22-Mec-B4 Integrated Manufacturing Systems · December 2017
Question 3 of 7: Lot sizing against a requirements schedule
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 16-Mec-B4 Integrated Manufacturing Systems,
December 2017 — a three-hour open-book examination; any non-communicating
calculator is permitted. The cover page states “Any five (5) questions constitute a complete
paper. Only the first five (5) questions as they appear in your answer book will be marked”
and “All questions are of equal value”, so each of the seven printed
questions carries 20 marks against a 100-mark paper. Note 1 invites the candidate to submit a clear
statement of any assumptions made where a question is open to interpretation; this paper needs that
licence twice, and both places are flagged below. All seven questions are worked here, because this
set is a study resource rather than a timed sitting.
Reference texts. E. S. Buffa and R. K. Sarin, Modern Production /
Operations Management, 8th ed. (requirements-schedule lot sizing, economic order interval,
part-period balancing, plant location, machine coupling and the man-machine chart);
R. B. Chase, F. R. Jacobs and N. J. Aquilano, Operations and Supply Chain Management,
16th ed. (aggregate planning strategies, categories of forecasting technique, weighted factor
rating for facility location); M. P. Groover, Automation, Production Systems, and
Computer-Integrated Manufacturing, 5th ed. (CAD geometric transformations, computer-aided
process planning, routing sheets, group technology); D. C. Montgomery, Introduction to
Statistical Quality Control, 8th ed. (Shewhart constants, process capability indices);
A. J. Duncan, Quality Control and Industrial Statistics, 5th ed. (natural tolerance versus
specification); C. E. Ebeling, An Introduction to Reliability and Maintainability
Engineering, 3rd ed. (when preventive maintenance pays).
Question 3: Lot sizing against a requirements schedule (20 marks)
Requirements schedule and cost data for the motor drive unit
Week
1
2
3
4
5
6
7
8
9
10
11
12
Requirements, units
25
30
75
125
200
325
400
100
0
100
0
100
Average requirements $\bar{R} = 116.7$ units per week; preparation (set-up) cost
$c_p = $$400 per lot; holding cost $c_H = $$4 per unit per week; planning
horizon 12 weeks.
Find. The week-by-week inventory record (orders released and stock on hand)
and the total incremental cost — set-up plus carrying — under each of the three lot-size
policies, and hence which policy is cheapest over this schedule.
Check: the paper's own three statements of the total demand disagree. The
tabulated weekly requirements sum to 1,480 units; the summary line under the table
says 1,390; and the stated average $\bar{R} = 116.7$ per week implies
$12 \times 116.7 = 1{,}400$. Only the tabulated figures can drive an inventory record, so the
record below is built from them, while $\bar{R} = 116.7$ is used in the two square-root formulas
exactly as the question directs. The discrepancy decides nothing: using the tabulated average of
123.3 per week instead gives $Q = 157$ units and an order interval of 1.27 weeks, i.e. the same
rounded interval, the same policy ranking and the same conclusion.
Approach. Size the lot three ways — a fixed economic quantity, a fixed
economic time interval, and a variable lot balanced on part-periods — then run each policy
week by week through the tabulated requirements, accumulating set-up cost per order released and
carrying cost on the week-ending balance.
Part (a) — compute the economic lot size. The classical square-root
formula balances the annualised (here, weekly) set-up cost against the carrying cost of the average
cycle stock:
$$Q^{*}=\sqrt{\frac{2\,\bar{R}\,c_p}{c_H}}
=\sqrt{\frac{2(116.7)(400)}{4}}=\sqrt{23{,}340}=152.8
\;\Longrightarrow\;\boxed{Q^{*}=153\ \text{units per lot}}$$
The formula assumes demand is uniform, which this lumpy schedule is not; that mismatch is exactly
what parts (b) and (c) are designed to expose.
Part (a) — run the fixed-quantity policy through the schedule. Whenever
the balance on hand cannot cover the week's requirement, a whole lot of 153 is released — two
lots at once in week 6, three in week 7, where a single lot is not enough. Carrying cost is charged
on the week-ending balance at $4 per unit per week:
(a) Economic lot size, Q = 153 units — inventory record
Week
1
2
3
4
5
6
7
8
9
10
11
12
Requirements
25
30
75
125
200
325
400
100
0
100
0
100
Order released
153
—
—
153
153
459
306
153
—
153
—
—
On hand, week end
128
98
23
51
4
138
44
97
97
150
150
50
Part (a) — cost the policy. Ten lots are released, and the week-ending
balances total 1,030 unit-weeks:
$$\text{set-up} = 10 \times 400 = 4{,}000
\qquad
\text{carrying} = 1{,}030 \times 4 = 4{,}120$$
$$\boxed{\text{total incremental cost (a)} = 4{,}000 + 4{,}120 = 8{,}120}$$
in dollars. Note how much stock this policy carries: because the lot is fixed while demand is not,
the leftover from a large release sits through the quiet weeks 9 to 12.
