16-Civ-B2 Advanced Structural Design · December 2019
Question 7 of 7: Prestressed beam section for the Figure 4 loading
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 16-Civ-B2 Advanced Structural Design, December 2019, 3 hours, closed book (handbooks and textbooks permitted). Seven design questions of 20 marks each in three parts — Part A (steel, do two of three), Part B (reinforced concrete, do two of three) and Part C (prestressed concrete, do question C1); five solutions constitute a complete paper. All seven are solved here, because the set is a study resource rather than an examination script.
Design data given on page 1. Solutions to the latest CAN/CSA S16 (steel), CAN/CSA A23.3 (concrete) and CAN/CSA O86 (timber). All loads shown on the figures are unfactored. Structural steel is G40.21 300W unless noted, so $F_y = 300\ \text{MPa}$; reinforcement is 400W, so $f_y = 400\ \text{MPa}$. Load combinations follow NBCC: $1.25D + 1.5L$.
Reference texts. CISC, Handbook of Steel Construction, 12th ed. (CSA S16-19 with commentary) — Parts 1, 4 and 5; Kulak & Grondin, Limit States Design in Structural Steel, 10th ed.; MacGregor & Bartlett, Reinforced Concrete: Mechanics and Design (Canadian edition); CAC, Concrete Design Handbook, 4th ed. (A23.3-14 with explanatory notes); Collins & Mitchell, Prestressed Concrete Structures; CPCI, Design Manual, 5th ed.; NBCC 2015 Part 4 for loads and load combinations.
Page 3 of this paper carries all four figures and nothing else, and the machine-readable extraction of that page is unreliable. The paper draws a pin as a triangle and a roller as a circle (Figures 1 and 4) but draws plain hatched ground with no symbol at A and F in Figure 2 and at A and E in Figure 3; those four bases are therefore taken as built in (fully fixed). Figure 2 dimensions the right-hand column as 4 m + 4 m but leaves the left-hand column undimensioned: it is drawn between the same beam line and the same base line, so it is taken as 8 m. Figure 3 gives no dead/live split for its four point loads, so the single factor 1.5 is applied to them.
Question C1: Prestressed beam section for the Figure 4 loading (20 marks)
CSA-certified precast shop — pretensioned, not post-tensioned
Find. A pretensioned section and strand layout; the extreme-fibre stresses verified at transfer and in service against the Clause 18.3 limits; the ultimate moment resistance including the Clause 18.8.2 cracking rule; and the long-term deflection under dead load.
Approach. Recognise that the member has reversing moment — sagging in the span, hogging over the support — so place the strands symmetrically about the centroid; then compute the moments at each stage, estimate the losses component by component, verify the fibre stresses, check the ultimate limit state including $1.2M_{cr}$, and finish with the creep-amplified dead-load deflection.
Recognise the governing feature: the moment reverses. The 1.0 m cantilever puts tension in the top fibre over the support while the span puts tension in the bottom fibre. A single eccentric tendon group cannot precompress both faces, and a 4 m precast member is far too short to harp. The correct response is to place the strands symmetrically about the centroid, giving $e = 0$, so the prestress is pure uniform precompression that benefits both faces equally and produces no camber.
Choose a trial section and strand pattern. Take a $150 \times 400\ \text{mm}$ rectangle with two 9.5 mm strands 50 mm from the top and two 50 mm from the bottom: $$A = 60\,000\ \text{mm}^2, \quad Z = \frac{bh^2}{6} = 4.00\times10^6\ \text{mm}^3, \quad I_g = 8.00\times10^8\ \text{mm}^4, \quad A_p = 4(55) = 220\ \text{mm}^2$$ Two strands per row fit the 150 mm width with 25 mm cover: the 70 mm clear spacing exceeds the $4d_b = 38\ \text{mm}$ minimum of Clause 18.7. Self weight is $0.150(0.400)(24) = 1.44\ \text{kN/m}$.
Compute the prestress force. $$\begin{aligned} f_{pi} &= 0.70 f_{pu} = 0.70(1860) = 1302\ \text{MPa} \\ P_i &= f_{pi} A_p = 1302(220)/10^3 = 286.4\ \text{kN} \end{aligned}$$ and since $e = 0$ the concrete stress at the strand level is simply $f_{cir} = P_i/A = 286\,440/60\,000 = 4.77\ \text{MPa}$, uniform over the section.
