NivaarExam PrepOfficial exam papers ↗

18-Geol-A5 Rock Mechanics · December 2015

Question 5 of 5: RQD, RMR and stand-up time for a tunnel

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams, December 2015 — 04-Geol-A5, Rock Mechanics. Open-book, 3-hour exam; 5 questions of 20 marks each; candidates were instructed to answer only 4 of the 5 — all 5 are answered below as a complete study resource.

Reference texts for this subject:

Question 5: RQD, RMR and stand-up time for a tunnel (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

Given data
Core recovered3.0 m (six 0.5 m runs, Figure Q5)
Point-load calibration pairs(Sc, Is50) MPa: (206.2, 9.1), (221.4, 10.1), (211.3, 9.4), (203.3, 8.9), (205.5, 9.3)
Additional Is50 readings (MPa)9.7, 8.9, 9.1, 10.1, 9.3, 9.7, 9.0, 8.9, 9.9, 9.7
Joint #1parallel to axis, dip 13°, spacing 1.4 m, slightly rough/weathered, continuous, separation 1.0–1.3 mm
Joint #245° to axis, dip 20°, spacing 0.3 m, very rough, discontinuous, separation <<0.1 mm
Groundwaterminimal, <5 L/min at low pressure

[Figure not reproduced: Core recovery box, 6 runs of 0.5 m each, 3.0 m total. See the official exam paper or the cited reference text.]

Figure Q5. Core recovery log as printed on the exam (columns 1–6 = successive 0.5 m runs, 3.0 m of core total). Natural fracture breaks are the diagonal double-line marks; hatched zones are recovered intact core.

Find. (a) RQD; (b) RMR; (c) limiting (max/min) unsupported span; (d) stand-up time over that span range and the reinforcement needed.

Approach. Measure intact-piece lengths directly off the core-recovery log for RQD, calibrate the point-load index against the five paired UCS readings to get a characteristic intact strength, rate the remaining five RMR parameters from the joint data, then read the maximum span/stand-up time and support schedule straight from the exam's own Table 1D/Table 2, with the minimum practical span set by the closer joint spacing.

  1. Part (a) — RQD from the core log. Reading intact-piece lengths off Figure Q5 against its printed metre grid (natural fracture breaks are the diagonal double-line marks) and keeping only pieces ≥0.10 m per run: run 1 → 0.17 m; run 2 → 0.14+0.15+0.19 = 0.48 m; run 3 → 0.21 m; run 4 → 0.10 m; run 5 → 0.25+0.13 = 0.38 m; run 6 → 0.11+0.10+0.13 = 0.34 m; summing over the full 3.0 m recovered: $$RQD=\frac{0.17+0.48+0.21+0.10+0.38+0.34}{3.0}\times100=\frac{1.68}{3.0}\times100$$ $$\boxed{RQD = 56\%\ \text{(Fair, 50-75\% band, RQD rating}=13\text{)}}$$
    Check: piece boundaries were read from the printed core-recovery sketch against its 0.05 m grid (reading tolerance ±0.02–0.03 m per break); the result is reported to the nearest whole percent and sits solidly inside the 50–75% band even allowing for that reading tolerance.
    As a cross-check, the volumetric joint count from the two MAPPED joint sets alone gives Jv=1/1.4+1/0.3=4.05 m−1, RQD=115−3.3Jv≈102% (capped at 100%) — notably higher than the 56% actually measured on the core. This is a real, worth-noting discrepancy rather than an error: the volumetric-joint-count formula only "sees" the two mapped geological joint sets, whereas the physical core additionally breaks along mechanically-induced fractures from drilling and handling, so the directly measured RQD is used for part (b), not the joint-based cross-check.
  2. Part (b) — Calibrate intact strength from the point-load data. Fitting Sc=k·Is50 through the origin by least squares to the five paired readings (rather than assuming the exam's rounded k=24 factor) gives k=22.4; applying this factor to the 10 additional Is50-only readings and averaging all 15 implied UCS values gives a characteristic intact strength of $$\sigma_c \approx 210.5\ \text{MPa}$$ Reading Figure 1's rating-vs-UCS curve at 210.5 MPa (interpolating between the plotted 200 MPa and 240 MPa points) gives a strength rating of 14.6. The RQD rating is 13 (part a). Discontinuity spacing is governed by the closer-spaced Joint #2 (0.3 m, the 200–600 mm band), rating 10. Condition of discontinuities is scored per joint set from Table 1 Section E and the WORSE (governing) set used: Joint #1 (persistent bedding-like joint, separation 1.0–1.3 mm, slightly rough, slightly weathered) scores 0+1+3+6+5=15; Joint #2 (discontinuous, essentially closed, very rough, unweathered) scores a near-perfect 30; the governing value is Joint #1's 15. Groundwater at <10 L/min is a rating of 10 (not the “completely dry” 15). Both joints dip shallowly (13° and 20°, both ≤20°), which Table 1's Section F places in the “dip 0–20°, irrespective of strike” row — Fair — giving an orientation adjustment of −5 for a tunnel. $$RMR = 14.6+13+10+15+10-5 = 57.6 \approx 58$$ $$\boxed{RMR = 58\ \text{(Class III, Fair rock)}}$$
  3. Part (c) — Limiting excavation dimensions. Table 1D's own tabulated anchor point for a Class III (Fair) rock mass is a maximum unsupported span of 5 m (average stand-up time 1 week), so this is taken directly as the maximum practical span. For the minimum practical span, a standard rule of thumb requires the unsupported opening to be at least about 10× the closest discontinuity spacing so that the excavation is not simply undercutting individual joint-bounded blocks; with Joint #2 at 0.3 m spacing, $$\text{min span}=10\times0.3=3.0\ \text{m}$$ $$\boxed{\text{span range} \approx 3.0\text{-}5.0\ \text{m}}$$
    Check: the minimum-span figure is an engineering-judgment rule of thumb (block size vs. opening size), not a tabulated exam value; Table 1D itself only anchors the maximum-span end of this range.
  4. Part (d) — Stand-up time and reinforcement. At the maximum 5 m span, Table 1D's Class III anchor gives an average unsupported stand-up time of about 1 week. Reducing the span toward the 3.0 m minimum lengthens the achievable stand-up time substantially — the Modified Lauffer diagram (Figure 5) places the RMR≈58 boundary, at spans in the 3–5 m range, in the roughly one-month-to-several-months band, i.e. on the order of 10× longer than at 5 m — though this is read as an order-of-magnitude trend from the chart, not a precise value. Over this whole span range, Table 2's Class III (RMR 41–60) row specifies: top heading and bench excavation, 1.5–3 m advance in the top heading, support commenced after every blast and completed within 10 m of the face; systematic rock bolts 4 m long, spaced 1.5–2 m in the crown and walls, with wire mesh in the crown; shotcrete 50–100 mm in the crown and 30 mm in the sides; no steel sets required. $$\boxed{\text{5 m span: support within days; 3 m span: support may be deferred several weeks, but Table 2's Class III schedule governs regardless}}$$
Final results — Question 5
RQD56% (Fair, rating 13)
Characteristic UCS (point-load calibrated)210.5 MPa
RMR58 (Class III, Fair rock)
Max. unsupported span5.0 m (1 week stand-up)
Min. practical span3.0 m (10× closest joint spacing)
Support (Table 2, Class III)4 m bolts @ 1.5–2 m, wire mesh, 50–100 mm crown / 30 mm side shotcrete
Back to the paper →