NivaarExam PrepOfficial exam papers ↗

24-MMP-A2 Underground Mining Methods and Design · May 2014

Question 4 of 7: Parametric Shaft and Block-Caving Cost Estimation with Escalation to 2012

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A2 Underground Mining Methods and Design, 2014-May. 3 hours duration, closed book; only a Casio or Sharp approved calculator permitted. Question 1 is compulsory (40 marks, all seven parts 1.1–1.7); a candidate then selects FOUR of Questions 2–7 (each worth 15 marks).

Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (underground mining methods, mine ventilation, shaft hoisting design, headframes, backfill practice, mine cost estimation — the primary reference throughout this paper); Hustrulid & Bullock, Underground Mining Methods: Engineering Fundamentals and International Case Studies (narrow-vein longitudinal-retreat/Avoca-family stoping, cut-and-fill variants); BC Ministry of Energy, Mines and Low Carbon Innovation, Health, Safety and Reclamation Code for Mines in British Columbia (Canadian regulatory context for hoisting-rope safety factors and shaft ventilation); Camm, T.W. (1991), Simplified Cost Models for Prefeasibility Mineral Evaluations, U.S. Bureau of Mines IC 9298 (source of the Question 4 parametric cost models).

Question 4: Parametric Shaft and Block-Caving Cost Estimation with Escalation to 2012 (15 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Check: the page-7 preamble asks for costs "escalated to 2013 US $," but the printed sub-question 4.3 and Table 4.3 (which stops at 2012) both ask explicitly for 2012 — this is read as a drafting inconsistency in the source, and the answer below follows the sub-question text and the data actually supplied, escalating to 2012.

Given.

Design basis and Table 4.1 / 4.2 model parameters
QuantitySymbolValue
Mine capacityX20,000 short tons/day
Nominal shaft depthD2,000 ft
Table 4.1 total capital cost model (USD)—371X + 180D·X0.404
Table 4.1 total operating cost model (USD/st)—2343/X + 0.44D/X + 0.00163D
Table 4.2 total capital cost model (USD)—64,800·X0.759
Table 4.2 total operating cost model (USD/st)—48.4·X-0.217
Capital cost index, 1989 / 2012 (Table 4.3)—95.5 / 256.8
Operating cost index, 1989 / 2012 (Table 4.3)—91.1 / 210.8

Find. The component and total 1989 shaft capital/operating costs (4.1), the component and total 1989 block-caving mining capital/operating costs excluding the shaft (4.2), and the total shaft-plus-mining capital and operating costs escalated to 2012 (4.3), with commentary on model adequacy throughout.

Approach. Substitute X = 20,000 and D = 2,000 into every component formula of Table 4.1 (shaft) and Table 4.2 (block-caving mine) to get the 1989 component and "Total" line costs; then multiply the 1989 shaft and mining totals by the ratio of the 2012 to 1989 capital and operating indices from Table 4.3.

