22-Mec-B4 Integrated Manufacturing Systems · May 2015
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Exams, May 2015 — 07-Mec-B4 Integrated Manufacturing Systems. Three hours, open book, any non-communicating calculator permitted. Seven questions are printed; any five constitute a complete paper and only the first five appearing in the answer book are marked, each of equal value (20 marks). All seven are solved here, because the complete set is the study resource. Questions 5, 6 and 7 are explicitly essay questions, in which the examiners award marks for clarity and organisation as well as content.
Reference texts. E. S. Buffa and R. K. Sarin, Modern Production / Operations Management, 8th ed. (requirements schedules, economic lot size, economic order interval, part-period balancing, production planning); R. B. Chase and F. R. Jacobs, Operations and Supply Chain Management, 16th ed. (demand components, adaptive forecasting, aggregate planning, statistical quality control); B. W. Niebel and A. Freivalds, Methods, Standards, and Work Design, 13th ed. (time study, performance rating, allowances, wage incentive plans); D. C. Montgomery, Introduction to Statistical Quality Control, 8th ed. (Shewhart charts, process capability); M. P. Groover, Automation, Production Systems, and Computer-Integrated Manufacturing, 5th ed. (process planning, CAPP, machinability data systems, maintenance); S. Nahmias and T. L. Olsen, Production and Operations Analysis, 7th ed. (forecasting, aggregate planning).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. A twelve-week requirements schedule for one purchased motor drive unit, together with the average weekly requirement used by the square-root formulas, the cost of preparing a lot and the cost of carrying one unit for one week.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Requirement (units) | 25 | 30 | 75 | 125 | 200 | 325 | 400 | 100 | 0 | 100 | 0 | 100 |
Average requirement as printed on the paper, $\bar{R}=116.7$ units per week; lot preparation cost $c_{p}=$ $400 per lot; carrying cost $c_{h}=$ $4 per unit per week; planning horizon twelve weeks.
Find. The complete inventory record — order releases and week-ending balances — and the total incremental cost (lot preparation plus carrying) for each of the three lot-sizing policies, and hence the policy that should be adopted.
Approach. Establish the two square-root parameters from the average requirement, then simulate each policy week by week against the tabulated discrete requirements — a lot-size rule is only meaningful once it has been run through the actual schedule — and cost each record as (number of lots)×$c_{p}$ plus $c_{h}$ times the sum of the week-ending balances.
Running that fixed lot against the schedule gives the record below. Weeks 6 and 7 each need more than one lot, which is the first symptom of a policy that ignores the timing of demand.
| Week | Requirement (units) | Receipt (units) | On hand at week end (units) | Carrying charge ($) |
|---|---|---|---|---|
| 1 | 25 | 153 | 128 | 512 |
| 2 | 30 | — | 98 | 392 |
| 3 | 75 | — | 23 | 92 |
| 4 | 125 | 153 | 51 | 204 |
| 5 | 200 | 153 | 4 | 16 |
| 6 | 325 | 459 | 138 | 552 |
| 7 | 400 | 306 | 44 | 176 |
| 8 | 100 | 153 | 97 | 388 |
| 9 | 0 | — | 97 | 388 |
| 10 | 100 | 153 | 150 | 600 |
| 11 | 0 | — | 150 | 600 |
| 12 | 100 | — | 50 | 200 |
| Total | 1480 | 1530 | 1030 | 4120 |
Ten lots are released and the week-ending balances total 1,030 unit-weeks, so the two cost elements and their sum are$$TC_{a}=mc_{p}+c_{h}\sum_{t}I_{t}=10(\$400)+4(1{,}030)=\$4{,}000+\$4{,}120=\boxed{\$8{,}120}$$This is the dearest of the three policies, and the record shows why: the fixed lot is far too large for the opening weeks and far too small for weeks 6 and 7, so it carries stock at both ends of the horizon.
