24-MMP-A2 Underground Mining Methods and Design · May 2014
Question 4 of 7: Parametric Shaft and Block-Caving Cost Estimation with Escalation to 2012
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A2 Underground Mining Methods and Design, 2014-May. 3 hours duration, closed book; only a Casio or Sharp approved calculator permitted. Question 1 is compulsory (40 marks, all seven parts 1.1–1.7); a candidate then selects FOUR of Questions 2–7 (each worth 15 marks).
Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (underground mining methods, mine ventilation, shaft hoisting design, headframes, backfill practice, mine cost estimation — the primary reference throughout this paper); Hustrulid & Bullock, Underground Mining Methods: Engineering Fundamentals and International Case Studies (narrow-vein longitudinal-retreat/Avoca-family stoping, cut-and-fill variants); BC Ministry of Energy, Mines and Low Carbon Innovation, Health, Safety and Reclamation Code for Mines in British Columbia (Canadian regulatory context for hoisting-rope safety factors and shaft ventilation); Camm, T.W. (1991), Simplified Cost Models for Prefeasibility Mineral Evaluations, U.S. Bureau of Mines IC 9298 (source of the Question 4 parametric cost models).
Question 4: Parametric Shaft and Block-Caving Cost Estimation with Escalation to 2012 (15 marks)
Check: the page-7 preamble asks for costs "escalated to 2013 US $," but the printed sub-question 4.3 and Table 4.3 (which stops at 2012) both ask explicitly for 2012 — this is read as a drafting inconsistency in the source, and the answer below follows the sub-question text and the data actually supplied, escalating to 2012.
Given.
Design basis and Table 4.1 / 4.2 model parameters
Quantity
Symbol
Value
Mine capacity
X
20,000 short tons/day
Nominal shaft depth
D
2,000 ft
Table 4.1 total capital cost model (USD)
—
371X + 180D·X0.404
Table 4.1 total operating cost model (USD/st)
—
2343/X + 0.44D/X + 0.00163D
Table 4.2 total capital cost model (USD)
—
64,800·X0.759
Table 4.2 total operating cost model (USD/st)
—
48.4·X-0.217
Capital cost index, 1989 / 2012 (Table 4.3)
—
95.5 / 256.8
Operating cost index, 1989 / 2012 (Table 4.3)
—
91.1 / 210.8
Find. The component and total 1989 shaft capital/operating costs (4.1), the component and total 1989 block-caving mining capital/operating costs excluding the shaft (4.2), and the total shaft-plus-mining capital and operating costs escalated to 2012 (4.3), with commentary on model adequacy throughout.
Approach. Substitute X = 20,000 and D = 2,000 into every component formula of Table 4.1 (shaft) and Table 4.2 (block-caving mine) to get the 1989 component and "Total" line costs; then multiply the 1989 shaft and mining totals by the ratio of the 2012 to 1989 capital and operating indices from Table 4.3.
Part 4.1 — shaft capital cost components, 1989. Each Table 4.1 capital term is evaluated at X=20,000, D=2,000 (Lumber, Fuel and Tires are marked "NAp" for a shaft and contribute nothing):
Table 4.1 shaft capital cost, 1989 (USD)
Category
Formula
Cost (USD)
Labor
75D·X0.399
7,801,900
Equipment
350X + 65D·X0.386
12,944,900
Steel
25D·X0.373
2,010,300
Lube
6D·X0.342
354,900
Explosives
5D·X0.389
471,100
Construction material
9D·X0.522
3,165,300
Electricity
4D·X0.230
78,000
Sum of components
—
26,826,400
Total (Table 4.1 formula)
371X + 180D·X0.404
27,095,200
Equipment (Equipment is the largest single item at roughly 48% of the sum of components) and Labor dominate, consistent with a mechanised shaft-sinking crew and permanent hoisting/guide/service installation; the printed "Total" formula (independently regressed against the historical cost database, not a re-sum of the component lines) comes out about 1% above the arithmetic sum of components — the two should always be checked against each other as a sanity cross-check, and here they agree closely.
At 20,000 st/d × 365 d/yr this is an annual shaft operating cost of about USD 24.97 million. The Electricity term (2.80/st, over 80% of the operating total) is disproportionately large compared with Labor and Equipment for what is normally a modest hoisting/pumping/ventilation power draw at a single shaft — a value this dominant is worth flagging as a possible scaling artefact in the underlying 1989 regression (an operating-cost model fitted mainly to shallower, lower-capacity shafts in the sample can extrapolate poorly to a 2,000 ft, 20,000 st/d case), and should be sanity-checked against an independent kWh-based estimate before being relied on for a real feasibility budget.
Part 4.2 — block-caving mining capital cost, 1989 (excluding shaft). All ten Table 4.2 categories are pure functions of X alone (no depth term):
Table 4.2 block-caving mining capital cost, 1989 (USD)
Category
Formula
Cost (USD)
Labor
27,900X0.646
16,752,100
Equipment
25,600X0.812
79,556,600
Steel
4,410X0.685
3,896,200
Lumber
149X0.902
1,129,100
Fuel
10.6X0.897
76,400
Lube
4.54X0.897
32,700
Explosives
1,040X0.737
1,537,800
Tires
1.87X0.946
21,900
Construction material
31,100X0.591
10,831,000
Electricity
50.4X0.748
83,100
Sum of components
—
113,917,000
Total (Table 4.2 formula)
64,800X0.759
119,139,800
Equipment again dominates (about 70% of the component sum), consistent with the mechanised LHD/crusher/conveying fleet a block-caving operation of this scale requires; the Total-formula result runs about 4.6% above the component sum, a wider gap than the shaft model's, which is expected since the mining Total was regressed across a capacity range (4,000–40,000 st/d) rather than summed directly — both figures should be carried forward and the difference treated as part of the estimate's inherent uncertainty band, not resolved arbitrarily in favour of one.
Part 4.2 — block-caving mining operating cost, 1989 (excluding shaft).
Labor is the single largest term (about 53% of the component sum), the pattern expected of an underground block-caving labour force, and the negative exponents on every category reflect the intended economy of scale — unit cost falling as capacity X rises. That every exponent is negative (or zero) is itself a useful adequacy check: a positive exponent here would produce a rising unit cost with capacity, which is not physically sensible for this class of model, and none of the ten terms shows that failure.
Part 4.3 — total shaft and mining costs escalated to 2012. Applying the 2012 factors from the previous step to the Table-formula 1989 totals of Steps 1–4:
2012 escalated totals (USD, using the Table 4.1/4.2 "Total" formulas)
Part 4.3 — adequacy of the 2008, 2009 and 2012 estimates. Table 4.3's capital index climbs from 95.5 (1989) to a local peak of 245.9 in 2008, falls back to 228.0 in 2009, then recovers to 256.8 by 2012 — a swing of roughly 8% down and 13% back up in just four years, driven by the 2008 construction/commodity cost boom and the subsequent 2009 financial-crisis pullback. A single scalar escalation factor, by construction, cannot represent that a Labor-heavy line item and an Equipment- or Steel-heavy line item did not move together through that cycle (structural steel and commodity-linked inputs spiked and crashed harder than site labour rates), so the escalated 2008/2009 figures understate the true cost dispersion across categories even though the blended total tracks roughly right. The estimate is further weakened by extrapolating a 1989-fitted regression 19–23 years forward and, for the shaft model, outside any depth range the source explicitly bounds — both are order-of-magnitude/pre-feasibility tools (per the question's own framing) and are adequate for screening-level comparison between design options, but should never substitute for vendor quotes once a project reaches a bankable feasibility study.
Question 4 — final numeric results (2012 USD unless noted)