Estimate the losses component by component. $$\begin{aligned} \text{elastic shortening} &: \Delta f_{ES} = \frac{E_p}{E_{ci}} f_{cir} = \frac{200\,000}{24\,648}(4.77) = 38.7\ \text{MPa} \\ \text{shrinkage} &: \Delta f_{SH} = \varepsilon_{sh} E_p = 400\times10^{-6}(200\,000) = 80.0\ \text{MPa} \\ \text{creep} &: \Delta f_{CR} = k_{cr}\frac{E_p}{E_c} f_{cir} = 2.0\frac{200\,000}{28\,460}(4.77) = 67.1\ \text{MPa} \\ \text{relaxation (low-relax)} &: \Delta f_{RE} = 0.025 f_{pi} = 32.6\ \text{MPa} \end{aligned}$$ The total is $218.4\ \text{MPa}$, i.e. 16.8 per cent of $f_{pi}$. Adopt 20 per cent as the design value, which is conservative in the direction that matters: a lower effective prestress leaves less compression to offset the service tension.
State the effective prestress. $$\begin{aligned} P_e &= 0.80 P_i = 229.2\ \text{kN} \\ f_{cpe} &= \frac{P_e}{A} = \boxed{3.82\ \text{MPa}}\ \text{uniform compression} \end{aligned}$$ with $f_{cpi} = 4.77\ \text{MPa}$ at transfer.
Compute the moments at each stage. Using $M_B = wa^2/2 + Pa$ over the support and $R_A = (wL^2/2 - M_B)/L$ with $M_{sag} = R_A^2/2w$ in the span: $$\begin{aligned} \text{transfer (self weight alone)} &: M_B = 0.72, \quad M_{sag} = 1.28 \\ \text{dead load in service} &: M_B = 4.72 \\ \text{full service load} &: M_B = 8.72, \quad M_{sag} = 3.54 \end{aligned}$$ all in kN·m. The hogging moment over B is the largest at every stage, which is unusual for a simply supported member and is entirely due to the tip load on the 1.0 m cantilever.
Verify the transfer stresses (Clause 18.3.1). At release only the self weight acts. With $e = 0$ the stress is the uniform precompression plus the flexural term $M/Z$: $$\begin{aligned} f_{top} &= -4.77 + \frac{0.72\times10^6}{4.00\times10^6} = -4.59\ \text{MPa} \\ f_{bot} &= -4.77 - 0.18 = -4.95\ \text{MPa} \end{aligned}$$ against limits of $0.25\sqrt{f'_{ci}} = 1.37\ \text{MPa}$ tension and $0.60f'_{ci} = 18.0\ \text{MPa}$ compression. Both fibres are in compression, so there is no tension to check and the compression is at 28 per cent of its limit ✓
Verify the service stresses (Clause 18.3.2). After losses, under full service load: $$\begin{aligned} \text{top fibre over B} &: -3.82 + 2.18 = -1.64\ \text{MPa} \\ \text{bottom fibre at mid-span} &: -3.82 - 0.89 = -4.70\ \text{MPa} \\ \text{top fibre at mid-span} &: -3.82 + 0.89 = -2.93\ \text{MPa} \end{aligned}$$ $$\boxed{\text{every fibre remains in compression at every stage — the member never cracks}}$$ and the peak compression is 20 per cent of the $0.60f'_c = 24\ \text{MPa}$ limit. This is exactly what the symmetric strand layout buys.
