NivaarExam PrepOfficial exam papers ↗

23-Ind-B10 Workplace Health and Safety · May 2016

Question 7 of 7: Foundry Overhead-Crane Casting Drop — Causes, Corrective Actions, and Follow-Up

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — May 2016 — 98-Ind-B10 Industrial Safety and Health. Closed book; no calculators permitted. Any five of the seven questions constitute a complete paper; all questions are of equal value (20 marks each). Answers are written in point form but fully, as instructed. Complete answers to all seven questions follow, with assumptions stated where the question invites them.

Reference texts: Brauer, Safety and Health for Engineers, 4th ed.; CCPS (Center for Chemical Process Safety), Guidelines for Risk Based Process Safety; CSA Z1002 Occupational health and safety — Hazard identification and elimination and risk assessment and control; CSA Z1006 Management of work in confined spaces.

Question 7: Foundry Overhead-Crane Casting Drop — Causes, Corrective Actions, and Follow-Up (20 marks: 6/8/6)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(i) Causes of the Accident

The narrative describes a single mechanical failure sequence — the hoist eyebolt assembly failed, the casting fell, and the falling load then caused the cables to snap — but a system-safety reading (Question 1(i)) requires tracing that mechanical event back through every contributing area, not stopping at "the eyebolt broke":

(ii) Corrective Actions Required

  1. Engineering — correct the rigging design — specify lifting hardware (eyebolts, shackles, slings) rated with an adequate safety factor for the actual maximum load including dynamic effects, always loaded in the orientation it is rated for (in-line, not side-loaded), and use multi-point rigging or a spreader bar matched to each casting's geometry and centre of gravity rather than a single-point lift wherever the load shape makes that unreliable.
  2. Engineering — add redundancy to the load path — a secondary restraint (independently rated safety chain or sling) so that a single-component failure does not result in an uncontrolled fall of the entire load.
  3. Inspection and maintenance program — implement (or tighten) a scheduled, documented pre-use and periodic certified inspection of all lifting hardware and the crane itself, with defective components removed from service immediately rather than returned to use pending "monitoring."
  4. Administrative controls — establish and enforce an exclusion zone / no-work-under-suspended-loads rule, with the operator and any ground personnel trained to keep clear of the load's swing and fall path at all times during a lift.
  5. Training — retrain crane operators and riggers on load calculation, correct rigging selection and orientation for irregular castings, and pre-lift inspection of hardware.
  6. PPE — retain and reinforce the head-protection requirement — the incident record itself shows the protective head gear already in place prevented a fatality; continue mandatory hard-hat use in the lifting area as a last-line control, without treating it as a substitute for the engineering and procedural fixes above.

(iii) Follow-Up Action Required

Back to the paper →