23-CS-1 Engineering Economics · December 2016
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Exams — December 2016 — 11-CS-1 Engineering Economics. Open book; non-communicating calculator permitted. Any four of the five questions constitute a complete paper; all questions are of equal value. Fully worked solutions to all five questions follow; standard compound-interest factors are used and minor rounding is immaterial.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Independent projects do not compete with one another — the budget is assumed sufficient for any combination — so each is judged on its own merits and no incremental analysis is needed. Accept every project whose overall IRR exceeds the MARR:
| Project | First cost | Overall IRR | vs MARR 17% | Decision |
|---|---|---|---|---|
| 1 | $100,000 | 19% | 19 > 17 | Accept |
| 2 | $175,000 | 15% | 15 < 17 | Reject |
| 3 | $200,000 | 18% | 18 > 17 | Accept |
| 4 | $250,000 | 16% | 16 < 17 | Reject |
Select Projects 1 and 3, a total commitment of $300,000. Note that the incremental columns are simply not used here; they answer a question — "which one?" — that independence does not pose.
Now only one project may be chosen, so the overall IRRs cannot decide the matter: a percentage says nothing about how much money is working at that percentage. Order the alternatives by increasing first cost, take do-nothing as the initial "current best" (it is permitted here), and advance to a costlier alternative only when the extra investment required to get there earns at least the MARR:
Select Project 3. The 23% in the $\text{IRR}_{3\text{-}2}$ cell is never used, because P2 was eliminated before P3 was considered — comparing a challenger against an already-rejected alternative is the classic error in this method.
A rate-of-return method is the right choice when:
Where cash flows are non-conventional (more than one sign change) the IRR may not be unique, and a present- or annual-worth method should be used instead or as a check.
No. Project 1 has the highest overall IRR (19%), yet the mutually-exclusive choice in (b) is Project 3, whose overall IRR is only 18%. The reason is scale: a rate of return is a ratio and carries no information about the size of the investment earning it. Moving from P1 to P3 costs an extra $100,000 that earns 17%, comfortably above the 15% MARR, so that extra money is worth committing even though it drags the average return down from 19% to 18%. Maximizing a percentage is not the objective; maximizing total value at the MARR is. The correct procedure is therefore always incremental analysis — which, applied properly, gives the same answer as maximizing present worth.