NivaarExam PrepOfficial exam papers ↗

16-Civ-B7 Transportation Planning and Engineering · December 2016

Question 5 of 7: Filter Design and Drainage-Layer Capacity

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Examinations, December 2016 — 98-Civ-B7 Highway Engineering. Three-hour duration, open book, any non-communicating calculator permitted. Seven questions, all of equal value (20 marks each); the paper requires a total of five solutions and marks only the first five as they appear in the answer book. The marking scheme printed on page 1 gives the sub-part split (Q1 20; Q2 8+12; Q3 20; Q4 10+10; Q5 8+12; Q6 10+10; Q7 20). All seven questions are solved here so that the set works as a study resource. The paper also notes that any data not given may be assumed, provided the assumption is stated — every assumption made below is flagged in a callout.

Reference texts.

Question 5: Filter Design and Drainage-Layer Capacity (8 + 12 = 20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

PartQuantityValue
(a)Subgrade gradation (sieve mm / percent passing) 4.75/98, 2.36/93, 1.18/85, 0.60/65, 0.30/35, 0.15/15, 0.075/10
(b)Drainage-layer thickness, H200 mm = 0.20 m
(b)Cross slope, S4 percent = 0.04 m/m
(b)Effective porosity, ne0.25
(b)Permeability, k3.5 cm/s = 0.035 m/s = 3024 m/day
(b)Drainage path length, L6 m

Find. (a) the D15 and D85 sizes that a soil filter placed against this subgrade must have; (b) the steady-state discharge capacity of the drainage layer per metre of width, and the times to 50 percent and 95 percent drainage.

Approach. Part (a): read D15, D50 and D85 off the subgrade curve, apply the three Terzaghi/Cedergren filter criteria to bound the filter's D15, then fix D85 by keeping the filter's gradation curve roughly parallel to the subgrade's and checking it against the pipe-bridging requirement. Part (b): Darcy's law along the cross slope for the steady capacity, and the Casagrande–Shannon time factor for the transient drawdown.

