NivaarExam PrepOfficial exam papers ↗

23-Ind-A3 Facilities Planning · May 2015

Question 5 of 7: Buffer Design in Flow Lines, and Muther's Systematic Layout Planning (SLP) Procedure

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — May 2015 — 98-Ind-A3 Facilities Planning. Three-hour, closed-book exam (Casio or Sharp approved calculator only); any five of the seven questions constitute a complete paper and only the first five answered in the answer book are marked — all seven are solved below for completeness.

Reference texts: Tompkins, White, Bozer & Tanchoco, Facilities Planning (4th ed., Wiley) — the facilities-planning hierarchy, the facilities planning process, layout types, computer-integrated manufacturing and automated storage/retrieval, machine space requirements, Muther's Systematic Layout Planning (SLP) procedure, computerized layout algorithms (CRAFT/CORELAP), and material handling equipment; Niebel & Freivalds, Niebel’s Methods, Standards, and Work Design (13th ed.) — assembly-line balancing (Ranked Positional Weight technique), buffer/decoupling design, operator-paced line speed, JIT and lean/waste-elimination concepts.

Question 5: Buffer Design in Flow Lines, and Muther's Systematic Layout Planning (SLP) Procedure (20 marks: i–6, ii–6, iii–8)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(i) Purpose of Buffer Design and Decoupling Techniques

The purpose of buffer design in flow lines is to protect the line's overall throughput from station-to-station variability and stoppages. Even a well-balanced line (like the 7-station line of Question 3(iii)) has stations whose actual cycle time varies (machine micro-stops, operator pace variation, quality rework) or that fail outright; without any buffer, every station is rigidly synchronous with every other, so a stoppage or slowdown at ANY one station immediately propagates and stops the entire line (the disadvantage noted in Question 2(i) for progressive/line layout). A buffer — a small amount of work-in-process inventory held between stations — decouples the stations' short-term timing from one another, so that a downstream station can keep working from buffer stock while an upstream station is stopped (and an upstream station can keep producing into the buffer while a downstream station is stopped), preserving overall line throughput despite local disruptions.

The two buffering techniques that use decoupling for this purpose are: (1) in-line (inter-station) storage buffers — a small bank of work-in-process parts physically held in a queue or accumulating conveyor section between two adjacent stations, sized to bridge the expected duration of a typical short stoppage; and (2) parallel stations (redundant/duplicate workstations) — providing two or more stations in parallel to perform the same operation, so that if one fails or falls behind, the parallel station(s) continue processing and the line's overall capacity is not reduced to zero at that point. Both achieve the same decoupling objective — breaking the strict one-to-one timing dependency between adjacent operations — by different physical means: storage buffers decouple in TIME (absorbing a temporary rate mismatch), while parallel stations decouple in CAPACITY (providing redundant capacity so a single failure does not stop the flow).

(ii) Two Major Costs of Providing a Buffer

The two major costs involved in providing a buffer are: (1) the carrying cost of the work-in-process inventory held in the buffer — capital tied up in partially completed units sitting idle, plus the risk of damage, obsolescence or quality issues accumulating undetected across a larger in-process inventory; and (2) the cost of the space and equipment needed to hold the buffer — the floor space, conveyor/accumulation hardware, and (for the parallel-station technique) the capital cost of the duplicate station itself, all of which increase the facility's footprint and capital investment. Buffer sizing is therefore a genuine trade-off, not a free improvement: a larger buffer improves the line's resilience to station stoppages but at the direct cost of more work-in-process capital, more floor space, and (for parallel stations) more duplicated equipment — the buffer/decoupling decision in Question 5(i) must be sized against these costs, not maximized without limit.

(iii) Muther's Systematic Layout Planning (SLP) Procedure

Systematic Layout Planning, developed by Richard Muther, is a structured, repeatable procedure for converting facility data into an evaluated, selected layout. It proceeds through the following steps, illustrated in the flowchart below:

1. Input Data & Activities (P—Q—R—S—T)2. Flow of Materials(From–To Chart)3. Activity Relationships(REL Chart)4. Relationship Diagram5a. Space Requirements5b. Space Available6. Space Relationship Diagram7. Modifying Considerations 8. Practical Limitations9. Develop Layout Alternatives10. Evaluate & Select Layout
Fig. 4 — Muther's Systematic Layout Planning (SLP) procedure: two input analyses (flow of materials, activity relationships) converge into a relationship diagram, which is combined with space data into a space relationship diagram, then adjusted and developed into evaluated layout alternatives.

1. Input data and activities (P–Q–R–S–T). Gather the Product(s), Quantity, process Routing, Supporting services, and Timing data that everything downstream depends on.

2. Flow of materials. Analyze the quantitative flow between activities (a from–to chart of volumes/loads/trips), applicable where material flow is the dominant siting criterion.

3. Activity relationships. Build the qualitative REL chart (A-E-I-O-U-X closeness ratings with reason codes) capturing closeness needs that flow volume alone does not (supervision, shared services, safety, noise).

4. Relationship diagram. Combine the flow and relationship data into a single schematic diagram that places activities so high-value relationships are drawn close and undesirable ones (X) are drawn far apart — a topology, not yet a scaled layout.

5. Space requirements and space available. Determine how much area each activity needs (Question 3(i)/(ii)) and compare it against the area actually available on the chosen site or building.

6. Space relationship diagram. Superimpose the space data onto the relationship diagram, so the schematic topology becomes a scaled arrangement reflecting both closeness and area.

7. Modifying considerations. Adjust the space relationship diagram for factors the relationship/space data alone do not capture — building shape, column grid, fire/safety codes, personnel preferences.

8. Practical limitations. Further adjust for hard constraints — budget, existing structure that cannot be moved, phased-construction requirements — that any candidate layout must respect.

9. Develop layout alternatives. Generate several distinct candidate layouts satisfying the adjusted space relationship diagram, whether manually or via a computerized layout algorithm (CRAFT/CORELAP, Question 4(ii)).

10. Evaluate and select. Score each alternative against the facility's objectives and select the layout to implement — the same evaluate-and-select logic used generically in the facilities planning process (Question 1(ii)).

SLP's defining feature is that it always proceeds from data (flow, relationships) toward a scaled, evaluated layout, never the reverse — a planner is not meant to sketch a layout first and then rationalize it against the data, precisely because that ordering is what causes locally attractive but globally poor layouts.