NivaarExam PrepOfficial exam papers ↗

18-Env-A4 Water and Wastewater Engineering · May 2014

Question 4 of 5

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — May 2014 — 04-Env-A4 / Water and Wastewater Engineering. 3 hours duration; closed book with one aid sheet written on both sides; an approved calculator is permitted. Question 1 is compulsory; any three of the remaining four questions constitute a complete paper (only the first four of Questions 2–5 in the work book are marked); all five questions are solved below for completeness. Each question is worth 25 marks.

Reference texts. Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery (5th ed.); MWH's Water Treatment: Principles and Design (3rd ed.); Davis & Cornwell, Introduction to Environmental Engineering (6th ed.); Guidelines for Canadian Drinking Water Quality (Health Canada); Canadian Council of Ministers of the Environment (CCME) water-quality guidelines.

Question 4 (25 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(a) Oxygen demand and air requirement for 95% BOD removal (10 marks)

Given.

QuantityValue
Average flow, $Q$15,000 m³/d
Primary effluent BOD5, $S_0$150 mg/L
Required BOD removal95%
Observed sludge yield, $Y_{obs}$0.8 kg TSS/kg BOD5 removed

Find. The net oxygen demand (kg O2/d) and the corresponding air requirement (m³ air/d).

Approach. Convert the BOD5 removed to an oxygen demand using the ultimate-BOD conversion factor, credit back the oxygen equivalent of the biomass that leaves as waste sludge, then convert the net oxygen demand to an air volume via air's oxygen content and an assumed field oxygen-transfer efficiency.

  1. BOD5 removed load. Effluent $S_e = S_0(1-0.95) = 150(0.05) = 7.5$ mg/L, so $$\Delta BOD_5 = \frac{Q(S_0-S_e)}{1000} = \frac{15{,}000\times(150-7.5)}{1000} = \boxed{2137.5\ \text{kg BOD}_5/\text{d}}$$
  2. Biomass (waste sludge) produced. Using the given observed yield, $$P_x = Y_{obs}\times\Delta BOD_5 = 0.8\times2137.5 = \boxed{1710\ \text{kg TSS/d}}$$
  3. Net oxygen demand. Converting BOD5 to ultimate oxygen demand with $f=BOD_L/BOD_5\approx1.47$ (from the standard $BOD_5/BOD_L=0.68$ relation) and crediting 1.42 kg O2 per kg of biomass carbon that leaves as waste sludge rather than being oxidized (Metcalf & Eddy AOTR relation): $$AOTR = f\cdot\Delta BOD_5 - 1.42\,P_x = 1.47(2137.5)-1.42(1710) = 3142.1-2428.2 = \boxed{713.9\ \text{kg O}_2/\text{d}}$$
  4. Air requirement. Air at standard conditions has density ≈1.2 kg/m³ and an oxygen mass fraction of 23.2%, so 1 m³ of air carries $1.2\times0.232=0.2784$ kg O2. Assuming a field oxygen-transfer efficiency $OTE=8\%$ (typical for diffused/mechanical aeration, per check note below): $$\text{Air} = \frac{AOTR}{1.2\times0.232\times OTE} = \frac{713.9}{1.2\times0.232\times0.08} = \frac{713.9}{0.02227} = \boxed{32{,}055\ \text{m}^3\ \text{air/d}}$$

(b) Aeration tank volume (8 marks)

Given. $SRT = 4$ d, $MLSS = 2000$ mg/L, and the biomass production $P_x=1710$ kg TSS/d from part (a).

Find. Required aeration tank volume $V$.

Approach. At steady state, the mass of biomass in the reactor ($MLSS\times V$) turns over once every SRT (biomass wasted per day, $P_x$, times SRT), so $SRT = (MLSS\cdot V)/P_x$ rearranges directly for $V$.

  1. Aeration volume. With $MLSS=2000\ \text{mg/L}=2.0\ \text{kg/m}^3$: $$V = \frac{P_x\cdot SRT}{MLSS} = \frac{1710\times4}{2.0} = \boxed{3420\ \text{m}^3}$$
  2. Hydraulic retention time check. $$HRT = \frac{V}{Q}\times24 = \frac{3420}{15{,}000}\times24 = \boxed{5.47\ \text{h}}$$ This falls within the typical 4–8 h HRT range for conventional activated sludge, confirming the tank size is physically reasonable.

(c) Secondary clarifier area (7 marks)

Given. Peak hourly flow factor $= 3.0$; maximum allowable peak hourly surface overflow rate $SOR_{max}=35\ \text{m}^3/\text{m}^2\text{-d}$.

Find. Minimum required clarifier surface area.

  1. Peak hourly flow. $$Q_{peak} = Q\times PF = 15{,}000\times3.0 = \boxed{45{,}000\ \text{m}^3/\text{d}}$$
  2. Clarifier area. $$A = \frac{Q_{peak}}{SOR_{max}} = \frac{45{,}000}{35} = \boxed{1285.7\ \text{m}^2}$$
QuantityValue
(a) BOD5 removed load2137.5 kg/d
(a) Net oxygen demand (AOTR)713.9 kg O2/d
(a) Air requirement (8% OTE)≈32,055 m³ air/d
(b) Aeration tank volume3420 m³ (HRT ≈ 5.47 h)
(c) Secondary clarifier area1285.7 m²
Check: the exam gives no kinetic coefficients ($k_d$, $a'$, $b'$) or aeration transfer-efficiency data, so this solution assumes (i) the standard $BOD_5/BOD_L=0.68$ ultimate-BOD conversion, (ii) the standard 1.42 kg O2/kg-biomass cell-mass credit, and (iii) an 8% field oxygen-transfer efficiency typical of diffused aeration — all standard Metcalf & Eddy design assumptions used because the question supplies the observed yield $Y_{obs}$ specifically to let the net (post-cell-credit) oxygen demand be computed rather than the gross BOD-only figure.