NivaarExam PrepOfficial exam papers ↗

16-Civ-B2 Advanced Structural Design · May 2015

Question 2 of 7: Welded corner at joint B and the beam-column check

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 98-Civ-B2 Advanced Structural Design, National Exams May 2015 — 3 hours, closed book (textbooks and design handbooks permitted, no notes). Seven design questions of 20 marks each; any five constitute a complete paper, so all seven are solved here. All loads shown on the figures are unfactored. Page 1 supplies the design data used throughout: concrete f′c = 30 MPa, structural steel Fy = 350 MPa, reinforcing steel fy = 400 MPa; for the prestressed member f′ci = 35 MPa, f′c = 50 MPa, n = 6, fpu = 1750 MPa, fpy = 1450 MPa, initial stress 1200 MPa and total losses 240 MPa.

Reference texts. CSA S16:19 Design of Steel Structures; CISC Handbook of Steel Construction, 12th ed.; CSA A23.3:19 Design of Concrete Structures; CSA S6:19 Canadian Highway Bridge Design Code; NBCC 2020 Part 4; Hibbeler, Structural Analysis, 10th ed. (plastic analysis, Ch. 18).

Check — load factors. Page 1 states only that “all loads shown are unfactored” and gives no dead/live split. Throughout this paper the applied loads on the figures are factored by 1.5, and any self weight introduced by the solution itself (the plate girder, the deck, the prestressed beam, the reinforced-concrete frame) by 1.25, consistent with NBCC 2020 Table 4.1.3.2. The mechanisms, section classifications and interaction equations are independent of that choice — only the magnitudes change.

Question 2: Welded corner at joint B and the beam-column check (10 + 5 + 2 + 3 = 20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. The sections selected in Question 1 — beam W410×67 (d = 410, flange 179 × 14.4, web 8.8) framing into column W530×92 (d = 533, flange 209 × 15.6, web 10.2) — and the collapse actions at that joint: a beam hinge moment of 375 kN·m, a beam end shear of 150 kN and a column shear of 56.2 kN. Both columns carry Cf = 750 kN. Electrodes are E49xx (Xu = 490 MPa), φw = 0.67.

Find. A welded knee detail that can deliver the beam’s plastic moment into the column, and the CSA S16 Cl 13.8 verification of AB and DF as beam-columns.

Approach. Resolve the beam moment into a flange couple, check the column panel zone in shear and the column web opposite each flange, add stiffeners for the shortfall, size the welds; then run the three Cl 13.8.2 interaction checks on each column using the collapse moments and the bracing implied by the paper’s note.

