NivaarExam PrepOfficial exam papers ↗

22-Mec-B4 Integrated Manufacturing Systems · December 2017

Question 3 of 7: Lot sizing against a requirements schedule

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 16-Mec-B4 Integrated Manufacturing Systems, December 2017 — a three-hour open-book examination; any non-communicating calculator is permitted. The cover page states “Any five (5) questions constitute a complete paper. Only the first five (5) questions as they appear in your answer book will be marked” and “All questions are of equal value”, so each of the seven printed questions carries 20 marks against a 100-mark paper. Note 1 invites the candidate to submit a clear statement of any assumptions made where a question is open to interpretation; this paper needs that licence twice, and both places are flagged below. All seven questions are worked here, because this set is a study resource rather than a timed sitting.

Reference texts. E. S. Buffa and R. K. Sarin, Modern Production / Operations Management, 8th ed. (requirements-schedule lot sizing, economic order interval, part-period balancing, plant location, machine coupling and the man-machine chart); R. B. Chase, F. R. Jacobs and N. J. Aquilano, Operations and Supply Chain Management, 16th ed. (aggregate planning strategies, categories of forecasting technique, weighted factor rating for facility location); M. P. Groover, Automation, Production Systems, and Computer-Integrated Manufacturing, 5th ed. (CAD geometric transformations, computer-aided process planning, routing sheets, group technology); D. C. Montgomery, Introduction to Statistical Quality Control, 8th ed. (Shewhart constants, process capability indices); A. J. Duncan, Quality Control and Industrial Statistics, 5th ed. (natural tolerance versus specification); C. E. Ebeling, An Introduction to Reliability and Maintainability Engineering, 3rd ed. (when preventive maintenance pays).

Question 3: Lot sizing against a requirements schedule (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

Requirements schedule and cost data for the motor drive unit
Week123456789101112
Requirements, units25307512520032540010001000100

Average requirements $\bar{R} = 116.7$ units per week; preparation (set-up) cost $c_p = $$400 per lot; holding cost $c_H = $$4 per unit per week; planning horizon 12 weeks.

Find. The week-by-week inventory record (orders released and stock on hand) and the total incremental cost — set-up plus carrying — under each of the three lot-size policies, and hence which policy is cheapest over this schedule.

Check: the paper's own three statements of the total demand disagree. The tabulated weekly requirements sum to 1,480 units; the summary line under the table says 1,390; and the stated average $\bar{R} = 116.7$ per week implies $12 \times 116.7 = 1{,}400$. Only the tabulated figures can drive an inventory record, so the record below is built from them, while $\bar{R} = 116.7$ is used in the two square-root formulas exactly as the question directs. The discrepancy decides nothing: using the tabulated average of 123.3 per week instead gives $Q = 157$ units and an order interval of 1.27 weeks, i.e. the same rounded interval, the same policy ranking and the same conclusion.

Approach. Size the lot three ways — a fixed economic quantity, a fixed economic time interval, and a variable lot balanced on part-periods — then run each policy week by week through the tabulated requirements, accumulating set-up cost per order released and carrying cost on the week-ending balance.

