidepanel shear demand 2805.9 kNweb panel resistance 1770.6 kNQuestion 5(b) — welded corner at Bflanges joined by CJP groove welds; web fillet welded
Welded corner at B: CJP flange welds, continuity plates and a diagonal stiffener sized for the panel shear deficit.
ItemResult
Beam mechanism$M_p = 1406.25\ \text{kN}\cdot\text{m}$
Sway mechanism$M_p = 600\ \text{kN}\cdot\text{m}$
Combined (governs)$M_p = 1706.25\ \text{kN}\cdot\text{m}$
Lower-bound check$M_{mid} = M_C = M_p$, $M_B = 506.25 < M_p$ — exact
Sectionwelded I, web $710 \times 14$, flanges $280 \times 20$, $d = 750\ \text{mm}$
Plastic modulus$Z = 5.852\times10^6\ \text{mm}^3$, Class 1
Moment resistance$M_r = 1843.5\ \text{kN}\cdot\text{m}$
Hinge bracing$L_{cr} = 4207\ \text{mm}$ — brace at quarter points (3750 mm)
Corner: flange force$1960\ \text{kN}$, CJP groove welds
Corner: panel sheardemand $2805.9$ vs resistance $1770.6\ \text{kN}$
Diagonal stiffener$2 - 200 \times 12$ plates ($4800 > 4648\ \text{mm}^2$)