Part (b) — compute the economic order interval. The periodic model fixes
the time between orders instead of the quantity:
$$T^{*}=\sqrt{\frac{2\,c_p}{c_H\,\bar{R}}}=\sqrt{\frac{2(400)}{4(116.7)}}
=\sqrt{1.714}=\boxed{1.31\ \text{weeks}}$$
This is the same policy expressed differently — $Q^{*}/\bar{R} = 152.8/116.7 = 1.31$ weeks
confirms it — but ordering can only happen on week boundaries, so $T$ must be rounded to 1 or
to 2 weeks. Because the total-cost curve is flat near the optimum, the choice is settled by costing
both, not by the rounding rule.
Part (b) — cost both roundings. With $T = 1$ week each order covers
exactly that week's requirement, so nothing is ever carried; the two weeks with zero requirement
need no order, giving ten set-ups:
$$\text{total}_{T=1} = 10(400) + 0 = 4{,}000$$
With $T = 2$ weeks the orders become 55, 200, 525, 500, 100, 100 in weeks 1, 3, 5, 7, 9 and 11, the
week-ending balances are 30, 125, 325, 100, 100, 100 (odd weeks) and zero in the even weeks, so
$$\text{total}_{T=2} = 6(400) + 780(4) = 2{,}400 + 3{,}120 = 5{,}520$$
The one-week interval is cheaper by $1,520, so the economic periodic policy is
$$\boxed{T = 1\ \text{week},\ \text{total incremental cost} = 4{,}000}$$
in dollars. It is lot-for-lot ordering in all but name, which is what an EOI of 1.31 weeks against
a weekly bucket must collapse to.
(b) Economic periodic reorder, T = 1 week — inventory record
Week
1
2
3
4
5
6
7
8
9
10
11
12
Requirements
25
30
75
125
200
325
400
100
0
100
0
100
Order released
25
30
75
125
200
325
400
100
—
100
—
100
On hand, week end
0
0
0
0
0
0
0
0
0
0
0
0
Part (c) — establish the economic part-period. Part-period balancing
lets the lot size vary, extending each order's coverage until the part-periods accumulated by the
stock being carried come closest to the part-periods that one set-up buys:
$$\text{EPP}=\frac{c_p}{c_H}=\frac{400}{4}=\boxed{100\ \text{part-periods (unit-weeks)}}$$
A part-period is one unit carried for one week; a requirement of $R_k$ placed $j$ weeks before it
is needed contributes $R_k\,j$ part-periods.
Part (c) — build the lots. Starting at week 1: covering week 1 alone
costs 0 part-periods, adding week 2 costs $30 \times 1 = 30$, and adding week 3 would cost a further
$75 \times 2 = 150$ for a running total of 180, which overshoots 100 by more than 30 undershoots it.
The first lot therefore covers weeks 1–2, i.e. 55 units. The same test applied from week 3
gives a lot of 200 covering weeks 3–4 (125 part-periods against 0 for week 3 alone), then
week 5 alone (200 units, because week 6 would add $325 \times 1 = 325$), week 6 alone, and weeks
7–8 together (500 units, 100 part-periods — an exact hit on EPP). Weeks 9 and 11 have no
requirement at all, so no lot starts there; the remaining orders are 100 in week 10 and 100 in
week 12.
Part (c) — cost the policy. Seven lots are released and the week-ending
balances total 255 unit-weeks:
$$\text{set-up} = 7 \times 400 = 2{,}800
\qquad
\text{carrying} = 255 \times 4 = 1{,}020$$
$$\boxed{\text{total incremental cost (c)} = 2{,}800 + 1{,}020 = 3{,}820}$$
in dollars. The week 7–8 tie is worth checking the other way: combining weeks 10 to 12 into
one order would save a set-up (−$400) but carry 100 units through weeks 10 and
11 (+$800), so the split shown is correct. An exact part-period tie must always be
settled by costing both branches rather than by the inequality.
(c) Part-period total cost balancing — inventory record
Week
1
2
3
4
5
6
7
8
9
10
11
12
Requirements
25
30
75
125
200
325
400
100
0
100
0
100
Order released
55
—
200
—
200
325
500
—
—
100
—
100
On hand, week end
30
0
125
0
0
0
100
0
0
0
0
0
The requirements schedule (week number on the horizontal axis), with the seven lot releases chosen by part-period balancing marked beneath the weeks they fall in. The policy orders ahead only where a small requirement sits in front of a larger one, and never starts a lot in a week with no requirement.
Ranking the three policies makes the lesson explicit: part-period balancing at
$3,820 beats the periodic model at $4,000, which in turn beats
the fixed economic lot size at $8,120. The fixed quantity is more than twice as
expensive as the best policy because a constant lot against a strongly varying requirement leaves
residual stock sitting through every quiet week.