NivaarExam PrepOfficial exam papers ↗

22-Mec-B3 Energy Conversion and Power Generation · December 2016

Question 4 of 6: Steam Plant Heat Rejection

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 07-Mec-B3 Energy Conversion and Power Generation, National Examinations, December 2016. Three hours, closed book. Two sections: Section A is calculative (Questions 1–4) and Section B is descriptive (Questions 5–6). Candidates answer three questions from Section A and one from Section B; four questions of 15 marks each constitute a complete paper (60 marks). Reference data for individual questions are bound in as attachments on pages 9–14, reference formulae and constants on pages 15–18, and Granet & Bluestein steam tables are supplied. All six questions are solved below, because the set is a study resource rather than a timed attempt.

Reference texts.

Where the paper's own attachments carry data that duplicate a computed result — the 392 °C exhaust in Question 2, the 177 °C boiler gas outlet, the 13 kg/s fuel flow, the torque curve on page 9 — those printed values are used as independent checks and the agreement is quoted in each answer.

Question 4: Steam Plant Heat Rejection (15 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Part I, from the page-10 Koeberg condenser data sheet; Part II, from the question page and the page-12 chart:

QuantityPart I (condenser)Part II (tower)
Heat rejected1805 MW (from the water side)1500 MJ/s
Electrical output—600 MW
Cooling water flow141 000 t/hto be found
Cooling water in / out13 °C / 24 °C15 °C / 25 °C
Condensing steam temperature30 °C (0.043 bar abs)30 °C
Terminal temperature difference6 °C—
Steam flow2996 t/h—
Ambient air—30 °C dry bulb, 40 % RH

Find. Part I: the design temperature profile and the new profiles, with ΔT and θ, for four changes of duty. Part II: the circulating-water flow, the evaporative loss in m³/GJ and m³/s, that loss as a percentage of the circulating flow, and the water consumed per kWh generated.

(a) cooling water inlet raised to 18 °Ctube lengthT, °C10203040steam 3518 → 29ΔT = 11 K, θ = 11.5 K(b) turbine load reduced to one quartertube lengthT, °C10203040steam 1713 → 16ΔT = 2.75 K, θ = 2.9 K(c) water flow halved, U to 70 %tube lengthT, °C10203040steam 4013 → 35ΔT = 22 K, θ = 16.4 K(d) U reduced 20 % by foulingtube lengthT, °C10203040steam 3313 → 24ΔT = 11 K, θ = 14.4 K
Part I: design profiles dotted, new profiles solid. In every panel the blue line is the cooling water along the tubes and the red line the condensing steam, which is at constant temperature because it is changing phase. Temperatures are rounded to the nearest degree as the question directs.

Approach. Two equations govern the condenser: the water-side energy balance $\dot Q = \dot m_w c_p \Delta T$ and the transfer equation $\dot Q = UA\,\theta$ written on the average temperature difference as the question permits. Each part changes one term and holds the rest, so ΔT and θ simply scale — no iteration is needed. Part II is a mass and energy balance on the tower with one chart reading.

