NivaarExam PrepOfficial exam papers ↗

21-Mat-A2 Materials Transport Phenomena · December 2018

Question 5 of 8: Hot-Strip-Mill Transfer-Bar Radiative Cooling — Maximum Slab Thickness and Annual Capacity

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — December 2018 — Met-A2 Metallurgical Rate Phenomena. Three-hour, open-book exam; any Casio or Sharp approved calculator permitted. Candidates answer Question 1 (compulsory) plus any four of Questions 2–8; the five answered count equally (20 marks each). All eight are solved below for completeness. Candidates were told to state any interpretive assumptions where doubt exists.

Reference texts: Geiger, G. H. & Poirier, D. R., Transport Phenomena in Materials Processing (TMS) — the primary reference for the momentum-, heat- and mass-transfer analyses in Questions 3, 5, 6, 7 and 8; Szekely, J., Evans, J. W. & Sohn, H. Y., Rate Phenomena in Process Metallurgy — reactor-network and interfacial mass-transfer modelling (Questions 2, 3); Welty, J. R. et al., Fundamentals of Momentum, Heat and Mass Transfer — dimensional analysis and pipe-friction data (Questions 4, 7); Gaskell, D. R., Introduction to the Thermodynamics of Materials — Fe–C phase relations (Question 1h).

Note on the questions
Question 8 specifies a fill hole of explicit length $L$ and asks whether to increase $L$, and it is solved below from first principles. Question 5 asks for the maximum thickness of slab and adds an explicit instruction to justify the four simplifying assumptions rather than merely state them.

Question 5: Hot-Strip-Mill Transfer-Bar Radiative Cooling — Maximum Slab Thickness and Annual Capacity (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

QuantitySymbolValue
Steel density$\rho$7450 kg/m$^3$
Specific heat$C_p$0.45 kJ/kg·K = 450 J/kg·K
Emissivity$\varepsilon$0.8
Exit (initial) temperature$T_0$1590 K
Minimum entry (final) temperature$T_f$1422 K
Minimum inter-slab lag$t_{avail}$5 s
Coiling speed$V_{coil}$20 m/s
Final strip thickness$\delta_{strip}$2.3 mm
Slab (strip) width$w$1.21 m
Current transfer-bar thickness$\delta_0$32 mm

Find. The gauge (thickness) of transfer bar the 5 s / 1422 K thermal constraint permits, and in which direction it is bounded; the mill's new theoretical annual tonnage; and a brief justification for neglecting through-thickness gradients, natural convection, roller conduction and back-radiation.

Approach. Write an unsteady, two-sided (top+bottom), radiation-only lumped-capacitance energy balance for a slab element of thickness $\delta$, integrate it to get cooling time as a function of thickness, then invert it at the 5 s window to get the critical gauge — and check which side of that gauge is actually feasible, since the question's word "maximum" presumes a ceiling; separately compute the mill's fixed downstream (coiler-limited) mass throughput for the annual-capacity figure.