Check the ultimate limit state. $w_f = 1.25(3.44) + 1.5(3.0) = 8.80\ \text{kN/m}$ and $P_f = 1.25(3.0) + 1.5(2.5) = 7.50\ \text{kN}$, so $M_f = 8.80(0.5) + 7.50 = 11.90\ \text{kN}\cdot\text{m}$ hogging and 4.84 kN·m sagging. For the hogging case the two top strands act as tension steel at $d_p = 350\ \text{mm}$, with $f_{pr} \approx 0.9f_{pu} = 1674\ \text{MPa}$: $$\begin{aligned} T &= \phi_p A_p f_{pr} = 0.90(110)(1674) = 165.7\ \text{kN} \\ a &= \frac{165\,726}{0.79(0.65)(40)(150)} = 53.8\ \text{mm} \end{aligned}$$ $$M_r = 165.7\left(350 - \frac{53.8}{2}\right)/10^3 = 53.55\ \text{kN}\cdot\text{m} \;\Longrightarrow\; \frac{M_f}{M_r} = 0.222$$
Apply the cracking rule, which is what actually sizes the strand. Clause 18.8.2 requires the factored resistance to exceed 1.2 times the cracking moment, so that a member which cracks does not immediately fail: $$M_{cr} = \left(0.6\sqrt{f'_c} + f_{cpe}\right) Z = (3.79 + 3.82)(4.00\times10^6)/10^6 = 30.46\ \text{kN}\cdot\text{m}$$ $$1.2 M_{cr} = 36.55\ \text{kN}\cdot\text{m} \le M_r = 53.55\ \text{kN}\cdot\text{m} \ \ \checkmark$$ Since $1.2M_{cr} = 36.6$ is three times the applied $M_f = 11.9$, this rule — not the applied load — is the binding requirement on the amount of prestressing steel. Adding prestress raises $M_{cr}$ as well as $M_r$, so over-prestressing does not help; the balance found here is deliberate.
Compute the immediate dead-load deflection. The member is uncracked, so use $E_c I_g = 28\,460(8.00\times10^8) = 2.277\times10^{13}\ \text{N}\cdot\text{mm}^2$. Superposing the span UDL and the hogging moment the cantilever applies at B, the two effects almost cancel: $$\Delta_{span} = \frac{5wL^4}{384EI} - \frac{M_B L^2}{16EI} = 0.159 - 0.117 = 0.047\ \text{mm}$$ and the free end of the cantilever drops $0.100\ \text{mm}$. Because $e = 0$ there is no prestress camber to superpose.
Amplify for creep to get the long-term deflection. Only the sustained load creeps, and here all of the dead load is sustained. With a creep coefficient $\phi_{cr} = 2.0$ for a steam-cured precast member, $$\Delta_{LT} = (1 + \phi_{cr})\Delta_i = 3.0 \Delta_i$$ $$\boxed{\begin{aligned} \Delta_{LT} &= 0.14\ \text{mm at mid-span}\ (L/21\,000) \\ & 0.30\ \text{mm at the cantilever tip}\ (a/3300) \end{aligned}}$$ The PCI final multiplier of 2.70 for the self-weight component of a non-composite member gives 0.13 and 0.27 mm, so the two methods agree. Both are negligible against any serviceability criterion.
Detail for handling and for the end zone. A symmetric strand pattern has a practical advantage beyond the stress checks: the member is safe to lift or store either way up, which matters for a 4 m precast unit that will be handled several times. Provide 6 mm welded-wire stirrups at 100 mm over the transfer length (about $50d_b = 475\ \text{mm}$ from each end) to control the bursting stresses at release, and 25 mm cover to the strands, appropriate for a certified shop under controlled conditions.
Figure C1.1 — Pretensioned section: 150 × 400 mm, two 9.5 mm low-relaxation strands 50 mm from the top and two 50 mm from the bottom. The strand centroid coincides with the section centroid, so the prestress is uniform precompression and no camber develops.
Final Results
Item
Result
Cross-section
150 mm × 400 mm rectangle
Prestressing steel
4 – 9.5 mm seven-wire low-relaxation strands ($A_p = 220$ mm$^2$), two at 50 mm from the top and two at 50 mm from the bottom, $e = 0$
Force at transfer
$P_i = 286.4$ kN, $f_{cpi} = 4.77$ MPa uniform
Losses (itemised)
ES 38.7 + SH 80.0 + CR 67.1 + RE 32.6 = 218.4 MPa = 16.8 %; design value 20 %
0.14 mm mid-span ($L/21\,000$), 0.30 mm at the tip ($a/3300$)
Camber
nil, because the strand centroid is at the section centroid
End-zone steel
6 mm WWF stirrups at 100 mm over 475 mm from each end
Check — prestressing is not the economical choice at this load, and the section is minimum-governed. The applied moment of 11.9 kN·m would not crack an unstressed 150 × 400 mm section, so this member is prestressed because question C1 asks for a prestressed design, not because the loading demands one. Two consequences are reported rather than hidden: the ultimate utilisation is only 0.22, and the amount of strand is set by the Clause 18.8.2 cracking rule rather than by the load. In practice the same loading over a 4 m span at 2 m centres would be carried by a reinforced or precast hollow-core unit at lower cost; the prestressed solution is justified only if the member must be precast for speed or if the same section is repeated many times.