At $T=1$ the policy is lot-for-lot: each week's requirement is ordered in that week, nothing is ever carried into the following week, and the two zero-requirement weeks generate no order at all.
| Week | Requirement (units) | Receipt (units) | On hand at week end (units) | Carrying charge ($) |
|---|---|---|---|---|
| 1 | 25 | 25 | 0 | 0 |
| 2 | 30 | 30 | 0 | 0 |
| 3 | 75 | 75 | 0 | 0 |
| 4 | 125 | 125 | 0 | 0 |
| 5 | 200 | 200 | 0 | 0 |
| 6 | 325 | 325 | 0 | 0 |
| 7 | 400 | 400 | 0 | 0 |
| 8 | 100 | 100 | 0 | 0 |
| 9 | 0 | — | 0 | 0 |
| 10 | 100 | 100 | 0 | 0 |
| 11 | 0 | — | 0 | 0 |
| 12 | 100 | 100 | 0 | 0 |
| Total | 1480 | 1480 | 0 | 0 |
Ten orders are placed — weeks 9 and 11 need none — and carrying cost is zero:$$TC_{b}=10(\$400)+4(0)=\boxed{\$4{,}000}$$Costing the other rounding confirms the choice: at $T=2$ the twelve weeks are covered by six orders ($2,400) but 780 unit-weeks are carried ($3,120) for a total of $5,520, which is $1,520 dearer. The total-cost curve is flat near its minimum, so the rounding genuinely has to be evaluated rather than assumed.
| Week | Requirement (units) | Receipt (units) | On hand at week end (units) | Carrying charge ($) |
|---|---|---|---|---|
| 1 | 25 | 55 | 30 | 120 |
| 2 | 30 | — | 0 | 0 |
| 3 | 75 | 200 | 125 | 500 |
| 4 | 125 | — | 0 | 0 |
| 5 | 200 | 200 | 0 | 0 |
| 6 | 325 | 325 | 0 | 0 |
| 7 | 400 | 500 | 100 | 400 |
| 8 | 100 | — | 0 | 0 |
| 9 | 0 | — | 0 | 0 |
| 10 | 100 | 100 | 0 | 0 |
| 11 | 0 | — | 0 | 0 |
| 12 | 100 | 100 | 0 | 0 |
| Total | 1480 | 1480 | 255 | 1020 |
Seven lots are prepared and only 255 unit-weeks are carried, so$$TC_{c}=7(\$400)+4(255)=\$2{,}800+\$1{,}020=\boxed{\$3{,}820}$$Part-period balancing wins because it is the only one of the three rules that looks at when demand occurs: it consolidates the two small early weeks and the flat tail, and refuses to consolidate the week-6 and week-7 peaks, which are exactly the decisions the other two rules get wrong.
| Policy | Parameter | Lots prepared | Preparation cost | Unit-weeks carried | Carrying cost | Total incremental cost |
|---|---|---|---|---|---|---|
| (a) Economic lot size | Q = 153 units | 10 | $4,000 | 1,030 | $4,120 | $8,120 |
| (b) Economic periodic reorder | T* = 1.31 wk → T = 1 wk | 10 | $4,000 | 0 | $0 | $4,000 |
| (b) alternative rounding | T = 2 wk | 6 | $2,400 | 780 | $3,120 | $5,520 |
| (c) Part-period balancing | EPP = 100 unit-weeks | 7 | $2,800 | 255 | $1,020 | $3,820 (best) |
Check: the source states its total demand three different ways. The tabulated requirements sum to 1,480 units, the summary line says 1,390 units, and $\bar{R}=116.7$ implies 1,400. The inventory records above are built from the tabulated row, which is the only figure that can drive a week-by-week record, and $\bar{R}$ is used as printed inside the two square-root formulas, as the question directs. Substituting the tabulated average of 123.3 units/week instead gives $Q^{*}=157$ units and $T^{*}=1.27$ weeks — the same rounded order interval and the same ranking of the three policies, so the discrepancy changes no conclusion.