NivaarExam PrepOfficial exam papers ↗

18-Geol-B3 Site Investigation · May 2018

Question 1 of 4

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams, May 2018 — 04-Geol-B3, Site Investigation (3 hours, open book, 4 questions × 25 marks = 100 marks, essay format).

Reference texts: Clayton, Matthews & Simons, Site Investigation, 2nd ed. (Blackwell Science); Canadian Geotechnical Society, Canadian Foundation Engineering Manual (CFEM), 4th ed.; Hunt, Geotechnical Engineering Investigation Handbook, 2nd ed. (CRC Press); Dunnicliff, Geotechnical Instrumentation for Monitoring Field Performance; Freeze & Cherry, Groundwater; EGBC Geoscience Professional Practice Guidelines; ASTM D1586 (SPT), D1587/D6519 (Shelby tube), D3441/D5778 (CPT/CPTu), D2573 (field vane), D4719 (pressuremeter), D1194 (plate load), D5731 (point load index), D4630 (packer/Lugeon), D5092/D5787 (monitoring well/piezometer construction).

Question 1 (25 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(a) What is a site investigation?

A site investigation is the systematic, staged process of gathering, interpreting and reporting information on the ground and groundwater conditions at and around a proposed (or existing) engineering site, for the specific purpose of informing the planning, design, construction and long-term performance of the works. It combines a desk-based review of existing information with a field and laboratory program — drilling, sampling, in-situ testing, and geotechnical/geological/environmental testing — to build a defensible ground model: the stratigraphy, groundwater regime, engineering properties, and any geohazards present. The investigation is not an end in itself; its output (the geotechnical/geological report) is the technical basis on which foundation type, earthworks, excavation support, dewatering, and construction methods are selected, and against which the contractor's risk and cost are allocated. It is distinct from, and precedes, detailed design: a site investigation characterizes the ground as it actually is, rather than assuming a ground condition and designing to it.

(b) Why is a site investigation important? (at least 5 reasons)

  1. Foundation and structural safety — every structure ultimately bears on or through the ground; without a verified ground model, foundation design defaults to unsubstantiated assumptions that can lead to bearing failure, excessive settlement, or slope/embankment instability.
  2. Cost control — unidentified ground problems (soft/organic deposits, boulders, artesian groundwater) discovered only during construction are far more expensive to resolve than the same condition identified and designed for in advance; the investigation cost is small relative to the downstream cost of a surprise.
  3. Schedule and risk allocation — a documented ground model, ideally as a Geotechnical Baseline Report, allows the ground-related risk to be explicitly priced and allocated between owner and contractor, reducing the likelihood of differing-site-condition claims and construction delay.
  4. Regulatory and code compliance — building codes, provincial legislation and professional practice guidelines (e.g. EGBC's) require the engineer of record to have a documented, adequate basis for the geotechnical design, which only a proper investigation provides; a design without one is not a defensible professional record.
  5. Environmental and life-safety hazard identification — the investigation is often the only opportunity to detect subsurface contamination, liquefiable soil, active faulting, or slope instability before people, structures, or the environment are exposed to that hazard.
  6. Constructability — groundwater level, rock rippability, and obstruction data drive the contractor's means and methods (dewatering, shoring, excavation equipment selection), so an inadequate investigation increases construction risk even where the final design itself is adequate.

(c) Overall design process for a site investigation (steps)

The process is staged, each step narrowing uncertainty and informing the scope of the next, with a feedback loop back to the ground model if construction reveals conditions the investigation did not anticipate:

Desk Study(records, geology,prior investigations)SiteReconnaissancePreliminaryHazard IDScope & PlanField ProgramField Exploration(drill / sample /in-situ test)LaboratoryTestingInterpretation &Ground ModelGeotechnicalReportfeedback if groundconditions differ atconstruction
Fig. 1 — The site investigation process: each stage narrows ground-model uncertainty and scopes the next; the report closes the loop back to the desk-study ground model if construction exposes different conditions.

In more detail: (1) Desk study — compile geological maps, aerial photography, prior investigations, well records and utility data to build a preliminary ground model; (2) Site reconnaissance — a walkover to verify the desk study against actual surface conditions (outcrops, seepage, existing distress, access constraints); (3) Preliminary hazard identification — flag credible geohazards (soft ground, slope instability, contamination, seismic considerations) that should drive the field scope; (4) Scope and plan the field program — decide exploration method, spacing, depth, and in-situ/laboratory testing based on the ground model and project risk; (5) Field exploration — drilling, sampling and in-situ testing, executed and logged to industry-standard practice; (6) Laboratory testing — index and strength/consolidation testing of recovered samples; (7) Interpretation and ground model — integrate field and lab data into stratigraphic cross-sections, design parameters, and a defensible ground model; (8) Geotechnical report — document findings, interpretation, and design recommendations, subject to internal peer review before issue; the process closes with construction verification (as-built confirmation against the design ground model), feeding back into the ground model, and into future investigations, if actual conditions differ.

