NivaarExam PrepOfficial exam papers ↗

23-Ind-A4 Production Management · December 2015

Question 2 of 7: EOQ for Plastic Fasteners

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Technical Examinations — December 2015 — 98-Ind-A4 Production Management. Three-hour, closed-book exam; Casio or Sharp approved calculators only. Format: seven questions, each worth 20 marks (sub-part weights as tabulated on the front page); only the first five questions appearing in the answer book are marked, so candidates effectively choose 5 of 7. All seven are solved below for completeness. The paper asks for point-form answers wherever possible; the solutions below use full working for clarity.

Reference texts: Nahmias & Olsen, Production and Operations Analysis (7th ed., Waveland/McGraw-Hill) — forecasting, inventory (EOQ) and aggregate planning; Sipper & Bulfin, Production: Planning, Control, and Integration — production-management systems; Hillier & Lieberman, Introduction to Operations Research (11th ed.) — LP formulation and project scheduling (CPM/PERT); Pinedo, Scheduling: Theory, Algorithms, and Systems (5th ed.) — parallel-machine scheduling, makespan and tardiness; Hopp & Spearman, Factory Physics (3rd ed.) — variability and production-system inefficiency; Niebel & Freivalds, Methods, Standards, and Work Design — division of labour and work-design history; ISO 9001:2015 and the Toyota Production System literature — quality management, 5S/lean and TPM.

Question 2: EOQ for Plastic Fasteners (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

QuantityValue
Usage rate6,000 fasteners/week (52 operating weeks/yr) $\Rightarrow D=312{,}000$/yr
Unit cost $c$0.002 cents $=\$0.00002$ each
Order cost $S$$\$12$/order
Holding cost rate25% of unit cost, annualized $\Rightarrow H=0.25c=\$0.000005$/unit-yr

Find. (a) Order interval and EOQ; (b) total annual ordering+holding cost at the EOQ; (c) the cost of continuing to order the part-(a) quantity if true demand is 12,000/week; (d) the true optimal cost at 12,000/week, and the difference.

Approach. Apply the classical EOQ model $Q^*=\sqrt{2DS/H}$ to get the order quantity and interval, then evaluate the total ordering+holding cost function $TC(Q)=\frac{D}{Q}S+\frac{Q}{2}H$ at the part-(a) quantity under both the original and the corrected demand, and separately at the true optimum for the corrected demand, to isolate the cost of having used the wrong order quantity.

  1. Economic order quantity (part a). $$Q^*=\sqrt{\frac{2DS}{H}}=\sqrt{\frac{2(312{,}000)(12)}{0.000005}}=\boxed{Q^*\approx1{,}223{,}765\ \text{fasteners}}.$$ Orders per year $=D/Q^*=312{,}000/1{,}223{,}765\approx0.255$/yr, i.e. an order interval of $52/0.255\approx\boxed{204\ \text{weeks}\approx3.9\ \text{years}}$.
  2. Total annual ordering + holding cost at $Q^*$ (part b). $$TC(Q^*)=\frac{D}{Q^*}S+\frac{Q^*}{2}H=\frac{312{,}000}{1{,}223{,}765}(12)+\frac{1{,}223{,}765}{2}(0.000005)=\boxed{\$6.12/\text{yr}}.$$
  3. Cost if actual demand is 12,000/week but still ordering $Q^*$ from (a) (part c). True annual demand is now $D_2=12{,}000\times52=624{,}000$/yr, double the forecast, but the order quantity is still the part-(a) value: $$TC_{\text{wrong }Q}=\frac{D_2}{Q^*}S+\frac{Q^*}{2}H=\frac{624{,}000}{1{,}223{,}765}(12)+\frac{1{,}223{,}765}{2}(0.000005)=\boxed{\$9.18/\text{yr}}.$$
  4. True optimal cost at 12,000/week (part d). Re-solving the EOQ formula at the corrected demand: $$Q_2^*=\sqrt{\frac{2D_2S}{H}}=\sqrt{\frac{2(624{,}000)(12)}{0.000005}}=1{,}730{,}665\ \text{fasteners},\qquad TC(Q_2^*)=\boxed{\$8.65/\text{yr}}.$$ Ordering the wrong (part-a) quantity instead of the true optimum costs $9.18-8.65=\boxed{\$0.52/\text{yr}}$ more, a $\boxed{6.1\%}$ penalty.
QuantityValue
EOQ (part a), demand as forecast1,223,765 fasteners, every ≈204 weeks (≈3.9 yr)
Total ordering+holding cost at EOQ (part b)\$6.12/yr
Cost using part-a quantity at true 12,000/wk demand (part c)\$9.18/yr
True optimal EOQ and cost at 12,000/wk (part d)1,730,665 fasteners; \$8.65/yr
Penalty for having used the wrong EOQ\$0.52/yr (6.1% above true optimum)
Check
The computed EOQ (≈1.22 million fasteners, a ≈3.9-year supply) is mathematically correct given the stated data but is an extreme result driven entirely by how cheap the fastener is (\$0.00002 each, so annualized holding cost is only \$0.000005/unit) — the EOQ formula has no awareness of practical limits such as warehouse space, shelf-life/plastic degradation, or minimum-order rules that a real purchasing department would also have to respect; those are not part of the given data and are flagged rather than silently overridden.