16-Civ-B5 Water Supply and Wastewater Treatment · December 2014
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Examination, December 2014 — 98-Civ-B5 Water Supply and Wastewater Engineering. Three hours; closed book with one two-sided aid sheet and an approved calculator. Question 1 is compulsory and any three of Questions 2–5 are attempted; every question carries 25 marks. All five questions are solved below, because the set is intended as a study resource rather than an exam script.
Reference texts.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given.
| Quantity | Symbol | Value |
|---|---|---|
| Average plant flow | $Q$ | $50\,000\ \text{m}^3/\text{d}$ |
| Solids retention time | $\theta_c$ | $10\ \text{d}$ |
| Aeration-tank MLSS | $X$ | $3\,000\ \text{mg/L}$ |
| Waste sludge flow | $Q_w$ | $500\ \text{m}^3/\text{d}$ |
| Waste sludge solids | $X_w$ | $8\,000\ \text{mg/L}$ |
| Total secondary clarifier volume | $V_{sc}$ | $12\,000\ \text{m}^3$ |
| Clarifier side water depth | $H$ | $3.5\ \text{m}$ |
| Primary-clarifier effluent BOD5 | $S_0$ | $150\ \text{mg/L}$ |
Find. (a) the aeration-tank volume and hydraulic retention time; (b) the secondary-clarifier surface overflow rate and solids loading rate; and (c) the oxygen demand in kg/d for carbonaceous BOD removal.
Approach. Part (a) follows from the definition of solids retention time as the solids inventory divided by the solids wastage rate, which gives the tank volume directly and hence the hydraulic retention time. Part (b) converts the clarifier volume and depth to a plan area, then applies the two loading definitions — the surface overflow rate on the plant flow alone, the solids loading rate on the plant flow plus the return sludge, whose magnitude comes from a solids balance around the clarifier. Part (c) uses the oxygen mass balance around the aeration tank: the ultimate oxygen demand of the BOD removed less the oxygen equivalent of the biomass wasted rather than oxidised.
where $V$ is the aeration-tank volume. Every concentration appears as a ratio, so mg/L may be used throughout without conversion.
Checking backwards: $VX = 13\,333 \times 3\,000 = 40.0 \times 10^6\ \text{g}$, that is $40\,000\ \text{kg}$ of MLSS in the tank, against a wastage of $Q_w X_w = 500 \times 8\,000 = 4\,000\ \text{kg/d}$; the quotient is $10\ \text{d}$ as required.
Both results sit squarely in the conventional plug-flow activated-sludge range ($\theta_c = 5$ to $15\ \text{d}$, $\tau = 4$ to $8\ \text{h}$, $X = 1\,500$ to $4\,000\ \text{mg/L}$), which is the first sanity check to make. The corresponding food-to-microorganism ratio is $F/M = QS_0/(VX) = 7\,500/40\,000 = 0.19\ \text{kg BOD}_5$ per kg MLSS per day, and the volumetric organic loading is $0.56\ \text{kg BOD}_5\,\text{m}^{-3}\text{d}^{-1}$ — again typical of a conventional plant, and both consistent with an SRT that is long enough to nitrify in warm weather.
This is the combined area of all secondary clarifiers in service.
Design guidance for activated-sludge secondary clarifiers is roughly $16$ to $28\ \text{m}^3\,\text{m}^{-2}\,\text{d}^{-1}$ at average flow, so at $14.6$ the clarifiers are conservatively loaded hydraulically and have useful headroom for peak wet-weather flow.
a recycle ratio of $R = Q_R/Q = 0.60$, comfortably within the usual 0.25 to 1.0 range for a conventional plant.