  1. Part (a) — read the controlling sizes off the subgrade gradation. Two of the three fall exactly on printed sieves: $$D_{15} = 0.15\ \text{mm} \ (15 \text{ percent passing}), \qquad D_{85} = 1.18\ \text{mm} \ (85 \text{ percent passing})$$ and D50 is interpolated logarithmically between 0.30 mm (35 percent) and 0.60 mm (65 percent): $$D_{50} = 0.30 \times 2^{(50-35)/(65-35)} = 0.30\sqrt{2} = 0.424\ \text{mm}$$
  2. Apply the retention (anti-piping) criterion. The filter must be fine enough that subgrade particles cannot wash through its pore throats: $$\frac{D_{15}^{F}}{D_{85}^{S}} \le 5 \quad\Longrightarrow\quad D_{15}^{F} \le 5 \times 1.18 = 5.90\ \text{mm}$$
  3. Apply the permeability criterion. The filter must also be coarse enough to be substantially more permeable than the soil it drains, otherwise it simply becomes part of the subgrade: $$\frac{D_{15}^{F}}{D_{15}^{S}} \ge 5 \quad\Longrightarrow\quad D_{15}^{F} \ge 5 \times 0.15 = 0.75\ \text{mm}$$ The two criteria together define the design window $$\boxed{0.75\ \text{mm} \le D_{15}^{F} \le 5.90\ \text{mm}}$$
  4. Select the filter D15. Taking the geometric mean of the window keeps equal proportional margin against piping and against clogging: $$\sqrt{0.75 \times 5.90} = 2.10\ \text{mm} \quad\Longrightarrow\quad \boxed{D_{15}^{F} = 2.0\ \text{mm}}$$
  5. Fix the filter D85. A filter is specified as a band, and the standard way to generate it is to shift the subgrade curve to the right by the ratio just chosen, keeping it roughly parallel so that the filter is itself internally stable. The subgrade has $$\frac{D_{85}^{S}}{D_{15}^{S}} = \frac{1.18}{0.15} = 7.87$$ so the parallel filter has $$D_{85}^{F} = 2.0 \times 7.87 = 15.7\ \text{mm} \quad\Longrightarrow\quad \boxed{D_{85}^{F} \approx 16\ \text{mm}}$$
  6. Check the selection against the remaining criteria. The uniformity criterion is satisfied, $$D_{50}^{F} = 2.0 \times \frac{0.424}{0.15} = 5.66\ \text{mm} \le 25\,D_{50}^{S} = 25 \times 0.424 = 10.6\ \text{mm}\ \checkmark$$ and the filter is coarse enough to bridge the openings of a slotted collector pipe: for a typical 3 mm slot the requirement D85F ≥ 2 × slot width = 6 mm is met more than twice over. The resulting specification is a well-graded sand to fine gravel running roughly from 0.75 mm to 20 mm.
  7. Part (b) — compute the steady-state capacity. Under steady infiltration the drainage layer flows full and parallel to the cross slope, so Darcy's law with a hydraulic gradient equal to the slope gives, per metre of width, $$q = k\,H\,S = 0.035 \times 0.200 \times 0.04 = 2.80 \times 10^{-4}\ \text{m}^{3}/\text{s per m}$$ $$\boxed{q = 0.28\ \text{L/s per metre of width} = 24.2\ \text{m}^{3}/\text{day per metre}}$$ Equivalently, expressed as the infiltration the layer can accept over its 6 m length, 24.2/6 = 4.03 m/day, which is far above any credible pavement infiltration rate — the layer is not capacity-limited.
  8. Form the time constant for the transient drawdown. The Casagrande–Shannon formulation writes the time to drain as a dimensionless time factor multiplied by $$m = \frac{n_{e}\,L^{2}}{k\,H} = \frac{0.25 \times 6^{2}}{0.035 \times 0.200} = \frac{9.0}{0.0070} = 1286\ \text{s} = 0.357\ \text{h}$$ with the slope factor $$S_{1} = \frac{L\,S}{H} = \frac{6 \times 0.04}{0.200} = 1.20$$
  9. Evaluate the time factors. For S1 of order one or more the drawdown is slope-driven: the drying front travels down the layer at the kinematic speed kS/ne, so the degree of drainage is U = t kS/(neL) and the time factor reduces to T = U/S1: $$T_{50} = \frac{0.50}{1.20} = 0.417, \qquad T_{95} = \frac{0.95}{1.20} = 0.792$$ The horizontal-layer limit of the same solution, T50 = 0.50, provides the upper bound used as a check below.
  10. Compute the drainage times. $$t_{50} = T_{50}\,m = 0.417 \times 1286 = 536\ \text{s}, \qquad t_{95} = T_{95}\,m = 0.792 \times 1286 = 1018\ \text{s}$$ $$\boxed{t_{50} = 8.9\ \text{min} \quad\text{and}\quad t_{95} = 17.0\ \text{min}}$$ The bound confirms the order of magnitude: even treating the layer as perfectly flat gives t50 = 0.50 × 1286 s = 10.7 min, so the answer is bracketed within two minutes regardless of how the slope is handled, and complete drainage takes neL/(kS) = 17.9 min.
  11. Interpret the result for design. AASHTO rates the quality of drainage by the time taken to remove water: 2 hours is "excellent" and 1 day is "good". At under 20 minutes to 95 percent drainage this layer is comfortably in the excellent class, which justifies drainage coefficients m2 = m3 in the range 1.25–1.40 for the granular layers it serves — a structural saving of roughly 25 percent of the granular thickness compared with the m = 1.00 assumed in Question 3.
0.050.0750.10.150.30.61.182.364.751020020406080100D₁₅ = 0.15D₈₅ = 1.18filter D₁₅ = 2.0filter D₈₅ = 15.7Particle size (mm) — log scalePercent passingSubgrade (solid red) and the proposed filter (dashed blue)
Figure 5.1 — Subgrade gradation with the proposed filter band. The filter curve is the subgrade curve shifted right by a factor of 13.3 (D15 from 0.15 mm to 2.0 mm), which keeps the two curves parallel and satisfies all three filter criteria.
asphalt concreteopen-graded drainage layer · H = 200 mm · k = 3.5 cm/s · nᵉ = 0.25subgradecrest200 mmL = 6 m at 4 % cross slope → q = kHS = 24.19 m³/day per metre of widthDrainage layer under the pavement (schematic)
Figure 5.2 — Drainage layer discharging along the 4 percent cross slope. The steady capacity is the Darcy flux through the full 200 mm thickness; the transient drawdown is a drying front travelling downslope at kS/nᵉ.

Final Results.

QuantityValue
(a) Subgrade D15 / D50 / D850.15 / 0.424 / 1.18 mm
(a) Permissible window for the filter D150.75 mm to 5.90 mm
(a) Selected filter D152.0 mm
(a) Selected filter D8516 mm (computed 15.7 mm)
(a) Check: filter D50 against 25 D50S5.66 mm ≤ 10.6 mm ✓
(b) Steady-state capacity0.28 L/s per m = 24.2 m³/day per m
(b) Time constant m / slope factor S11286 s / 1.20
(b) Time to 50 percent drainage8.9 min (flat-layer bound 10.7 min)
(b) Time to 95 percent drainage17.0 min
(b) AASHTO quality of drainageExcellent (m = 1.25 to 1.40)

Check: part (a) needs a pipe slot width to close the bridging criterion, which the question does not give; a typical 3 mm slotted subdrain is assumed and stated, and the selected filter clears that requirement by a factor of 2.6, so the conclusion is insensitive to the assumption. Part (b) treats the drainage path as running down the 4 percent cross slope only, with no longitudinal grade; if the road also fell longitudinally the resultant slope and the resultant path length would both change and the times would shorten. The time factors are taken from the slope-driven form of the Casagrande–Shannon solution, and the flat-layer value T50 = 0.50 is quoted alongside as an upper bound, so t50 is known to lie between 8.9 and 10.7 minutes whichever chart is used.