NivaarExam PrepOfficial exam papers ↗

23-Ind-B10 Workplace Health and Safety · May 2017

Question 7 of 7: Case Study — Die-Rigging Crane Accident Resulting in Fatal-Risk Head Injury

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Reference texts: Brauer, Safety and Health for Engineers, 4th ed.; CCPS (Center for Chemical Process Safety), Guidelines for Risk Based Process Safety; CSA Z1002 Occupational health and safety — Hazard identification and elimination and risk assessment and control; CSA Z94.4 Selection, use, and care of respirators.

Question 7: Case Study — Die-Rigging Crane Accident Resulting in Fatal-Risk Head Injury (20 marks: 7/7/6)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(i) Determining the Causes of the Accident

Applying the unsafe-act/unsafe-condition framework and root-cause analysis used for accident investigation in this subject, the accident has one immediate cause and several contributing (root) causes:

The determined cause is therefore not simply "the die setter rigged it wrong": it is an unsafe act (an unverified, incorrect rigging point) made possible by the absence of an independent verification step, an attachment point that was not unambiguously distinguishable, and a lift sequence that applied load before confirming the rigging and the die setter's position were both safe.

(ii) Corrective Actions Required

  1. Engineering control — make the correct rigging point unambiguous: modify the die/fixture so the keeper pin cannot physically accept a lifting chain (shield it, recess it, or use a distinct, differently shaped fitting for the die notch), removing the possibility of confusing the two.
  2. Administrative control — require independent rigging verification: implement a mandatory two-person check (each rigger verifies the other's attachment point, not just their own) before any signal to take up slack is given, formalized in a written pre-lift procedure.
  3. Administrative control — sequence the lift with a positive "all clear" step: require both riggers to visually confirm correct rigging AND move to a safe position clear of the load path before any signal to take up slack, rather than signalling as soon as rigging is believed complete.
  4. Formalize a job safety analysis (JSA) for die-handling lifts specifically, covering rigging point identification, verification sequence, and safe positioning during slack take-up and travel, incorporated into a standard operating procedure for this recurring task.
  5. Training — retrain all die setters and crane signal personnel on the revised procedure, the specific failure mode that occurred, and why the extra verification step is required even under production time pressure, reinforced with hands-on demonstration and competency verification.
  6. Load-rated rigging point identification — ensure every fixture handled by crane has its designated lifting points clearly marked (permanently, not just by shape) and that any non-lifting hardware near the lifting points (such as a keeper pin) is visually and physically distinguishable from the rated lifting point.

(iii) Follow-Up Action Required

Back to the paper →