24-MMP-A2 Underground Mining Methods and Design · December 2014
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
EGBC National Exam — Mining and Mineral Processing Engineering, 09-Mmp-A2 Underground Mining Methods and Design, 2014-Dec. 3 hours duration, closed book; only an approved Sharp or Casio calculator permitted, one hand-written 8.5×11 in. reference sheet allowed. Question 1 is compulsory (40 marks, all seven parts 1.1–1.7); a candidate then selects THREE of Questions 2–7 (each nominally 20 marks, Question 7 sub-totalling higher).
Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (underground mining methods, rock support, mine ventilation, shaft hoisting design, headframes, backfill practice, mine cost estimation — the primary reference throughout this paper); Hustrulid & Bullock, Underground Mining Methods: Engineering Fundamentals and International Case Studies (room-and-pillar, vertical crater retreat and trackless mechanized stoping practice); O'Hara, T.P., "Quick Guides to the Evaluation of Orebodies," CIM Bulletin, February 1980, and Mular, A.L. & Poulin, R., CapCost – CIM Special Volume 47, 1998 (parametric underground mine capital-cost models used in Question 7); BC Ministry of Energy, Mines and Low Carbon Innovation, Health, Safety and Reclamation Code for Mines in British Columbia (Canadian regulatory context for hoisting-rope safety factors, overwind protection and shaft ventilation).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
An experienced mining/cost engineer applying a published parametric (order-of-magnitude) cost model — exactly the O'Hara-type formulas used through the rest of this question — rather than an external engineering (EPCM) firm: a full EPCM scoping estimate takes weeks, while a parametric, capacity-and-depth-based model can be evaluated by one engineer, from a handful of inputs (tonnage, depth, stope width), inside a single day, at the ±35–40% accuracy such models are calibrated to deliver.
A parametric (power-law, regression-based) cost-estimating method, published by T.P. O'Hara in the CIM Bulletin, February 1980, and subsequently updated and republished by Mular & Poulin as "CapCost" in CIM Special Volume 47 (1998). Rather than a detailed, bottom-up engineering estimate, it expresses each major mine capital-cost component (shaft sinking, hoist plant, mine development, mining equipment, compressor plant, etc.) as a simple function of a small number of easily known design variables — principally daily tonnage $T$, depth/hoisting distance $h$, and stope width $W$ — each regressed from a database of actual historical mine costs. It is the standard reference method for rapid, scoping-level (±35–40%) underground mine capital estimates, exactly the class of estimate identified in 7.1.
Each O'Hara/CapCost formula returns a cost in its own base publication year (1980 or 1998); to convert to a target year (2014, or a further projection to 2020), the base-year cost is multiplied by the ratio of a published cost index at the target year to the same index at the base year — exactly the escalation technique described for the Marshall & Swift M/M index in Question 1.7.1: $C_{target} = C_{base}\times(Index_{target}/Index_{base})$. Separate capital and operating cost indices should be used (they escalate at different rates — capital equipment/construction costs typically outpace labour-heavy operating costs, or vice versa depending on the period), and, since the O'Hara/CapCost formulas themselves are not re-derived here, the same index ratio is simply reapplied a second time to step from 2014 to a 2020 estimate once the relevant index values for those years are looked up.
Given. $T = 4500+1000 = 5500\ \text{mt/day}$ (total hoisted); $F=h=600\ \text{m}$; $W=10\ \text{m}$; $T_{ore}=4500\ \text{mt/day}$ (ore only, for $C_2$); $D_s=1.608\,T^{0.15}=5.85\ \text{m}$ and $d=3.976\ \text{m}$ as worked in the question statement.
Find. $C_{12}$, $L$, $S$, $H$ (motor power), $C_2$.
