NivaarExam PrepOfficial exam papers ↗

24-MMP-A2 Underground Mining Methods and Design · December 2016

Question 6 of 6: Shrinkage and Sub-Level Caving Mining Methods — Comparison

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A2 Underground Mining Methods and Design, 2016-Dec. 3 hours duration, closed book; only a Casio or Sharp approved calculator permitted. Question 1 is compulsory (40 marks, all six parts 1.1–1.6); a candidate then selects TWO of Questions 2–4 (Section B) and ONE of Questions 5–6 (Section C), each worth 20 marks.

Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (underground mining methods, backfill systems, mine hoisting design, mine ventilation, mine cost estimation — the primary reference throughout this paper); Hustrulid & Bullock, Underground Mining Methods: Engineering Fundamentals and International Case Studies (room-and-pillar, VCR, cut-and-fill, longhole, shrinkage and sub-level caving practice); ASHRAE, ASHRAE Handbook — Fundamentals (psychrometric relations, humidity ratio and enthalpy of moist air); BC Ministry of Energy, Mines and Low Carbon Innovation, Health, Safety and Reclamation Code for Mines in British Columbia (Canadian regulatory context for hoisting-rope safety factors); Camm, T.W. (1989), Simplified Cost Models for Prefeasibility Mineral Evaluations, U.S. Bureau of Mines IC 9298 (Question 4 parametric cost models); O'Hara, T.A. (1980), "Quick Guides to the Evaluation of Orebodies," CIM Bulletin, February 1980 (Question 1.4.3).

Question 6: Shrinkage and Sub-Level Caving Mining Methods — Comparison (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Shrinkage stoping mines a steeply dipping orebody upward in horizontal slices, leaving roughly 60% of the broken ore in the stope as a working platform/temporary wall support and drawing off only enough to keep a safe working headroom until the stope is complete, when the full pile is finally drawn. Sub-level caving drives a grid of parallel sub-level drifts through the orebody, drilling and blasting each ring so the ore caves and is drawn from the drift face while the overlying waste is deliberately allowed to cave and follow the ore down, with no stope left open at any point. Both are largely non-selective bulk methods for steep, competent-to-moderate orebodies, but they differ sharply in how ground control and dilution are managed.

Shrinkage stoping vs. sub-level caving — comparative summary
CriterionShrinkage stopingSub-level caving
Geology, orebody shape/size/orientationSteeply dipping (≥50°, ideally near-vertical so broken ore gravity-flows to drawpoints), narrow to moderate width, regular wallsSteeply dipping, larger/thicker orebodies where the overlying rock mass is suitable (or can be induced) to cave uniformly
Host and ore rock propertiesOre and walls both need to be reasonably competent — walls must stand unsupported against the temporarily-retained broken-ore pileOre should be moderately competent (fragments well on blasting) while the overlying waste/host rock must be capable of caving readily and continuously as ore is withdrawn
Development size/amount/cost/time to startModerate: a single set of sub-level drifts (top for drilling, bottom for drawpoints) per stope block; relatively fast to bring into productionExtensive: a full grid of closely spaced parallel sub-level drifts and crosscuts driven through the ENTIRE orebody height, repeated at every sub-level; high up-front development cost and time
Ground supportRib/wall support as needed on the standing walls; minimal support inside the stope itself (the broken-ore pile is the working floor)Significant support in the closely spaced production drifts, which must remain serviceable while overlying waste caves close behind the retreating face
Mining sequence and mill feed rateSlice-by-slice upward blast with partial draw between slices, full draw only at completion; moderate, somewhat batch-like mill feed rateContinuous ring drilling/blasting and drawing, retreating along each sub-level drift; high, continuous mill feed rate once the method is established
Personnel (number/skills)Moderate crew, skilled in slice drilling/blasting and safe partial-draw practice under a broken-ore backLarger crew given the extent of sub-level development, with skilled ring-drilling/blasting and LHD draw-control (avoiding waste dilution) personnel
Mechanized equipmentSmaller-scale drilling equipment (often hand-held or light jumbo, since headroom in the stope is limited); minimal LHD use until final drawRing/fan drill jumbos and a large fleet of LHDs working continuously along the production drifts
Cost of miningModerate unit cost — less bulk than caving but more than a fully mechanised bulk method, owing to the slower slice cycleLow unit cost once established — high mechanisation and continuous production offset the heavy up-front development cost
Mine lifeSuited to moderate-tonnage, narrower deposits over a moderate mine lifeSuited to large-tonnage deposits, sustaining production over a long mine life once the sub-level grid is developed
Mining rateLow to moderateHigh, among the highest of underground bulk methods
Dilution and recoveryLow-to-moderate dilution if walls are competent; recovery limited by the roughly 40% of broken ore that must be drawn early to keep working headroom, plus ore left against irregular wallsInherently high dilution — waste rock mixes with ore as both cave and are drawn together through the same drawpoint, and the draw must be stopped once waste content rises, capping recovery per ring
Pillar recovery method/costSill pillars at the stope base are recovered as a final, higher-risk draw once the stope is otherwise exhaustedNo conventional pillars are left (the method is inherently non-pillared); crown remnants above the uppermost sub-level are the main un-recovered loss instead
Post-mining stabilizationRemaining voids after final draw typically require backfilling or are allowed to collapse in a controlled mannerSurface subsidence is an EXPECTED, planned consequence of caving and must be managed by a pre-planned subsidence/exclusion zone rather than treated as an incidental stabilization afterthought
Back to the paper →