National Exams — May 2015 — 11-CS-1 Engineering Economics. Open book; non-communicating calculator permitted. Any four of the five questions constitute a complete paper; all questions are of equal value. Fully worked solutions to all five questions follow; standard compound-interest factors are used and minor rounding is immaterial.

Question 1: Expressway — Present and Annual Worth (25 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Assumptions: present $t=0$ at end of 2015; construction $40M at ends of 2020–2023 ($t=5\text{–}8$); O&M from 2024 to 2063 ($t=9$ to $t=48$, 40 payments), first $3M growing 1%/yr; overhauls of $5M at operation years 10, 20, 30 ($t=18, 28, 38$; not at end of life); analysis horizon 48 years; $i=6\%$; no salvage.

(a) Cash-Flow Diagram

$M
0 --+----+-----+---------+---------+---------+------+  (t=0..48)
       t=5..8  t=9........................ t=48
     -40(×4)   O&M: 3.0 rising 1%/yr to t=48
                 ↓ -5    ↓ -5    ↓ -5   (overhauls t=18,28,38)

(b) Present Worth (t = 0, i = 6%)

Construction ($40M at $t=5\text{–}8$): $PW_c = 40(0.74726+0.70496+0.66506+0.62741)=40(2.74469)=\$109.79$M.

O&M (geometric, $A_1=3$M, $g=1\%$, $n=40$): the closed form values the series one period before its first payment, i.e. at $t=8$, so $P_8 = 3\frac{1-(1.01/1.06)^{40}}{0.05}=3(17.10499)=\$51.3150$M; then $PW_{OM}=51.3150(P/F,6\%,8)=51.3150(0.62741)=\$32.20$M.

Overhauls ($5M at $t=18,28,38$): $PW_{oh}=5(0.35034+0.19563+0.10924)=5(0.65521)=\$3.28$M.

$$PW = -(109.79 + 32.20 + 3.28) \approx \boxed{-\$145.3\text{M}}$$

(c) Annual Worth (over the 48-year horizon)

$$AW = PW\,(A/P,6\%,48) = -145.3(0.063898) \approx \boxed{-\$9.28\text{M/yr}}$$

The expressway costs an equivalent of about $9.28M per year over the analysis horizon (again counting only costs, not the value of improved traffic flow).