21-Mat-A2 Materials Transport Phenomena · December 2018
Question 5 of 8: Hot-Strip-Mill Transfer-Bar Radiative Cooling — Maximum Slab Thickness and Annual Capacity
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Exams — December 2018 — Met-A2 Metallurgical Rate Phenomena. Three-hour, open-book exam; any Casio or Sharp approved calculator permitted. Candidates answer Question 1 (compulsory) plus any four of Questions 2–8; the five answered count equally (20 marks each). All eight are solved below for completeness. Candidates were told to state any interpretive assumptions where doubt exists.
Reference texts: Geiger, G. H. & Poirier, D. R., Transport Phenomena in Materials Processing (TMS) — the primary reference for the momentum-, heat- and mass-transfer analyses in Questions 3, 5, 6, 7 and 8; Szekely, J., Evans, J. W. & Sohn, H. Y., Rate Phenomena in Process Metallurgy — reactor-network and interfacial mass-transfer modelling (Questions 2, 3); Welty, J. R. et al., Fundamentals of Momentum, Heat and Mass Transfer — dimensional analysis and pipe-friction data (Questions 4, 7); Gaskell, D. R., Introduction to the Thermodynamics of Materials — Fe–C phase relations (Question 1h).
Note on the questions
Question 8 specifies a fill hole of explicit length $L$ and asks whether to increase $L$, and it is solved below from first principles. Question 5 asks for the maximum thickness of slab and adds an explicit instruction to justify the four simplifying assumptions rather than merely state them.
Question 5: Hot-Strip-Mill Transfer-Bar Radiative Cooling — Maximum Slab Thickness and Annual Capacity (20 marks)
Find. The gauge (thickness) of transfer bar the 5 s / 1422 K thermal constraint permits, and in which direction it is bounded; the mill's new theoretical annual tonnage; and a brief justification for neglecting through-thickness gradients, natural convection, roller conduction and back-radiation.
Approach. Write an unsteady, two-sided (top+bottom), radiation-only lumped-capacitance energy balance for a slab element of thickness $\delta$, integrate it to get cooling time as a function of thickness, then invert it at the 5 s window to get the critical gauge — and check which side of that gauge is actually feasible, since the question's word "maximum" presumes a ceiling; separately compute the mill's fixed downstream (coiler-limited) mass throughput for the annual-capacity figure.
Radiative cooling energy balance. For a slab of thickness $\delta$ radiating from both faces (area $A$, volume $A\delta$), with the surroundings taken as a cold background (back-radiation neglected, justified in Step 5):
$$\rho A\delta C_p\,\dfrac{dT}{dt}=-2A\varepsilon\sigma T^4\ \Rightarrow\ \dfrac{dT}{T^4}=-\dfrac{2\varepsilon\sigma}{\rho\delta C_p}\,dt$$
Integrating from $(T_0,0)$ to $(T,t)$:
$$\boxed{t(\delta)=\dfrac{\rho\delta C_p}{6\varepsilon\sigma}\left(\dfrac{1}{T^3}-\dfrac{1}{T_0^3}\right)}$$
Every term in this balance is per unit plan area of slab, so the only geometric variable it contains is the thickness $\delta$ — and $t$ is linear and increasing in $\delta$, which is what decides the direction of the bound in Step 4.
Current 32 mm transfer bar — implied cooling time to 1422 K.
$$t(0.032)=\dfrac{(7450)(0.032)(450)}{6(0.8)(5.67\times10^{-8})}\left(\dfrac{1}{1422^3}-\dfrac{1}{1590^3}\right)=\boxed{39.0\ \text{s}}$$
This is the time a 32 mm bar takes to radiate its way down from 1590 K to exactly 1422 K — nearly 8× longer than the stated 5 s minimum lag, so the current gauge carries a large thermal margin.
Critical thickness for a 5 s window. Solving Step 1 for $\delta$ at $t=5$ s:
$$\delta_{crit}=\dfrac{6\varepsilon\sigma\,t_{avail}}{\rho C_p\left(1/T_f^3-1/T_0^3\right)}=\boxed{4.10\ \text{mm}}$$
This is the one gauge the given data actually pins down: it is the thickness whose cooling time is exactly the 5 s window.
