NivaarExam PrepOfficial exam papers ↗

18-Env-A4 Water and Wastewater Engineering · December 2017

Question 5 of 5: Activated Sludge – Waste Sludge Volume and Aeration Tank Sizing

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — December 2017 — 04-Env-A4 / Water and Wastewater Engineering. 3 hours duration; closed book with one double-sided aid sheet; approved calculator permitted. The paper instructs that Question 1 is compulsory and any three of the remaining four questions are required; all five are solved below for completeness.

Reference texts. Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery (5th ed.) — activated-sludge kinetics, solids/hydraulic retention time, nitrogen and phosphorus forms; Davis & Cornwell, Introduction to Environmental Engineering (6th ed.) — discrete settling theory, indicator organisms, coagulation chemistry; MWH’s Water Treatment: Principles and Design (3rd ed.) — process selection, softening, rapid and slow sand filtration; Guidelines for Canadian Drinking Water Quality (Health Canada).

Question 5: Activated Sludge – Waste Sludge Volume and Aeration Tank Sizing (25 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. The plant flow, primary effluent $BOD_5$, observed yield, clarifier underflow concentration and target SRT below:

QuantitySymbolValue
Plant flow$Q$10,000 m³/d
Primary effluent $BOD_5$$S_0$120 mg/L
Observed TSS yield$Y_{obs}$0.75 kg TSS/kg $BOD_5$
Clarifier underflow (WAS) concentration$X_u$8,000 mg/L
Target solids retention time$SRT$10 d

Find. (i) the volumetric flow of waste activated sludge per day, $Q_w$; (ii) the aeration-tank volume $V$ needed to hold that biomass at a 10-day SRT.

Approach. Convert the $BOD_5$ load to a daily WAS solids-production rate via the given observed yield, divide by the underflow concentration for $Q_w$, then use the steady-state solids balance $SRT=(MLSS\cdot V)/P_x$ (mass of biomass in the tank turns over once per SRT through wasting) to size the aeration volume.

  1. Daily $BOD_5$ load and WAS solids production. With essentially complete biological removal of the primary effluent $BOD_5$ assumed (no effluent $BOD_5$ is given, and the yield is quoted as an observed/net figure that already reflects endogenous decay), the load applied is $$Q\,S_0=10{,}000\ \tfrac{\text{m}^3}{\text{d}}\times0.120\ \tfrac{\text{kg}}{\text{m}^3}=1200\ \text{kg}\ BOD_5/\text{d}.$$ The waste-sludge TSS production rate follows from the given yield: $$\boxed{P_x=Y_{obs}\,Q\,S_0=0.75\times1200=900\ \text{kg TSS/d}}.$$
  2. WAS volumetric flow. Dividing the daily solids mass by the clarifier underflow concentration ($X_u=8{,}000\ \text{mg/L}=8.0\ \text{kg/m}^3$): $$\boxed{Q_w=\frac{P_x}{X_u}=\frac{900}{8.0}=112.5\ \text{m}^3/\text{d}}.$$
  3. Aeration-tank volume from the SRT solids balance. At steady state the mass of biomass held in the aeration tank ($MLSS\times V$) must turn over once every SRT through wasting at rate $P_x$ (effluent solids taken as negligible), so $$SRT=\frac{MLSS\cdot V}{P_x}\ \Longrightarrow\ V=\frac{P_x\cdot SRT}{MLSS}.$$ No aeration-tank MLSS is stated in the question, so a typical conventional activated-sludge design value $MLSS=3{,}000\ \text{mg/L}=3.0\ \text{kg/m}^3$ is adopted (flagged below).
  4. Solve for $V$. $$\boxed{V=\frac{P_x\cdot SRT}{MLSS}=\frac{900\times10}{3.0}=3{,}000\ \text{m}^3}.$$
Check: assumes (a) essentially complete $BOD_5$ removal across the aeration tank, consistent with the yield being quoted as an observed/net figure; (b) effluent suspended solids are negligible in the SRT solids balance; (c) aeration-tank $MLSS=3{,}000\ \text{mg/L}$, a typical conventional activated-sludge design value (Metcalf & Eddy design-range table, 1,500–4,000 mg/L) since the question does not state one — $V$ scales inversely with whatever MLSS is actually specified or selected.
QuantityResult
$BOD_5$ load, $Q\,S_0$1,200 kg/d
WAS solids production, $P_x$900 kg TSS/d
WAS volumetric flow, $Q_w$112.5 m³/d
Aeration tank volume, $V$ (at MLSS = 3,000 mg/L)3,000 m³
Back to the paper →