diagonal stiffener 2–90×12transverse stiffeners 2–90×12beam W410×67column W530×92CJP groove weld, both flanges6 mm fillet, web, both sidesT = C = 948 kN flange force
Welded knee at joint B — complete-joint-penetration groove welds to the beam flanges, fillet weld to the web, transverse stiffeners opposite each flange and a diagonal stiffener across the panel.
  1. Part (a) — convert the beam moment into a flange couple. At the collapse moment the beam delivers $$T = C = \frac{M_f}{d_b - t_{fb}} = \frac{375\times10^6}{410 - 14.4} = 948\ \text{kN}$$ Because this is a plastic-design joint, the connection is proportioned for the beam’s full plastic moment rather than the demand, so that the hinge forms in the member and not in the connection: $$T_{cap} = \frac{F_y Z_x}{d_b - t_{fb}} = \frac{350(1.339\times10^6)}{395.6} = 1185\ \text{kN}$$
  2. Check the panel zone in shear. The horizontal shear carried by the column web within the knee is the flange force less the column shear: $$V_f = 1185 - 56.2 = 1128\ \text{kN},\qquad V_r = 0.55\phi F_y w_c d_c = 0.55(0.9)(350)(10.2)(533)/10^3 = 942\ \text{kN}$$ The web alone is 187 kN short, so a diagonal stiffener is required across the panel.
  3. Size the diagonal stiffener. The diagonal runs from the re-entrant corner to the outer corner, at $\theta = \tan^{-1}(410/533) = 37.6^{\circ}$ to the horizontal, so the axial force needed to supply 187 kN of horizontal shear is $$F_d = \frac{187}{\cos 37.6^{\circ}} = 235\ \text{kN},\qquad A_{req} = \frac{235\times10^3}{0.9(350)} = 747\ \text{mm}^2$$ Provide a pair of 90 × 12 mm plates ($A = 2160\ \text{mm}^2$), one each side of the column web.
  4. Transverse (continuity) stiffeners. Opposite each beam flange the column web must carry the concentrated force. Taking a bearing length $N = t_{fb} + 2(8) = 30$ mm, CSA S16 Cl 14.3.2 gives $$B_r = \phi_{bi} w (N + 10t)F_y = 0.80(10.2)(30 + 156)(350)/10^3 = 531\ \text{kN} < 1185\ \text{kN}$$ so stiffeners must take the balance, $1185 - 531 = 654$ kN, requiring $A = 654\times10^3/(0.9\times350) = 2076\ \text{mm}^2$. The same pair of 90 × 12 mm plates ($A = 2160\ \text{mm}^2$) is used opposite both flanges, giving one consistent plate size for the whole knee.
  5. Weld the joint. Each beam flange is joined to the column with a complete-joint-penetration groove weld, which develops the flange in tension and needs no separate calculation. The beam web is fillet welded both sides; a 6 mm fillet in E49xx over the 381 mm clear web depth gives $$V_r = 2(0.67)\phi_w (0.707 \times 6)(X_u)L = 2(0.67)(0.67)(4.242)(490)(381)/10^3 = 711\ \text{kN} \gg 150\ \text{kN}$$ so 6 mm fillets both sides are ample. The stiffeners are fillet welded to the web and to the flanges they bear against, and the re-entrant corner is given a generous radius to avoid a notch at the point of highest strain.
  6. Part (b) — actions on the two beam-columns. From the collapse state of Question 1, both columns carry $C_f = 750$ kN. Column AB has end moments 74.3 and 375 kN·m; column DF has 375 kN·m at D, 150.4 kN·m at E and 434.3 kN·m at F. The paper’s note “lateral support is provided where necessary” is taken as bracing at mid-height of each column, so $K_yL_y = 4000$ mm and the unbraced lengths for lateral-torsional buckling are also 4000 mm.
  7. Compression resistances (W530×92). With $A = 11\,639\ \text{mm}^2$, $r_x = 216.2$ mm and $r_y = 45.2$ mm, $$\lambda = \frac{KL}{r}\sqrt{\frac{F_y}{\pi^2E}},\qquad C_r = \phi A F_y\left(1+\lambda^{2n}\right)^{-1/n},\ n = 1.34$$ giving $\lambda_x = 0.493 \Rightarrow C_{rx} = 3303$ kN over the 8 m in-plane length and $\lambda_y = 1.178 \Rightarrow C_{ry} = 1822$ kN over the 4 m braced length. The cross-sectional axial resistance is $\phi AF_y = 3666$ kN and $M_{rx} = \phi Z F_y = 733.6\ \text{kN}\cdot\text{m}$. Because the frame is unbraced against sway, $U_{1x} = 1.0$ is used in all three checks (Cl 13.8.4).
  8. Column AB — the three Cl 13.8.2 checks. $$\text{(a) cross-section: } \frac{750}{3666} + \frac{0.85(375)}{733.6} = 0.205 + 0.434 = 0.639$$ $$\text{(b) overall member: } \frac{750}{1822} + 0.434 = 0.412 + 0.434 = 0.846$$ For (c) the worst segment is the upper 4 m, whose moments 150.4 and 375 kN·m give $\kappa = -0.401$, $\omega_2 = 1.377$, $M_u = 1182$ kN·m and hence $M_r = 680.8$ kN·m, so $$\text{(c) lateral-torsional: } \frac{750}{3303} + \frac{0.85(375)}{680.8} = 0.227 + 0.468 = 0.695$$ Governing ratio 0.846.
  9. Column DF. The same resistances apply, with the larger moment 434.3 kN·m at the base: $$\text{(a) } \frac{750}{3666} + \frac{0.85(434.3)}{733.6} = 0.708,\qquad \text{(b) } \frac{750}{1822} + 0.503 = 0.915$$ For (c) the lower segment E–F is bent in double curvature, $\kappa = +0.346$, $\omega_2 = 2.150$, $M_u = 1845$ kN·m and $M_r = 733.6$ kN·m (the full plastic value), so $$\text{(c) } \frac{750}{3303} + \frac{0.85(434.3)}{733.6} = 0.227 + 0.503 = 0.730$$ Governing ratio 0.915.
  10. Verdict. Both members satisfy every Cl 13.8.2 check, DF with the smaller margin because the 60 kN horizontal load is applied to that column. The sections chosen in Question 1 are therefore adequate as beam-columns, and no change is needed. Had the bracing assumption been relaxed to a single 8 m unbraced length, $C_{ry}$ would fall to about 760 kN and check (b) would rise past 1.4 — which is precisely why the paper permits lateral support to be assumed where necessary.
ResultValue
Beam flange force at the knee (capacity design)1185 kN
Panel-zone shear demand / web resistance1128 kN / 942 kN
Diagonal stiffener2 – 90 × 12 mm plates
Transverse stiffeners opposite each flange2 – 90 × 12 mm plates
WeldsCJP groove to both flanges; 6 mm fillet both sides of the web
Column AB, governing Cl 13.8.2 ratio0.846 — adequate
Column DF, governing Cl 13.8.2 ratio0.915 — adequate