  1. Part I — the design condition (dotted profiles). From the page-10 data the cooling water rises $\Delta T = 24 - 13 = \boxed{11\ \text{K}}$ and the mean water temperature is $(13+24)/2 = 18.5\ ^\circ\text{C}$, so $$\theta = t_{steam} - \bar t_w = 30 - 18.5 = \boxed{11.5\ \text{K}}$$ The printed terminal temperature difference, $30 - 24 = 6$ K, and the printed condenser pressure of 0.043 bar (saturation temperature 30.0 °C) both confirm the data set is self-consistent. As a final check on the sheet, the water side removes $\dot m_w c_p \Delta T = 39\,167 \times 4.19 \times 11 = 1805$ MW, which over the printed 2996 t/h of steam is 2169 kJ/kg — the latent heat of steam at 30 °C times a quality of 0.89, exactly what a large low-pressure turbine exhausts.
  2. Part I (a) — cooling water inlet raised to 18 °C. The turbine load, the water flow and the surface are all unchanged, so neither $\Delta T$ nor $\theta$ can change: $$\Delta T = 11\ \text{K} \Rightarrow t_{w,out} = 18 + 11 = 29\ ^\circ\text{C}, \qquad t_{steam} = \frac{18+29}{2} + 11.5 = \boxed{35\ ^\circ\text{C}}$$ The whole profile simply lifts by the 5 K added at inlet, and the back pressure rises with it — from 0.043 bar to about 0.056 bar — costing turbine output. This is why summer river or sea temperature is a first-order constraint on station output.
  3. Part I (b) — turbine load reduced to one quarter. Now the duty falls to $0.25\dot Q$ while $\dot m_w$, $U$ and $A$ all hold, so both differences scale directly with the duty: $$\Delta T = 0.25 \times 11 = 2.75\ \text{K} \Rightarrow t_{w,out} = 13 + 2.75 \approx \boxed{16\ ^\circ\text{C}}$$ $$\theta = 0.25 \times 11.5 = 2.875\ \text{K} \Rightarrow t_{steam} = \frac{13 + 15.75}{2} + 2.875 \approx \boxed{17\ ^\circ\text{C}}$$ The condenser is now hugely oversurfaced for the duty, so the steam sits only a few degrees above the incoming water and the back pressure collapses — in practice it would be limited by air in-leakage and by the turbine's own exhaust-loss floor rather than by heat transfer.
  4. Part I (c) — water flow halved and U reduced to 70 %%. Full load returns, but with half the flow the same duty needs twice the temperature rise, and with 70 %% of the coefficient it needs the driving difference divided by 0.7: $$\Delta T = \frac{11}{0.5} = 22\ \text{K} \Rightarrow t_{w,out} = 13 + 22 = \boxed{35\ ^\circ\text{C}}, \qquad \theta = \frac{11.5}{0.7} = 16.4\ \text{K}$$ $$t_{steam} = \frac{13+35}{2} + 16.4 = 40.4 \approx \boxed{40\ ^\circ\text{C}}$$ This is the worst of the four cases: the steam temperature rises 10 K, roughly doubling the back pressure to about 0.074 bar. Note the two effects compound — reducing pump flow to save auxiliary power also degrades the film coefficient inside the tubes, so the coefficient penalty is not independent of the flow reduction.
  5. Part I (d) — overall coefficient reduced 20 %% by fouling. Load and flow are unchanged, so the water still rises 11 K to 24 °C, but the same duty must now be pushed through a poorer surface: $$\theta = \frac{11.5}{0.8} = 14.375\ \text{K} \Rightarrow t_{steam} = 18.5 + 14.4 = 32.9 \approx \boxed{33\ ^\circ\text{C}}$$ so the back pressure rises about 3 K worth, near 0.050 bar. Because this penalty is permanent until the tubes are cleaned, condenser fouling is monitored continuously through exactly this quantity — the difference between measured steam saturation temperature and mean water temperature is the plant's cleanliness factor.
  6. Part II (a) — circulating water flow. All the rejected heat is carried by the water over its 10 K rise: $$\dot m_w = \frac{\dot Q}{c_p \Delta t} = \frac{1\,500\,000}{4.19 \times 10} = 35800\ \text{kg/s} \quad\Rightarrow\quad \dot V_w = \boxed{35.80\ \text{m}^3\text{/s}}$$ Note the 5 K approach between the 25 °C returning water and the 30 °C condensing steam, consistent with the terminal difference of a large condenser.
  7. Part II (b) — evaporative loss from the chart. The page-12 chart is entered on wet bulb against dry bulb, so the 40 % relative humidity at 30 °C must first be converted: the adiabatic-saturation balance gives a wet bulb of 20.1 °C, which lands on the chart's own 40 % dash-dot line and so confirms the entry point. Reading the contour through (30 °C dry bulb, 20.1 °C wet bulb) gives $$\boxed{0.375\ \text{m}^3\text{/GJ rejected}}$$ A useful bound: if every joule left as latent heat the loss would be $1/h_{fg} = 10^6/2430.5/1000 = 0.411\ \text{m}^3\text{/GJ}$, so 0.375 corresponds to 91 % of the duty leaving as evaporation and the balance as sensible heating of the air — the right split for warm, fairly dry air.
  8. Part II (c) and (d) — loss in m³/s and as a percentage. The plant rejects 1500 MJ/s = 1.5 GJ/s, so $$\dot V_{evap} = 0.375 \times 1.5 = \boxed{0.5625\ \text{m}^3\text{/s}}$$ $$\frac{\dot V_{evap}}{\dot V_w} = \frac{0.5625}{35.80} = \boxed{1.57\ \%}$$ A little over 1.5 % of the circulating flow is evaporated on each pass, which is the classic figure for a wet tower on a 10 K range. Make-up must also cover drift and blowdown, so the real intake is appreciably larger — typically half as much again once the cycles of concentration are set.
  9. Part II (e) — water consumed per unit generated. Converting to hourly quantities against the 600 MW sent out, $$\frac{0.5625\ \text{m}^3\text{/s} \times 1000 \times 3600}{600\,000\ \text{kW}} = \boxed{3.375\ \text{L/kWh}}$$ Roughly three and a half litres per kilowatt-hour, or about 2 million litres an hour for the station. This single number is what makes once-through and wet-tower cooling a siting question as much as a thermodynamic one, and it is the figure air-cooled condensers trade efficiency to avoid.
QuantityValue
Part I design ΔT, θ11 K, 11.5 K
(a) water 18 → 29 °C, steam35 °C (ΔT 11 K, θ 11.5 K)
(b) water 13 → 16 °C, steam17 °C (ΔT 2.75 K, θ 2.9 K)
(c) water 13 → 35 °C, steam40 °C (ΔT 22 K, θ 16.4 K)
(d) water 13 → 24 °C, steam33 °C (ΔT 11 K, θ 14.4 K)
Part II (a) cooling water flow35.80 m³/s
Part II (b) evaporative loss0.375 m³/GJ rejected
Part II (c) evaporative loss0.5625 m³/s
Part II (d) percentage of circulating flow1.57 %
Part II (e) consumption per unit generated3.375 L/kWh
CONDENSER1500 MW rejectedNATURAL DRAUGHTCOOLING TOWERhot water 25 °Ccold water 15 °C35.80 m³/s circulatedmoist air outevaporation 0.5625 m³/sair in30 °C db, 40 % RHchart entry: 30 °C dry bulb at 40 % RH → 0.375 m³/GJturbine exhaust steammake-up
Part II: the closed circulating-water loop between condenser and natural draught tower. Of the 35.80 m³/s circulated, 0.5625 m³/s leaves as vapour in the plume and must be replaced as make-up.