  1. Radiative cooling energy balance. For a slab of thickness $\delta$ radiating from both faces (area $A$, volume $A\delta$), with the surroundings taken as a cold background (back-radiation neglected, justified in Step 5): $$\rho A\delta C_p\,\dfrac{dT}{dt}=-2A\varepsilon\sigma T^4\ \Rightarrow\ \dfrac{dT}{T^4}=-\dfrac{2\varepsilon\sigma}{\rho\delta C_p}\,dt$$ Integrating from $(T_0,0)$ to $(T,t)$: $$\boxed{t(\delta)=\dfrac{\rho\delta C_p}{6\varepsilon\sigma}\left(\dfrac{1}{T^3}-\dfrac{1}{T_0^3}\right)}$$ Every term in this balance is per unit plan area of slab, so the only geometric variable it contains is the thickness $\delta$ — and $t$ is linear and increasing in $\delta$, which is what decides the direction of the bound in Step 4.
  2. Current 32 mm transfer bar — implied cooling time to 1422 K. $$t(0.032)=\dfrac{(7450)(0.032)(450)}{6(0.8)(5.67\times10^{-8})}\left(\dfrac{1}{1422^3}-\dfrac{1}{1590^3}\right)=\boxed{39.0\ \text{s}}$$ This is the time a 32 mm bar takes to radiate its way down from 1590 K to exactly 1422 K — nearly 8× longer than the stated 5 s minimum lag, so the current gauge carries a large thermal margin.
  3. Critical thickness for a 5 s window. Solving Step 1 for $\delta$ at $t=5$ s: $$\delta_{crit}=\dfrac{6\varepsilon\sigma\,t_{avail}}{\rho C_p\left(1/T_f^3-1/T_0^3\right)}=\boxed{4.10\ \text{mm}}$$ This is the one gauge the given data actually pins down: it is the thickness whose cooling time is exactly the 5 s window.
  4. Which side of $\delta_{crit}$ is feasible — the constraint is a floor, not a ceiling. Because $t(\delta)$ is linear and increasing in $\delta$ (Step 1), a thinner section carries more radiating area per unit thermal mass and therefore cools faster. Any bar thinner than $\delta_{crit}\approx4.10$ mm drops below 1422 K inside the 5 s window; every bar at or above it — including the current 32 mm gauge, by a factor of nearly 8 — stays compliant, and stays more compliant the thicker it gets. There is no way for a slab to be too thick to hold 1422 K over a fixed radiative-cooling window, so the constraint admits no finite maximum: the question's word "maximum" is the wrong sense for the physics it supplies. $$\boxed{\delta_{crit}=4.10\ \text{mm is the critical gauge; the 5 s/1422 K constraint sets it as a }\textbf{minimum}\text{ viable thickness, not a maximum — any }\delta\ge4.10\ \text{mm is admissible, and the current 32 mm transfer bar clears it with an }8\times\text{ margin}}$$ Reporting the 4.10 mm figure together with the direction of the inequality is the honest answer: the superintendent's proposal to lengthen the slabs is not limited by this radiative-cooling constraint at all, and any real cap on transfer-bar gauge or length would come from non-thermal factors outside this problem's scope — rougher-stand draft schedule, reheat-furnace hearth length, coiler mandrel/coil-weight rating, or crane and handling limits — none of which are given here.
  5. Justifying the four neglected mechanisms.
    • Temperature gradients across the slab (lumped-capacitance assumption). A rough Biot-number check, $Bi=h_{rad}(\delta/2)/k_{steel}$ with a linearized radiative coefficient $h_{rad}\approx4\varepsilon\sigma T^3\approx4(0.8)(5.67\times10^{-8})(1500)^3\approx 610$ W/m$^2$K and $k_{steel}\approx30$ W/m·K, gives $Bi\approx610(0.016)/30\approx0.33$ — small enough (well under 1) that a single representative temperature through the 32 mm thickness is a reasonable exam-level approximation, though not a negligible correction in a rigorous design calculation.
    • Natural convection from the slab surfaces. Free-convection coefficients in air are typically $h_{conv}\sim10$–$30$ W/m$^2$K, versus the effective radiative coefficient of order 600 W/m$^2$K estimated above at $\sim$1500 K (radiation scales as $T^4$, so it dominates overwhelmingly at these temperatures) — convection is at most a few percent correction and is safely dropped.
    • Conduction into the support rollers. Contact between the moving bar and each roller is both brief (rolling contact, not stationary) and confined to a small fraction of the bar's total surface area at any instant, compared with the large, continuously-radiating top and bottom faces — the conductive heat sink is small in both area and duration relative to the radiative loss.
    • Back-radiation from the plant. The net radiative exchange is $\propto(T_{slab}^4-T_{surr}^4)$; with $T_{surr}\sim300$ K versus $T_{slab}\sim1500$ K, $T_{surr}^4/T_{slab}^4\sim(300/1500)^4=0.0016$, under 0.2% of the slab's own emissive term — negligible.
  6. Mill's fixed downstream throughput. The finishing train's own speed/gauge limits (20 m/s at 2.3 mm) set the mass flow rate irrespective of transfer-bar thickness or length (mass is conserved from transfer bar through to coiled strip): $$\dot m=\rho\,w\,\delta_{strip}\,V_{coil}=(7450)(1.21)(0.0023)(20)=\boxed{414.7\ \text{kg/s}}$$
  7. Annual capacity (24 h/day, 365 d/yr, no shutdowns). $$\text{Annual tonnage}=\dot m\times(3600\times24\times365)=414.7\times3.156\times10^7\ \text{s}=\boxed{1.31\times10^7\ \text{tonnes/yr}\ (\approx13.1\ \text{Mt/yr})}$$
QuantityValue
Cooling time, current 32 mm bar≈ 39.0 s (8× the 5 s minimum)
Critical gauge for a 5 s window, $\delta_{crit}$≈ 4.10 mm
Sense of the bounda minimum viable thickness, not a maximum (Step 4) — no finite ceiling exists on these data
Mass flow rate (coiler-limited)414.7 kg/s
Theoretical annual capacity≈ 1.31×10&sup7; tonnes/yr
Check
The paper asks for a "maximum thickness", but the governing balance makes thickness a stabilising variable: $t(\delta)\propto\delta$, so compliance improves monotonically with gauge and the 5 s/1422 K window can only ever set a lower bound. The single number the data determine is $\delta_{crit}=4.10$ mm, and it is reported here with the direction of the inequality stated explicitly (Step 4) rather than relabelled to match the question's wording. The annual-capacity figure is unaffected by any of this, being set entirely by the fixed downstream coiling speed and finished gauge, independent of the transfer bar's own thickness or length.