  1. Part 4.1 — shaft capital cost components, 1989. Each Table 4.1 capital term is evaluated at X=20,000, D=2,000 (Lumber, Fuel and Tires are marked "NAp" for a shaft and contribute nothing):
    Table 4.1 shaft capital cost, 1989 (USD)
    CategoryFormulaCost (USD)
    Labor75D·X0.3997,801,900
    Equipment350X + 65D·X0.38612,944,900
    Steel25D·X0.3732,010,300
    Lube6D·X0.342354,900
    Explosives5D·X0.389471,100
    Construction material9D·X0.5223,165,300
    Electricity4D·X0.23078,000
    Sum of components—26,826,400
    Total (Table 4.1 formula)371X + 180D·X0.40427,095,200
    Equipment (Equipment is the largest single item at roughly 48% of the sum of components) and Labor dominate, consistent with a mechanised shaft-sinking crew and permanent hoisting/guide/service installation; the printed "Total" formula (independently regressed against the historical cost database, not a re-sum of the component lines) comes out about 1% above the arithmetic sum of components — the two should always be checked against each other as a sanity cross-check, and here they agree closely.
  2. Part 4.1 — shaft operating cost components, 1989.
    Table 4.1 shaft operating cost, 1989 (USD/short ton)
    CategoryFormulaCost (USD/st)
    Labor2010/X0.1005
    Equipment0.325D/X0.0325
    Steel0.00014D0.2800
    Lube0.090D/X0.0090
    Construction material200/X0.0100
    Electricity0.0014D2.8000
    Sum of components—3.2320
    Total (Table 4.1 formula)2343/X + 0.44D/X + 0.00163D3.4211
    At 20,000 st/d × 365 d/yr this is an annual shaft operating cost of about USD 24.97 million. The Electricity term (2.80/st, over 80% of the operating total) is disproportionately large compared with Labor and Equipment for what is normally a modest hoisting/pumping/ventilation power draw at a single shaft — a value this dominant is worth flagging as a possible scaling artefact in the underlying 1989 regression (an operating-cost model fitted mainly to shallower, lower-capacity shafts in the sample can extrapolate poorly to a 2,000 ft, 20,000 st/d case), and should be sanity-checked against an independent kWh-based estimate before being relied on for a real feasibility budget.
  3. Part 4.2 — block-caving mining capital cost, 1989 (excluding shaft). All ten Table 4.2 categories are pure functions of X alone (no depth term):
    Table 4.2 block-caving mining capital cost, 1989 (USD)
    CategoryFormulaCost (USD)
    Labor27,900X0.64616,752,100
    Equipment25,600X0.81279,556,600
    Steel4,410X0.6853,896,200
    Lumber149X0.9021,129,100
    Fuel10.6X0.89776,400
    Lube4.54X0.89732,700
    Explosives1,040X0.7371,537,800
    Tires1.87X0.94621,900
    Construction material31,100X0.59110,831,000
    Electricity50.4X0.74883,100
    Sum of components—113,917,000
    Total (Table 4.2 formula)64,800X0.759119,139,800
    Equipment again dominates (about 70% of the component sum), consistent with the mechanised LHD/crusher/conveying fleet a block-caving operation of this scale requires; the Total-formula result runs about 4.6% above the component sum, a wider gap than the shaft model's, which is expected since the mining Total was regressed across a capacity range (4,000–40,000 st/d) rather than summed directly — both figures should be carried forward and the difference treated as part of the estimate's inherent uncertainty band, not resolved arbitrarily in favour of one.
  4. Part 4.2 — block-caving mining operating cost, 1989 (excluding shaft).
    Table 4.2 block-caving mining operating cost, 1989 (USD/short ton)
    CategoryFormulaCost (USD/st)
    Labor60.0X-0.3052.9264
    Equipment4.40X-0.2300.4510
    Steel0.217X0.00.2170
    Lumber0.310X0.00.3100
    Fuel0.894X-0.2390.0838
    Lube0.545X-0.2530.0445
    Explosives0.183X-0.00.1830
    Tires0.412X-0.1510.0924
    Construction material2.83X-0.1820.4667
    Electricity1.36X-0.0600.7507
    Sum of components—5.5255
    Total (Table 4.2 formula)48.4X-0.2175.6432
    Labor is the single largest term (about 53% of the component sum), the pattern expected of an underground block-caving labour force, and the negative exponents on every category reflect the intended economy of scale — unit cost falling as capacity X rises. That every exponent is negative (or zero) is itself a useful adequacy check: a positive exponent here would produce a rising unit cost with capacity, which is not physically sensible for this class of model, and none of the ten terms shows that failure.
  5. Part 4.3 — escalation factors, 1989→2012 (Table 4.3). $$\text{capital factor} = \dfrac{256.8}{95.5} = 2.689, \qquad \text{operating factor} = \dfrac{210.8}{91.1} = 2.314$$
  6. Part 4.3 — total shaft and mining costs escalated to 2012. Applying the 2012 factors from the previous step to the Table-formula 1989 totals of Steps 1–4:
    2012 escalated totals (USD, using the Table 4.1/4.2 "Total" formulas)
    Item1989× factor2012
    Shaft capital27,095,2002.68972,859,100
    Shaft operating (/st)3.42112.3147.9163
    Mining capital119,139,8002.689320,367,500
    Mining operating (/st)5.64322.31413.0579
    $$\boxed{C_{cap,2012} = 72.86\text{M} + 320.37\text{M} = 393.23\text{M USD}}$$ $$\boxed{c_{op,2012} = 7.9163 + 13.0579 = 20.97\ \text{USD/st}\ \ (\times 20{,}000 \times 365 \approx 153.1\text{M USD/yr})}$$
  7. Part 4.3 — adequacy of the 2008, 2009 and 2012 estimates. Table 4.3's capital index climbs from 95.5 (1989) to a local peak of 245.9 in 2008, falls back to 228.0 in 2009, then recovers to 256.8 by 2012 — a swing of roughly 8% down and 13% back up in just four years, driven by the 2008 construction/commodity cost boom and the subsequent 2009 financial-crisis pullback. A single scalar escalation factor, by construction, cannot represent that a Labor-heavy line item and an Equipment- or Steel-heavy line item did not move together through that cycle (structural steel and commodity-linked inputs spiked and crashed harder than site labour rates), so the escalated 2008/2009 figures understate the true cost dispersion across categories even though the blended total tracks roughly right. The estimate is further weakened by extrapolating a 1989-fitted regression 19–23 years forward and, for the shaft model, outside any depth range the source explicitly bounds — both are order-of-magnitude/pre-feasibility tools (per the question's own framing) and are adequate for screening-level comparison between design options, but should never substitute for vendor quotes once a project reaches a bankable feasibility study.
Question 4 — final numeric results (2012 USD unless noted)
ItemResult
4.1 Shaft capital, 198927.10M USD (component sum 26.83M)
4.1 Shaft operating, 19893.42 USD/st (24.97M USD/yr)
4.2 Mining capital, 1989 (excl. shaft)119.14M USD (component sum 113.92M)
4.2 Mining operating, 1989 (excl. shaft)5.64 USD/st (41.20M USD/yr)
4.3 Escalation factors, 1989→2012capital ×2.689, operating ×2.314
4.3 Shaft capital, 201272.86M USD
4.3 Shaft operating, 20127.92 USD/st (57.79M USD/yr)
4.3 Mining capital, 2012320.37M USD
4.3 Mining operating, 201213.06 USD/st (95.32M USD/yr)
4.3 TOTAL capital (shaft+mining), 2012393.23M USD
4.3 TOTAL operating (shaft+mining), 201220.97 USD/st (153.11M USD/yr)