23-Ind-A2 Analysis and Design of Work · December 2015
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Exams — December 2015 — 98-Ind-A2 Analysis and Design of Work. Three-hour, closed-book exam (approved Casio/Sharp calculator only); any five of the seven questions constitute a complete paper and only the first five answered in the answer book are marked — all seven are solved below for completeness. The source prints Question 3's second and third sub-parts both labelled “(iii)” in the question text (and the marking-scheme line repeats “(ii)” for the same slot) — a typesetting slip; they are answered here in the marking-scheme order (i)/(ii)/(iii), 8/6/6 marks.
Reference texts: Niebel & Freivalds, Niebel’s Methods, Standards, and Work Design (13th ed.) — operations analysis and process/flow charting, motion economy, multiple-machine assignment, stopwatch time study, performance rating and allowances, predetermined time systems (MTM/MOST), work sampling, and wage-incentive and job-evaluation systems.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Work sampling estimates the proportion of time spent by a worker, machine, or group in defined activity categories (working, idle, on allowance, waiting for material) by taking a large number of instantaneous, randomly timed observations, rather than by continuously timing a single cycle with a stopwatch. Its basic purpose is to obtain a statistically reliable estimate of an activity proportion at a fraction of the observer cost and worker intrusion of continuous stopwatch study, and it applies well precisely where continuous timing is impractical.
Its applications include: (1) measuring machine or labour utilization across a shift or department; (2) determining the empirical size of personal, fatigue and delay allowances directly from observed idle categories, rather than assuming a traditional fixed percentage; (3) establishing time standards for long-cycle, irregular or group work by combining the observed working proportion with a performance rating and an output count, exactly as done in part (ii) below; (4) measuring the percentage of time spent on each of several jobs in a mixed-work or indirect-labour environment; and (5) auditing existing standards for method drift without the cost of a full re-study.
Given.
| Quantity | Value |
|---|---|
| Total observations, $N$ | 150 |
| Observations operator idle | 50 |
| Average performance rating | 150% |
| Total time worked per day | 480 min |
| Pieces produced per day | 250 |
| Allowances | 5% personal + 5% delays + 5% fatigue = 15% |
Find. The standard time for the operation, in min./pc.
Approach. Convert the idle-observation count to a working percentage, apply it and the average rating to the day’s total time to get the day’s normal time, divide by output to get normal time per piece, then apply the 15% allowance.
| Quantity | Value |
|---|---|
| Working time, day 1 | 66.67% |
| Normal time, $NT$ | 1.92 min/pc |
| Standard time, $ST$ | 2.208 min/pc |
Given. Day-2 observations $N_2=300$; operator found idle 75 times; confidence level 99% ($z=2.576$).
Find. The absolute and relative accuracy of the estimated proportion of idle time.
Approach. Each observation is a Bernoulli trial (idle / not idle), so the count of idle observations is binomial; with $N_2p$ and $N_2(1-p)$ both well above 5, the normal approximation applies and the standard proportion confidence-interval formula gives the absolute accuracy directly, with the relative accuracy obtained by dividing by $p$.
| Quantity | Value |
|---|---|
| Idle proportion, $p$ | 25.0% |
| Absolute accuracy (99%) | ±6.44 percentage points |
| Relative accuracy (99%) | ±25.76% of $p$ |