18-Env-A1 Principles of Environmental Engineering · May 2015
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Exams — May 2015 — 04-Env-A1 / Principles of Environmental Engineering. 3 hours duration; closed book with an 8.5×11 in double-sided aid sheet; Casio or Sharp approved calculator only. Any five questions constitute a complete paper (first five answers marked); all seven are solved below for completeness. Each question is worth 20 marks.
Reference texts. Davis & Cornwell, Introduction to Environmental Engineering (6th ed.); Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery (5th ed.); MWH’s Water Treatment: Principles and Design (3rd ed.); Guidelines for Canadian Drinking Water Quality (Health Canada); Canadian Council of Ministers of the Environment (CCME) water-quality and landfill guidelines; Canadian Environmental Protection Act, 1999 (CEPA); Impact Assessment Act, 2019 (Canada) and Alberta Environmental Protection and Enhancement Act; Andrews, Canadian Professional Engineering and Geoscience (professional ethics).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Physical-chemical and biological treatment remove different fractions of a wastewater's particulate and colloidal load, and neither alone is sufficient. Physical-chemical primary treatment (screening followed by gravity sedimentation in a primary clarifier) removes the coarse, readily-settleable fraction of solids by density difference alone — fast and low-cost, but it cannot touch the finely divided and dissolved organic matter that remains suspended or in solution. Biological secondary treatment (an aeration basin growing a mixed microbial population — activated sludge) then converts that dissolved and colloidal organic matter into new microbial cell mass and $\text{CO}_2$ through metabolism; critically, this step converts a fraction of the pollutant load that is not particulate at all into flocculant biomass that a secondary clarifier can then remove by the same gravity-settling principle as the primary stage. The two mechanisms are therefore complementary rather than redundant: physical-chemical treatment strips out what settles on its own, and biological treatment turns what does not settle on its own into something that will.
Given. Divalent-cation concentrations from the water analysis, with atomic weights Ca = 40, H = 1, C = 12, O = 16, Mg = 24, Fe = 56 as stated on the exam:
| Ion | Concentration | Atomic weight | Valence |
|---|---|---|---|
| $Ca^{2+}$ | 150 mg/L | 40 (given) | 2 |
| $Mg^{2+}$ | 800 mg/L | 24 (given) | 2 |
| $Fe^{2+}$ | 60 mg/L | 56 (given) | 2 |
Find. The total hardness of the water expressed as mg/L CaCO3, and its qualitative classification (soft, moderately hard or hard).
Approach. Convert each hardness-forming ion's mass concentration to an equivalent mass concentration as $\text{CaCO}_3$ using the ratio of equivalent weights, then sum and classify against the standard hardness scale.
| Quantity | Value |
|---|---|
| Hardness from $Ca^{2+}$ | 375.0 mg/L as CaCO3 |
| Hardness from $Mg^{2+}$ | 3333.3 mg/L as CaCO3 |
| Hardness from $Fe^{2+}$ | 107.1 mg/L as CaCO3 |
| Total hardness | 3815.5 mg/L as CaCO3 |
| Classification | Hard (very hard) |
Given. Flow rates and temperatures of the two streams mixing in the river (from the source diagram):
| Quantity | Symbol | Value |
|---|---|---|
| Cooling-tower discharge flow | $Q_c$ | 200 m³/s |
| Cooling-tower discharge temperature | $T_c$ | 50°C |
| Upstream river temperature | $T_s$ | 10°C |
| Combined downstream flow | $Q$ | 300 m³/s |
Find. The combined downstream river temperature $T$.
Approach. The upstream river flow $Q_s$ is not stated directly but is fixed by continuity ($Q=Q_s+Q_c$); a steady-flow thermal energy balance (constant density and specific heat) on the mixing point then gives the combined temperature as a flow-weighted average.
| Quantity | Value |
|---|---|
| Upstream river flow (by continuity), $Q_s$ | 100 m³/s |
| Combined downstream temperature, $T$ | 36.7 °C |
A downstream temperature of 36.7°C is far above the roughly 10–19°C range most cold-water salmonid fisheries need, so the cooling-tower discharge is a serious thermal-pollution concern. Two engineering solutions to reduce it: (1) increase the cooling tower's approach/rejection performance (larger tower, added cooling cells, or a wet-and-dry hybrid tower) so that $T_c$ itself is reduced before the flow ever reaches the river, directly lowering the mixed $T$; and (2) install a multiport diffuser outfall that discharges the heated flow as many small, high-velocity jets across the river's width and depth rather than as one concentrated point source — this does not reduce the total heat load but rapidly entrains additional river water into the near-field mixing zone, lowering the peak temperature any single fish encounters and shortening the reach of river above the fishery's thermal tolerance.