  1. Part (a) — compute the economic lot size. The classical square-root formula balances the annualised (here, weekly) set-up cost against the carrying cost of the average cycle stock: $$Q^{*}=\sqrt{\frac{2\,\bar{R}\,c_p}{c_H}} =\sqrt{\frac{2(116.7)(400)}{4}}=\sqrt{23{,}340}=152.8 \;\Longrightarrow\;\boxed{Q^{*}=153\ \text{units per lot}}$$ The formula assumes demand is uniform, which this lumpy schedule is not; that mismatch is exactly what parts (b) and (c) are designed to expose.
  2. Part (a) — run the fixed-quantity policy through the schedule. Whenever the balance on hand cannot cover the week's requirement, a whole lot of 153 is released — two lots at once in week 6, three in week 7, where a single lot is not enough. Carrying cost is charged on the week-ending balance at $4 per unit per week:
(a) Economic lot size, Q = 153 units — inventory record
Week123456789101112
Requirements25307512520032540010001000100
Order released153——153153459306153—153——
On hand, week end128982351413844979715015050
  1. Part (a) — cost the policy. Ten lots are released, and the week-ending balances total 1,030 unit-weeks: $$\text{set-up} = 10 \times 400 = 4{,}000 \qquad \text{carrying} = 1{,}030 \times 4 = 4{,}120$$ $$\boxed{\text{total incremental cost (a)} = 4{,}000 + 4{,}120 = 8{,}120}$$ in dollars. Note how much stock this policy carries: because the lot is fixed while demand is not, the leftover from a large release sits through the quiet weeks 9 to 12.
  2. Part (b) — compute the economic order interval. The periodic model fixes the time between orders instead of the quantity: $$T^{*}=\sqrt{\frac{2\,c_p}{c_H\,\bar{R}}}=\sqrt{\frac{2(400)}{4(116.7)}} =\sqrt{1.714}=\boxed{1.31\ \text{weeks}}$$ This is the same policy expressed differently — $Q^{*}/\bar{R} = 152.8/116.7 = 1.31$ weeks confirms it — but ordering can only happen on week boundaries, so $T$ must be rounded to 1 or to 2 weeks. Because the total-cost curve is flat near the optimum, the choice is settled by costing both, not by the rounding rule.
  3. Part (b) — cost both roundings. With $T = 1$ week each order covers exactly that week's requirement, so nothing is ever carried; the two weeks with zero requirement need no order, giving ten set-ups: $$\text{total}_{T=1} = 10(400) + 0 = 4{,}000$$ With $T = 2$ weeks the orders become 55, 200, 525, 500, 100, 100 in weeks 1, 3, 5, 7, 9 and 11, the week-ending balances are 30, 125, 325, 100, 100, 100 (odd weeks) and zero in the even weeks, so $$\text{total}_{T=2} = 6(400) + 780(4) = 2{,}400 + 3{,}120 = 5{,}520$$ The one-week interval is cheaper by $1,520, so the economic periodic policy is $$\boxed{T = 1\ \text{week},\ \text{total incremental cost} = 4{,}000}$$ in dollars. It is lot-for-lot ordering in all but name, which is what an EOI of 1.31 weeks against a weekly bucket must collapse to.
(b) Economic periodic reorder, T = 1 week — inventory record
Week123456789101112
Requirements25307512520032540010001000100
Order released253075125200325400100—100—100
On hand, week end000000000000
  1. Part (c) — establish the economic part-period. Part-period balancing lets the lot size vary, extending each order's coverage until the part-periods accumulated by the stock being carried come closest to the part-periods that one set-up buys: $$\text{EPP}=\frac{c_p}{c_H}=\frac{400}{4}=\boxed{100\ \text{part-periods (unit-weeks)}}$$ A part-period is one unit carried for one week; a requirement of $R_k$ placed $j$ weeks before it is needed contributes $R_k\,j$ part-periods.
  2. Part (c) — build the lots. Starting at week 1: covering week 1 alone costs 0 part-periods, adding week 2 costs $30 \times 1 = 30$, and adding week 3 would cost a further $75 \times 2 = 150$ for a running total of 180, which overshoots 100 by more than 30 undershoots it. The first lot therefore covers weeks 1–2, i.e. 55 units. The same test applied from week 3 gives a lot of 200 covering weeks 3–4 (125 part-periods against 0 for week 3 alone), then week 5 alone (200 units, because week 6 would add $325 \times 1 = 325$), week 6 alone, and weeks 7–8 together (500 units, 100 part-periods — an exact hit on EPP). Weeks 9 and 11 have no requirement at all, so no lot starts there; the remaining orders are 100 in week 10 and 100 in week 12.
  3. Part (c) — cost the policy. Seven lots are released and the week-ending balances total 255 unit-weeks: $$\text{set-up} = 7 \times 400 = 2{,}800 \qquad \text{carrying} = 255 \times 4 = 1{,}020$$ $$\boxed{\text{total incremental cost (c)} = 2{,}800 + 1{,}020 = 3{,}820}$$ in dollars. The week 7–8 tie is worth checking the other way: combining weeks 10 to 12 into one order would save a set-up (−$400) but carry 100 units through weeks 10 and 11 (+$800), so the split shown is correct. An exact part-period tie must always be settled by costing both branches rather than by the inequality.
(c) Part-period total cost balancing — inventory record
Week123456789101112
Requirements25307512520032540010001000100
Order released55—200—200325500——100—100
On hand, week end30012500010000000
010020030040025155302753200125420052003256325400750010089100101001110012100Requirements schedule for the motor drive unit (units per week)lot released (triangle marks the week, figure is the lot size)
The requirements schedule (week number on the horizontal axis), with the seven lot releases chosen by part-period balancing marked beneath the weeks they fall in. The policy orders ahead only where a small requirement sits in front of a larger one, and never starts a lot in a week with no requirement.

Ranking the three policies makes the lesson explicit: part-period balancing at $3,820 beats the periodic model at $4,000, which in turn beats the fixed economic lot size at $8,120. The fixed quantity is more than twice as expensive as the best policy because a constant lot against a strongly varying requirement leaves residual stock sitting through every quiet week.

Question 3 — total incremental cost by policy
PolicyLot ruleOrdersSet-up costCarrying costTotal
(a) Economic lot sizeQ = 153 units10$4,000$4,120$8,120
(b) Economic periodic reorderT* = 1.31 wk → 1 wk10$4,000$0$4,000
(b) alternative roundingT = 2 wk6$2,400$3,120$5,520
(c) Part-period balancingEPP = 100 unit-weeks7$2,800$1,020$3,820