Approach. Substitute the given $T$, $F/h$, $W$ and the worked $D_s$, $d$ directly into each formula in turn, since $L$, $S$ and $H$ each depend on quantities already found earlier in the chain.
| Quantity | Value |
|---|---|
| Shaft diameter $D_s$ | 5.85 m (given) |
| Shaft-sinking cost $C_{12}$ | USD 8.49 M |
| Hoist drum diameter $d$ | 3.976 m (given) |
| Head-frame height $L$ | 52.37 m |
| Hoisting speed $S$ | 11.41 m/s |
| Hoist motor power $H$ | 2455 kW |
| Mine development cost $C_2$ | USD 26.41 M |
Every formula in 7.4 is driven by only two or three easily known variables ($T$, $h$/$F$, $W$), which is exactly what makes the method usable for a same-day estimate (7.1) but also its central limitation: none of the formulas take rock strength, ground-support intensity, labour/regional cost differences, or the specific shaft-lining/headframe design as explicit inputs, even though the question itself states the rock is "relatively weak." The models capture the dominant, first-order economy-of-scale and depth trends correctly (cost rising with tonnage and depth in physically sensible ways, as seen in $C_{12}$ and $C_2$ above), but two mines with identical $T$, $h$ and $W$ yet very different ground conditions would receive the same cost estimate here — appropriate for a ±35–40% scoping estimate and options screening, but not a substitute for site-specific engineering once a project is far enough advanced to justify the cost of that engineering.
Comment. The head-frame complex ($C_{34}$, driven by $L^{1.8}$) and the hoist equipment itself ($C_{31}$) together dominate the total, while the hoist-room cost ($C_{33}$) is disproportionately sensitive to drum diameter through its steep $d^{3.2}$ exponent — a modest error in the drum-diameter calculation (7.4.2) would be amplified roughly three-and-a-half-fold in $C_{33}$ alone. Reliability would improve by adding the winder type (drum vs. friction) and drive type (DC vs. modern AC/VFD, Question 4.2) as explicit inputs, since these materially change both $C_{31}$ and installation labour cost, and by using a location-specific structural-steel cost factor for the head-frame ($C_{34}$) rather than a single national-average coefficient.
Comment. A computed $Q$ of about 5 m³/s falls within the range typically seen at mines of this scale (broadly 2–8 m³/s depending on how much of the underground fleet is pneumatically powered), but the single power-law-in-$T$ form is a coarse proxy: it says nothing about how much of the fleet is pneumatic (rock drills, pneumatic loaders) versus electric or electro-hydraulic. A mine that has already converted most of its fleet away from compressed air — as most modern trackless operations have (Question 2.3) — would find $C_4$ from this formula a conservative upper bound rather than a close estimate.
These items are governed almost entirely by location (grid-connection distance, water source/dewatering needs, existing road access) and by the milling/processing complex, so a full estimate for $C_7$ is intentionally excluded here and would be developed alongside the mill/surface-infrastructure package. For underground-only purposes: electrical power distribution (transformers/substations feeding the hoist, ventilation and pumping loads) is typically already partly embedded in $C_3$/$C_5$ above rather than separately itemised; underground water supply/dewatering pumping infrastructure typically runs a few percent of total underground fixed capital; general plant services (compressed-air/power reticulation, communications) are a similarly small incremental fraction once the major systems above are costed; and access, town-site and housing costs are the most site-specific of all — negligible for a mine with existing road/rail/town access, but potentially very large (new access road, fly-in/fly-out camp, or a purpose-built town-site) for a remote greenfield operation.
The O'Hara/CapCost parametric method is appropriate, and reliable to its stated ±35–40% band, for early-stage scoping and prefeasibility-level estimates and for screening multiple project options against each other quickly and consistently — exactly the "quick estimate within a day" use case of 7.1. It is not a substitute for a detailed, bottom-up engineering estimate (±10–15%) once a project advances to feasibility study, and, as noted in 7.5, it is most reliable when the tonnage/depth/width inputs fall within the range of mines used to originally calibrate the regressions — extrapolating well outside that range (a much deeper or much smaller operation than the database) degrades the stated accuracy. Any estimate from the method should be escalated with a current, published cost index (7.3) and, wherever possible, sanity-checked against recent comparable-project actual costs before being used for investment decisions.
| Cost item | Value |
|---|---|
| Shaft sinking $C_{12}$ | USD 8.49 M |
| Mine development $C_2$ | USD 26.41 M |
| Hoist plant $C_3$ | USD 12.04 M |
| Compressor plant $C_4$ | USD 1.60 M |
| Underground mining equipment $C_5$ | USD 13.77 M |
| Underground maintenance facility $C_6$ | USD 2.37 M |
| Subtotal (excl. $C_7$) | USD 64.68 M |