18-Env-B4 Site Assessment and Remediation · May 2013
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Reference texts: Davis & Cornwell, Introduction to Environmental Engineering, 6th ed.; Freeze & Cherry, Groundwater, 1979; Fetter, Contaminant Hydrogeology, 2nd ed.; LaGrega, Buckingham & Evans, Hazardous Waste Management, 2nd ed.; Suthersan, Remediation Engineering: Design Concepts, 2nd ed.; Leeson & Hinchee (AFCEE), Principles and Practices of Bioventing, 1997; CSA Z768/Z769 (Phase I/II ESA); BC Environmental Management Act & Contaminated Sites Regulation.
The paper instructs candidates to answer any THREE of the FIVE questions in Section A and any TWO of the THREE questions in Section B. All eight questions are answered in full below, since this solution set is used as a complete study resource.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Total hydrocarbon mass spilled (as hexane), soil composition and dry bulk density, porosity, gravimetric water content, initial soil concentration, oxygen-utilization rate for part (i), lab first-order rate constant for part (ii), and the target clean-up level.
| Quantity | Symbol | Value |
|---|---|---|
| Hydrocarbon mass spilled | MHC | 10 tonnes (10,000 kg) |
| Dry bulk density | ρb | 1,410 kg/m3 |
| Total porosity | n | 0.35 |
| Gravimetric water content | w | 25% |
| Initial soil concentration | C0 | 2,600 µg/g dry soil |
| Target concentration | Ct | 200 µg/g dry soil |
| Oxygen utilization rate (field design) | kO2 | 10%/day |
| Lab first-order rate constant | ln(k) | −3.688 |
Find. (i) the design air flowrate for bioventing; (ii) the field remediation time to reach the target concentration under the lab-derived first-order rate; (iii) whether that time is realistic.
Approach. For (i), convert the spill mass and concentration into the volume of soil affected, evaluate the air-filled porosity available to carry injected air, and apply the standard oxygen-utilization design equation; for (ii), apply first-order decay with the lab rate constant.
(iii) Is the answer in (ii) realistic? Not as a field commitment. The lab rate constant comes from a controlled microcosm or column test with optimized temperature, moisture, nutrient supply and oxygen delivery — conditions the field essentially never matches. Field heterogeneity lets injected air bypass fine-grained, low-permeability zones (exactly the concern flagged above for this soil) rather than sweeping through them uniformly; seasonal temperature swings slow microbial kinetics substantially, since biodegradation rates typically follow a Q10-type relationship that can halve the rate for every 10°C drop; and diffusion-limited oxygen and vapour transport through a fine-textured soil is inherently slower than in a well-mixed lab reactor. Field bioventing timelines are commonly two to five times longer than lab-derived first-order estimates as a result. The 103-day figure should therefore be treated as a best-case, lower-bound benchmark — not a design or contractual schedule — and a field pilot-scale respiration test should be run to derive a field-calibrated rate constant before committing to a remediation timeline.
| Quantity | Value |
|---|---|
| Volume of soil affected | ≈ 2,728 m3 |
| Air-filled porosity from given data | ≈ 0 (soil essentially saturated — flagged) |
| Illustrative design air flowrate (θa=0.10) | ≈ 27 m3/d |
| Lab first-order rate constant | 0.0250 d−1 |
| Field remediation time to 200 µg/g | ≈ 103 days (lab-derived, likely optimistic) |