24-MMP-A2 Underground Mining Methods and Design · December 2019
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
EGBC National Exam — Mining and Mineral Processing Engineering, 18-Mmp-A2 Underground Mining Methods and Design, 2019-Dec. Closed book exam, Sharp/Casio approved calculator plus one hand-written 8.5x11 in. reference sheet permitted. Question 1 is compulsory (40 marks, all five parts 1.1–1.5); a candidate then selects THREE of the five optional Questions 2–6 (20 marks each).
Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (rock haulage systems, shaft hoisting design, ground support, mine ventilation, mine cost estimation — the primary reference throughout this paper); Hustrulid & Bullock, Underground Mining Methods: Engineering Fundamentals and International Case Studies (room-and-pillar, vertical crater retreat and shaft/incline material-handling comparisons); BC Ministry of Energy, Mines and Low Carbon Innovation, Health, Safety and Reclamation Code for Mines in British Columbia (Canadian regulatory context for hoisting-rope factors of safety, ground support and ventilation practice); O'Hara, "Quick Guides to the Evaluation of Orebodies," CIM Bulletin, Feb. 1980, and Mular & Poulin, CapCost, CIM Special Volume 47, 1998 (parametric underground capital-cost formulas used in Question 2).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
2.1.1 Cost estimation methods. A cost estimation method is a systematic, repeatable procedure for predicting a project's capital and/or operating cost before it is actually built, ranging from a rough order-of-magnitude estimate based on a single scaling parameter (capacity, tonnage — the "six-tenths rule" family, including the parametric O'Hara/Mular&Poulin formulas used below) through a factored/parametric estimate built up from major cost centres, to a detailed (definitive) estimate priced from completed engineering, quantity take-offs and vendor quotes. Each level trades estimating effort and time against accuracy, matching the AACE Class 5 (order-of-magnitude, ±30–50%) through Class 1 (definitive, ±3–10%) framework used across the mining and process industries.
2.1.2 Hugh Taylor's rule. Hugh Taylor's rule is a well-known mining-industry rule of thumb linking a project's economic mining rate (and hence much of its capital scale) to the size and depth of the orebody itself — commonly expressed as mine life in years being roughly proportional to the fourth root of the reserve tonnage (or, in its production-rate form, daily/annual mining rate scaling with a fractional power of total reserve tonnes), so that a bigger orebody supports a proportionately larger, but not linearly larger, production rate and mine life. It is used at the very earliest stage of overall cost estimation to set a defensible target production rate (and hence the capacity variable T that every downstream capital-cost formula, including all of Question 2.3, is built around) directly from an orebody's tonnage, before any detailed mine design exists to derive that rate a more rigorous way.
As a capital cost estimator today I would not apply a general inflation index (CPI) to a mining capital cost, because construction and mining-equipment costs have historically escalated at a different rate than consumer prices. Instead I would apply a mining/milling-specific cost index ratio, escalating each historical figure independently to 2019 dollars: $$C_{2019} = C_{1980}\times\dfrac{\text{Index}_{2019}}{\text{Index}_{1980}} \qquad\text{and}\qquad C_{2019} = C_{1998}\times\dfrac{\text{Index}_{2019}}{\text{Index}_{1998}}$$ using the Marshall & Swift Mining/Milling index (or, equivalently, the historical USBM/Camm capital-cost index family the O'Hara/Mular&Poulin formulas themselves are built from), reading the index value published for each of the three years from the current M&S M/M index tables and applying the ratio directly — exactly as Question 1.5.2 describes and exactly the operation used to keep the Question 2.3 formulas (originally published against a 1980s/1990s base year) valid for a present-day (2019) capital estimate. Because the two source years (1980, 1998) sit on different points of the same index series, each must be escalated with its own year-specific ratio — a single blended "18 years vs. 39 years" average factor would systematically mis-price whichever of the two costs is estimated less directly.
Given. Ore-only hoisting rate $T = 1500$ t/day; stope width $W = 10$ m; the O'Hara/Mular&Poulin parametric cost formulas quoted above for compressed-air plant ($C_1$), mine development ($C_2$), underground mining equipment ($C_5$) and the underground maintenance facility ($C_6$).
Find. $Q$, $C_1$ (2.3.1); $C_2$, $C_5$, $C_6$ (2.3.2); the total fixed cost excluding milling and $C_3,C_4,C_7$–$C_{10}$ (2.3.3); and a reliability comment (2.3.4).
Approach. Substitute $T$ and $W$ directly into each independent power-law formula, then sum the computed cost centres for the 2.3.3 total.
2.3.4 — Reliability and applicability of this methodology. These O'Hara/Mular&Poulin-style formulas are single-variable power-law regressions fitted to a historical database of built mines, so they are reliable for a fast, defensible order-of-magnitude (Class 4/5, roughly ±25–35%) screening estimate early in a project's evaluation — exactly the "quick fix" role identified in Question 1.5.4 — and they scale sensibly across a wide range of T and W, correctly capturing the direction (if not the exact magnitude) of economies of scale. Their applicability is limited, however, because: they were regressed against mines built in a specific era and jurisdiction, so unusual geology, remote-site logistics, extreme depth or a mining method outside the database's population can fall well outside the fitted relationship's valid range; they use only T and W as inputs, ignoring genuinely cost-driving factors such as rock competence (support cost), depth (haulage/ventilation cost) and labour-market conditions; and because escalating a decades-old regression via a single blended cost index (Question 2.2) compounds the base regression's uncertainty with the index's own approximation error. The methodology is therefore appropriate for screening/ranking alternative mine plans and for an early feasibility check, but a project actually proceeding to construction requires a detailed, engineered estimate before capital is committed.
| Item | Value |
|---|---|
| Q (compressed-air quantity) | 0.308 m3/s |
| C1 (compressor plant, C11+C12) | USD 180,100 |
| C2 (mine development) | USD 8,804,000 |
| C5 (underground mining equipment) | USD 4,869,200 |
| C6 (underground maintenance facility) | USD 1,236,100 |
| Total fixed cost (C1+C2+C5+C6) | USD 15,089,400 |