(d) Contracting between client and contractor; industry-standard contract types

Contracting for the execution of a site investigation is normally a distinct, earlier procurement from the construction contract itself: the client (owner) engages a geotechnical/geoscience consultant (or, on a design-build project, the design-builder engages one) to scope and manage the investigation, and the drilling/field contractor is separately retained (usually competitively tendered) to execute the drilling, sampling and in-situ testing under the consultant's specification and field supervision. The consultant defines the scope (borehole locations, depths, sampling frequency, testing program) in a tender package; contractors bid against a schedule of rates (cost per metre drilled, per sample, per test) rather than a lump sum, because the actual ground conditions — and therefore the effort required — are not fully known until drilling begins. The most common industry-standard arrangements are: unit-price (schedule-of-rates) contracts, the default for exploratory drilling, where the contractor is paid per unit of measured work (metres drilled by method, number of samples, number of in-situ tests) and the final total varies with actual ground conditions encountered; time-and-materials (cost-reimbursable) contracts, used where the scope is genuinely open-ended (e.g. exploratory work in poorly known ground, or emergency response) and the contractor is paid for verified labour, equipment and materials plus a fee; and lump-sum contracts, used only where the scope is precisely fixed and well-understood (e.g. a specified number of boreholes to a fixed depth in known, easily-drilled ground), since a lump sum poorly accommodates the ground-condition uncertainty inherent to exploration work. For the subsequent construction contract (once design is complete), the same range of arrangements recurs at a larger scale — unit-price, lump-sum (stipulated-sum), cost-plus, and design-build/EPC — with a Geotechnical Baseline Report increasingly used on unit-price and design-build construction contracts specifically to state the ground conditions the contractor is entitled to assume for bidding, allocating (rather than leaving ambiguous) the risk of conditions differing from that baseline.

(e) Resources acquired during the desk study; where and how to obtain them

The desk study assembles existing information before any field work is committed, so that the field program can be targeted rather than exploratory-by-guesswork. Typical resources, and their sources:

ResourceWhat it providesWhere/how obtained
Published geological maps (bedrock & surficial)Regional stratigraphy, structure, likely soil/rock unitsProvincial geological survey; Geological Survey of Canada map library (often free digital download)
Topographic mapping & aerial/satellite imageryTerrain, drainage, slope, land-use history (time-sequence imagery reveals old channels, slope scarps, fill)Provincial base-mapping agency; national air photo libraries; commercial satellite imagery providers
Prior geotechnical/geological reports & borehole logsDirect subsurface data for the same or an adjacent siteClient/owner's own archive; consultant's project files; provincial water-well/borehole registries (often a searchable public database)
Soil/terrain survey mappingSurficial soil classification, organic/sensitive-soil flagsProvincial agriculture or terrain-classification agency
Seismic hazard dataDesign ground motion, liquefaction screening inputsNational Building Code of Canada seismic hazard tool; Natural Resources Canada
Utility & right-of-way recordsBuried service locations to avoid during drillingOne-call/utility-locate service; municipal/utility as-built drawings
Environmental/contamination recordsKnown or suspected contamination, prior land useProvincial environmental site registry; municipal records; historical fire-insurance/land-use maps
Applicable codes, standards & legislationDesign and regulatory framework the investigation must satisfyNational Building Code, provincial building/engineering acts, CSA/ASTM standards, EGBC practice guidelines
ItemAnswer
1(a)Systematic staged desk + field + lab program to characterize ground/groundwater conditions and build the ground model that underpins design, construction and risk allocation
1(b)Safety, cost control, schedule/risk allocation, code compliance, hazard identification, constructability (≥5 reasons)
1(c)Desk study → reconnaissance → hazard ID → scope/plan → field exploration → lab testing → interpretation/ground model → report → construction verification (feedback loop) — Fig. 1
1(d)Consultant contracted by client, driller separately tendered against consultant's spec; unit-price (schedule-of-rates) is the industry default for exploration, with time-and-materials and lump-sum used where warranted; GBR allocates ground risk on the construction contract
1(e)Geological/topographic maps, imagery, prior reports/borehole registries, terrain mapping, seismic hazard data, utility records, environmental registries, codes/standards — see table
← Paper overview