NivaarExam PrepOfficial exam papers ↗

18-Env-A2 Hydrology and Municipal Hydraulics Engineering · December 2014

Question 3 of 7: Pipe Network Analysis, Water Hammer, and Pump System Curves

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — December 2014 — 04-Env-A2 / Hydrology and Municipal Hydraulics Engineering. 3 hours duration; closed book with an 8.5×11 in double-sided aid sheet; Casio or Sharp approved calculator only. Any five questions constitute a complete paper (first five answers marked); all seven are solved below for completeness. Each question ("Problem") is worth 20 marks.

Reference texts. Chow, Open-Channel Hydraulics; Linsley, Kohler & Paulhus, Hydrology for Engineers (3rd ed.); Walski et al., Advanced Water Distribution Modeling and Management; Davis & Cornwell, Introduction to Environmental Engineering (6th ed.); Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery (5th ed.).

Problem 3: Pipe Network Analysis, Water Hammer, and Pump System Curves (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(i) Hardy-Cross Pipe Network Solution

Given. A 4-node network (A, B, C, D) with 5 pipes forming two loops (A-B-C-A and B-D-C-B), inflow 1000 L/s at A, and outflows of 100 L/s at B, 300 L/s at C and 600 L/s at D:

Given data
PipeLength, $L$ (m)Diameter, $d$ (mm)
AB600250
BC800300
CD600250
AC800300
BD600250
Check: no pipe roughness / Hazen–Williams $C$ is given. A common $C$ is assumed for every pipe (same material throughout the network), using the Hazen–Williams head-loss form $h_f = K Q^{1.852}$ with $K_i \propto L_i/d_i^{4.87}$. A single common $C$ cancels out of the pipe-to-pipe resistance ratios, so the resulting flow split is exact and independent of the (unstated) $C$ value.

Find. The flow in each of the five pipes.

Approach. Start from an initial flow distribution that satisfies continuity at every node, then apply Hardy-Cross loop-balancing corrections $\Delta Q = -\dfrac{\sum K Q|Q|^{n-1}}{n\sum K|Q|^{n-1}}$ (with $n=1.852$) to Loop 1 (A→B→C→A) and Loop 2 (B→D→C→B, sharing pipe BC) until both loops' signed head-loss sums vanish.

  1. Initial (continuity-satisfying) trial flows. $Q_{AB}=600$, $Q_{AC}=400$ L/s (sum 1000 at A). At B: $Q_{BC}=200$, $Q_{BD}=300$ L/s (so $600=200+300+100$). At C: $Q_{CD}=300$ L/s (so $400+200=300+300$). Node D then balances exactly: $300+300=600$ L/s. ✓
  2. Loop-balance corrections. With $K_i = L_i/d_i^{4.87}$ for each pipe, iterate the Hardy-Cross correction around Loop 1 (via AB, BC, CA) and Loop 2 (via BD, DC, CB) until each loop's signed $\sum KQ|Q|^{n-1}$ is zero to numerical precision.
  3. Converged flows. The iteration converges (residual loop head-loss $<10^{-4}$) to: $$Q_{AB}=\boxed{419.4\ \text{L/s}}, \quad Q_{AC}=\boxed{580.6\ \text{L/s}}, \quad Q_{BC}=\boxed{19.2\ \text{L/s}}, \quad Q_{BD}=\boxed{300.3\ \text{L/s}}, \quad Q_{CD}=\boxed{299.7\ \text{L/s}}.$$
  4. Check. Node continuity: A: $419.4+580.6=1000.0$ ✓. B: $419.4=19.2+300.3+100.0$ ✓. C: $580.6+19.2=299.7+300.0$ ✓. D: $300.3+299.7=600.0$ ✓.
AB: L=600 m, d=250 mm Q = 419.4 L/s BC: L=800 m, d=300 mm Q = 19.2 L/s CD: L=600 m, d=250 mm Q = 299.7 L/s AC: L=800 m, d=300 mm Q = 580.6 L/s BD: L=600 m, d=250 mm Q = 300.3 L/s 1000 L/s in 100 L/s out 300 L/s out 600 L/s out A B C D
Solved pipe network: converged Hardy-Cross flows on each of the five pipes, satisfying continuity at every node and zero net head loss around both loops.
PipeFlow, $Q$
AB419.4 L/s (A→B)
AC580.6 L/s (A→C)
BC19.2 L/s (B→C)
BD300.3 L/s (B→D)
CD299.7 L/s (C→D)

(ii) Water Hammer

Water hammer is the pressure transient produced when the velocity of a moving water column is changed abruptly: the column's kinetic energy converts into a pressure pulse that propagates back and forth along the pipe at the pressure-wave celerity (typically 1000–1400 m/s for water in a rigid steel/ductile-iron main). A pump system causes water hammer whenever the change in flow is rapid relative to the pipe's characteristic reflection time $2L/a$ (the round-trip travel time of the pressure wave along the pipe of length $L$) — classically, sudden pump trip (power failure), fast valve closure, or a pump starting against a closed or partially-open discharge valve. If the closure/stoppage time is shorter than $2L/a$, the full Joukowsky pressure rise $\Delta p = \rho a \Delta V$ is realized; if it is slower, the surge is attenuated.

One effective way to reduce or eliminate the effect is to slow the rate of flow change so that it exceeds the critical time $2L/a$ — for example, a slow-closing check valve or a controlled valve-closure schedule at the pump discharge (or, on the pump-trip side, a flywheel that extends the pump's coast-down time). This converts a "rapid" closure into a "slow" one and greatly reduces the peak transient pressure without the added infrastructure of a surge tank or air chamber.

(iii) System Head Curve

Flow rate, Q Total head, H Pump curve System curve Static head Shutoff head Operating point System Head Curve
Typical system head curve: the drooping pump curve intersects the rising (static + friction) system curve at the operating point; the pump curve's Q=0 intercept is the shutoff head, the system curve's Q=0 intercept is the static head.

The pump curve plots the head the pump can deliver against flow, falling from its maximum at zero flow (the shutoff head) as flow increases. The system curve plots the head the pipeline demands against flow — the static lift (elevation difference between source and delivery, present even at $Q=0$) plus friction losses, which grow with $Q^2$. The two curves' intersection is the operating point: the unique flow and head at which the pump's delivered head exactly equals the system's demanded head, and hence the flow the installation will actually deliver.

(iv) Multiple-Pump Configurations

(a) Increase discharge head, same flow — pumps in series. Staging two (or more) identical pumps in series (the discharge of one feeding the suction of the next) adds their heads at a common flow: the combined H–Q curve is obtained by adding heads vertically at each Q. This is the cost-effective route when a higher head is needed to reach a fixed downstream demand without changing the flow requirement, since a single much-larger-headed pump may not exist in a standard line or may be far less efficient at the required duty point.

(b) Increase discharge rate, same static head — pumps in parallel. Staging identical pumps in parallel (common suction and discharge headers) adds their flows at a common head: the combined H–Q curve is obtained by adding flows horizontally at each H. This is the cost-effective route when more capacity is needed at essentially the same static lift, and it has the added operational benefit that pumps can be staged on/off to track demand (running one, two, or three units) rather than running one oversized pump throttled back for most of its duty cycle.