Against a typical average-flow design value of $70$ to $120\ \text{kg}\,\text{m}^{-2}\,\text{d}^{-1}$ and a peak limit near $200$, the clarifiers are adequately but not generously sized for thickening. Had the recycle been omitted, the answer would have been $43.8\ \text{kg}\,\text{m}^{-2}\,\text{d}^{-1}$, understating the thickening duty by a factor of 1.6 and giving the false impression of substantial spare capacity — this is the single most common error in the calculation. The clarifier hydraulic retention time on the combined flow, $12\,000/80\,000 = 0.15\ \text{d}$ or $3.6\ \text{h}$, is also reasonable.
where $f = \mathrm{BOD_5}/\mathrm{BOD_u} = 0.68$ for municipal wastewater, and $1.42\ \text{kg O}_2$ per kg of cell tissue is the oxygen equivalent of $\mathrm{C_5H_7NO_2}$. Nitrogenous demand is excluded, as the question asks only for BOD removal.
and converting the five-day value to the ultimate demand,
$$\frac{Q(S_0 - S)}{f} = \frac{7\,000}{0.68} = 10\,294\ \text{kg/d as O}_2$$equivalent to $0.82\ \text{kg O}_2$ per kg of BOD5 removed, or an average uptake rate of about $240\ \text{kg/h}$. Because oxygen transfer efficiency in a diffused system under process conditions is typically only 8 to 12 percent, this actual oxygen requirement corresponds to a standard oxygen requirement roughly 1.7 to 2.0 times larger — the number that would actually size the blowers.
Check: the assumptions behind part (c), and their weight. The question supplies neither the effluent BOD nor the volatile fraction of the waste sludge, so three values are assumed and each is declared here. (1) Effluent soluble BOD5 $S = 10\ \text{mg/L}$; taking $S = 0$ instead raises the answer to $6\,485\ \text{kg/d}$, about 13 percent higher. (2) Volatile fraction $\mathrm{MLVSS/MLSS} = 0.80$; applying the $1.42$ factor to the whole $4\,000\ \text{kg TSS/d}$ would give $4\,614\ \text{kg/d}$, about 20 percent lower, but that is not defensible because the $1.42$ oxygen equivalent belongs to cell tissue, which is volatile matter. (3) $f = 0.68$, the standard municipal value.
A second cross-check is worth recording. Estimating the biomass from synthesis theory rather than from the reported wastage, with $Y = 0.40\ \text{kg VSS/kg BOD}$ and $k_d = 0.06\ \text{d}^{-1}$, gives $P_{X} = Y Q (S_0 - S) / (1 + k_d \theta_c) = 1\,750\ \text{kg VSS/d}$ and hence $R_O = 7\,809\ \text{kg/d}$, or $1.12\ \text{kg O}_2$ per kg BOD removed — the textbook range. The discrepancy is real and traceable: the data as given imply an observed yield of $4\,000/7\,000 = 0.57\ \text{kg TSS}$ per kg BOD, which is high for a 10-day SRT and suggests either substantial inert solids carried over from the primary clarifier or an over-stated wastage rate. The boxed answer uses the plant’s own reported wastage, as the question intends; a designer sizing blowers for this plant should carry the higher figure as the aeration design case.
| Part | Quantity | Value |
|---|---|---|
| (a) | Aeration-tank volume, $V$ | $13\,333\ \text{m}^3$ |
| (a) | Hydraulic retention time, $\tau$ | $0.267\ \text{d} = 6.4\ \text{h}$ |
| (a) | MLSS inventory / $F\!/\!M$ | $40\,000\ \text{kg}$ / $0.19\ \text{d}^{-1}$ |
| (b) | Clarifier plan area, $A$ | $3\,428.6\ \text{m}^2$ |
| (b) | Surface overflow rate | $14.6\ \text{m}^3\,\text{m}^{-2}\,\text{d}^{-1}$ |
| (b) | Return sludge flow / ratio | $30\,000\ \text{m}^3/\text{d}$ / $R = 0.60$ |
| (b) | Solids loading rate | $70.0\ \text{kg}\,\text{m}^{-2}\,\text{d}^{-1}$ |
| (c) | BOD5 removed | $7\,000\ \text{kg/d}$ |
| (c) | Oxygen demand, $R_O$ | $5\,750\ \text{kg O}_2/\text{d}$ |