Which side of $\delta_{crit}$ is feasible — the constraint is a floor, not a ceiling. Because $t(\delta)$ is linear and increasing in $\delta$ (Step 1), a thinner section carries more radiating area per unit thermal mass and therefore cools faster. Any bar thinner than $\delta_{crit}\approx4.10$ mm drops below 1422 K inside the 5 s window; every bar at or above it — including the current 32 mm gauge, by a factor of nearly 8 — stays compliant, and stays more compliant the thicker it gets. There is no way for a slab to be too thick to hold 1422 K over a fixed radiative-cooling window, so the constraint admits no finite maximum: the question's word "maximum" is the wrong sense for the physics it supplies.
$$\boxed{\delta_{crit}=4.10\ \text{mm is the critical gauge; the 5 s/1422 K constraint sets it as a }\textbf{minimum}\text{ viable thickness, not a maximum — any }\delta\ge4.10\ \text{mm is admissible, and the current 32 mm transfer bar clears it with an }8\times\text{ margin}}$$ Reporting the 4.10 mm figure together with the direction of the inequality is the honest answer: the superintendent's proposal to lengthen the slabs is not limited by this radiative-cooling constraint at all, and any real cap on transfer-bar gauge or length would come from non-thermal factors outside this problem's scope — rougher-stand draft schedule, reheat-furnace hearth length, coiler mandrel/coil-weight rating, or crane and handling limits — none of which are given here.
Justifying the four neglected mechanisms.
Temperature gradients across the slab (lumped-capacitance assumption). A rough Biot-number check, $Bi=h_{rad}(\delta/2)/k_{steel}$ with a linearized radiative coefficient $h_{rad}\approx4\varepsilon\sigma T^3\approx4(0.8)(5.67\times10^{-8})(1500)^3\approx 610$ W/m$^2$K and $k_{steel}\approx30$ W/m·K, gives $Bi\approx610(0.016)/30\approx0.33$ — small enough (well under 1) that a single representative temperature through the 32 mm thickness is a reasonable exam-level approximation, though not a negligible correction in a rigorous design calculation.
Natural convection from the slab surfaces. Free-convection coefficients in air are typically $h_{conv}\sim10$–$30$ W/m$^2$K, versus the effective radiative coefficient of order 600 W/m$^2$K estimated above at $\sim$1500 K (radiation scales as $T^4$, so it dominates overwhelmingly at these temperatures) — convection is at most a few percent correction and is safely dropped.
Conduction into the support rollers. Contact between the moving bar and each roller is both brief (rolling contact, not stationary) and confined to a small fraction of the bar's total surface area at any instant, compared with the large, continuously-radiating top and bottom faces — the conductive heat sink is small in both area and duration relative to the radiative loss.
Back-radiation from the plant. The net radiative exchange is $\propto(T_{slab}^4-T_{surr}^4)$; with $T_{surr}\sim300$ K versus $T_{slab}\sim1500$ K, $T_{surr}^4/T_{slab}^4\sim(300/1500)^4=0.0016$, under 0.2% of the slab's own emissive term — negligible.
Mill's fixed downstream throughput. The finishing train's own speed/gauge limits (20 m/s at 2.3 mm) set the mass flow rate irrespective of transfer-bar thickness or length (mass is conserved from transfer bar through to coiled strip):
$$\dot m=\rho\,w\,\delta_{strip}\,V_{coil}=(7450)(1.21)(0.0023)(20)=\boxed{414.7\ \text{kg/s}}$$
a minimum viable thickness, not a maximum (Step 4) — no finite ceiling exists on these data
Mass flow rate (coiler-limited)
414.7 kg/s
Theoretical annual capacity
≈ 1.31×10&sup7; tonnes/yr
Check
The paper asks for a "maximum thickness", but the governing balance makes thickness a stabilising variable: $t(\delta)\propto\delta$, so compliance improves monotonically with gauge and the 5 s/1422 K window can only ever set a lower bound. The single number the data determine is $\delta_{crit}=4.10$ mm, and it is reported here with the direction of the inequality stated explicitly (Step 4) rather than relabelled to match the question's wording. The annual-capacity figure is unaffected by any of this, being set entirely by the fixed downstream coiling speed and finished gauge, independent of the transfer bar's own thickness or length.