18-Env-A4 Water and Wastewater Engineering · December 2019
Question 3 of 5: Wastewater Treatment Plant Process Schematic
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Examination, December 2019 — 18-Env-A4 Water and Wastewater Engineering (3 hours). Question 1 is compulsory; this study resource answers all five questions in full. Reference texts: Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery (5th ed.); MWH’s Water Treatment: Principles and Design (3rd ed.); Davis & Cornwell, Introduction to Environmental Engineering (6th ed.); Guidelines for Canadian Drinking Water Quality (GCDWQ).
Question 3: Wastewater Treatment Plant Process Schematic (25 marks)
not given (assumed 8 mg/L, typical medium-strength domestic sewage)
$\le$ 0.3 mg/L
Coliform
not given (assumed $1\times10^7$ CFU/100 mL, typical raw sewage)
$\le$ 150 CFU/100 mL
Find. A fully labelled process schematic (unit processes, streams, chemical injection points) for a conventional wastewater treatment train, sized to confirm it can meet all five stated effluent limits from this raw sewage.
Approach. Select a conventional liquid train — screening/grit removal, primary clarification, a nitrifying activated-sludge process with return activated sludge (RAS) for ammonia removal, secondary clarification, tertiary filtration for a final TSS/$cBOD_5$ polish, chemical phosphorus removal ahead of the tertiary filter, and UV disinfection — plus a parallel solids train (thickening, anaerobic digestion, dewatering), then check each effluent limit in turn using literature-typical removal fractions and size the two chemical injection points (alkalinity supplementation, ferric chloride) that the raw water quality specifically demands.
Conventional wastewater treatment schematic: screening/grit → primary clarifier (sludge draw-off) → nitrifying activated-sludge aeration tank (alkalinity supplement injected; RAS returned from the secondary clarifier) → secondary clarifier (WAS to solids train) → tertiary filter (FeCl3 injected upstream for chemical P removal; backwash to equalization) → UV disinfection → effluent. Solids train: primary sludge + WAS → thickening → anaerobic digestion → mechanical dewatering → biosolids.
TSS: check the overall removal the train must achieve. $$\text{Overall TSS removal required}=\frac{250-10}{250}=96\%$$ A primary clarifier alone typically removes about 60% of raw TSS: $250\times(1-0.60)=100\text{ mg/L}$ carried into the secondary process. Conventional secondary clarification alone typically achieves only 85–90% overall removal from the raw value — not reliably enough to guarantee 10 mg/L from 250 mg/L raw — which is exactly why the train adds a tertiary (granular or cloth media) filter after the secondary clarifier: filtration is the step that closes the gap and makes the 96% overall removal target routinely achievable. $\boxed{\text{TSS: met, by design of the tertiary filtration step.}}$
$cBOD_5$: check the overall removal the train must achieve. Assuming raw $BOD_5\approx$ raw $cBOD_5$ (nitrifiers have not yet developed in the raw sample), $$\text{Overall }cBOD_5\text{ removal required}=\frac{220-10}{220}=95.5\%$$ Primary clarification removes about 30% of raw $BOD_5$: $220\times(1-0.30)=154\text{ mg/L}$ enters the aeration tank, so the secondary process plus tertiary filter together must remove $$\frac{154-10}{154}=93.5\%$$ of the load reaching them — comfortably inside the 85–98% overall removal range documented for a nitrifying activated-sludge plant with tertiary filtration. $\boxed{cBOD_5:\text{ met.}}$
Ammonia-N: check whether the raw alkalinity can support full nitrification. With a fraction $f_s\approx0.20$ of influent TKN assimilated into new cell mass (typical for conventional activated sludge) and an ammonia-N effluent target of 3.0 mg/L, the nitrogen actually oxidized by the nitrifiers is $$N_{ox}=TKN(1-f_s)-NH_3\text{-}N_{eff}=40(1-0.20)-3.0=29.0\text{ mg/L as N}$$ Nitrification consumes 7.14 mg alkalinity (as $CaCO_3$) per mg of ammonia-N oxidized, so $$\text{Alkalinity consumed}=7.14\times29.0=207.1\text{ mg/L as }CaCO_3$$ against a raw alkalinity of only 100 mg/L, of which roughly 50 mg/L must remain as a residual floor to hold pH in the range nitrifiers tolerate — leaving only $100-50=50\text{ mg/L}$ available to be consumed. $$\text{Alkalinity deficit}=207.1-50=157.1\text{ mg/L as }CaCO_3$$ $\boxed{\text{Ammonia-N target is achievable only with alkalinity supplementation}\approx157\text{ mg/L as }CaCO_3\text{ (lime or soda ash) dosed ahead of/into the aeration tank.}}$ Without it, nitrification would stall as alkalinity and pH collapse well before 3.0 mg/L ammonia-N is reached.
Total phosphorus: size the FeCl3 dose for chemical polishing. Assumed raw TP of 8 mg/L (typical medium-strength domestic sewage, not given by the exam) is reduced by roughly 10% in the primary clarifier and a further 15% by biomass synthesis uptake in the secondary process (conventional, non-enhanced biological treatment): $$TP\text{ at tertiary dosing point}=8\times(1-0.10)\times(1-0.15)=6.12\text{ mg/L}$$ so chemical precipitation must remove $6.12-0.3=5.82\text{ mg/L}$ of phosphorus. Using a standard 1.5:1 Fe:P molar dosing ratio for a low (0.3 mg/L) target and the molar masses $M_{Fe}=55.85$, $M_P=30.97$, $M_{FeCl_3}=162.2\text{ g/mol}$: $$\text{Fe dose}=5.82\times\frac{55.85}{30.97}\times1.5=15.7\text{ mg/L as Fe}\;\Rightarrow\;\text{FeCl}_3\text{ dose}=15.7\times\frac{162.2}{55.85}$$ $$\boxed{\text{FeCl}_3\text{ dose}\approx45.7\text{ mg/L, injected ahead of the tertiary filter}}$$ so the precipitated $FePO_4$ floc is captured in the same filtration step already provided for TSS polishing.
Coliform: check the UV disinfection credit needed. From an assumed raw coliform density of $1\times10^7$ CFU/100 mL down to the 150 CFU/100 mL limit, the required log reduction is $$\log_{10}\!\left(\frac{1\times10^7}{150}\right)=4.8\text{-log}$$ Biological treatment plus tertiary filtration typically credits about 2 to 2.5-log of this on their own (die-off, predation, and physical capture with the solids removed), leaving roughly 2.3–2.8-log for UV to provide — well inside the 3–4-log inactivation of fecal coliform routinely achieved by a standard UV dose in the 30–40 mJ/cm² range. $\boxed{\text{Coliform: met, with margin, at a standard UV design dose.}}$
Question 3 — effluent quality vs. limits (final results)
Parameter
Raw
Train result
Limit
Met?
TSS
250 mg/L
≤ 10 mg/L (via tertiary filtration)
10 mg/L
Yes
$cBOD_5$
220 mg/L
≤ 10 mg/L (93.5% removal across secondary + filter)
Check: the exam gives only TSS, $BOD_5$, alkalinity and TKN for the raw sewage, and only numeric limits for the treated side. Raw total phosphorus (assumed 8 mg/L), raw coliform density (assumed $1\times10^7$ CFU/100 mL), and every removal-efficiency/synthesis fraction used above (primary 60% TSS/30% $BOD_5$/10% TP; 20% TKN assimilated to biomass; 15% biological P uptake; 50 mg/L residual alkalinity floor) are literature-typical design values from Metcalf & Eddy, not exam-supplied data, and are stated explicitly here rather than presented as given.