24-MMP-A3 Mineral Processing · May 2015
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Professional Examination 09-MMP-A3 Mineral Processing, May 2015. Closed book, 3 hours, approved Casio or Sharp calculator only. Five problems totalling 100 marks plus a 2-mark bonus: Problem 1 (34), Problem 2 (7), Problem 3 (17), Problem 4 (30, answer any five of nine), Problem 5 (12, answer any six of nine). Every question and every option is worked below, because the set is a study resource rather than a timed sitting.
Reference texts.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. The printed flowsheet carries fourteen unlabelled blocks (A to H, then J to N and P; the letters I and O are skipped, as is normal on engineering drawings) and four blocks that are already named: primary crusher, primary screen, regrind cyclone and third-stage cleaner flotation cells. The candidate list contains exactly fourteen unit operations, so the answer is a one-to-one assignment.
Find. The unit operation belonging at each lettered position, justified by the stream connections drawn on the flowsheet rather than by guesswork.
Approach. Read the diagram in three blocks — the closed crushing circuit, the closed grinding circuit and the flotation and dewatering train — and in each block use the recycle loops to fix the identity of the equipment, because a closed loop only makes sense for one pairing of machines.
Working from the primary crusher down, the primary screen sends its oversize sideways to A and its undersize downwards. A machine that takes screen oversize and discharges to another screen, C, is a secondary crusher, and the screen it feeds is the secondary screen. That screen's oversize goes right to B and B returns its product to the same screen: a closed-circuit third stage of crushing, so B is the tertiary crusher. The secondary screen's undersize joins the primary screen undersize and passes to the grinding circuit — the standard three-stage crushing arrangement of a 1970s porphyry copper mill.
In the grinding block, D takes the crushing product directly and discharges to E; E splits, sending one stream to F and one stream on to flotation, and F returns to E. Only a classifier can split a stream two ways, so E is the bank of hydrocyclones, F is the ball mill grinding the cyclone underflow, and D, which is fed dry crushed ore and needs no classifier of its own, is the rod mill. The same logic identifies the regrind loop lower down: the regrind cyclone underflow goes to J and J returns to the cyclone feed, so J is the regrind ball mill.
The flotation block is read from the tailings side. G receives the cyclone overflow, which is fresh flotation feed, so it is the rougher flotation cells; its tailing goes to H, whose concentrate returns to the rougher feed and whose tailing leaves as final mill tailings, which is exactly the duty of the scavenger flotation cells. The rougher concentrate is reground and then upgraded in a countercurrent cleaner train, so K and L are the first-stage and second-stage cleaner flotation cells feeding the named third-stage cells. Finally the concentrate is dewatered in three steps of decreasing water content: M is the thickener, N the filter and P the dryer.
| Position | Unit operation | The connection that proves it |
|---|---|---|
| A | Secondary crusher | Takes primary screen oversize, discharges to a screen |
| B | Tertiary crusher | Closed with C: takes its oversize, returns its product |
| C | Secondary screen | Splits crusher product; undersize joins the mill feed |
| D | Rod mill | First grinding stage on dry crushed ore, open circuit |
| E | Hydrocyclones | Two-way split: overflow to flotation, underflow to F |
| F | Ball mill | Closed with E, grinding the cyclone underflow |
| G | Rougher flotation cells | Fed by cyclone overflow, the fresh flotation feed |
| H | Scavenger flotation cells | Fed by rougher tails; concentrate recycles, tails leave |
| J | Regrind ball mill | Closed with the named regrind cyclone |
| K | 1st stage cleaner flotation cells | Fed by regrind cyclone overflow |
| L | 2nd stage cleaner flotation cells | Between the first and third cleaner stages |
| M | Thickener | First dewatering step on final concentrate |
| N | Filter | Second dewatering step, thickener underflow |
| P | Dryer | Last step before the concentrate leaves the plant |
Given. The mill treats a fixed tonnage of ore and produces one concentrate and one tailing, with all three copper assays measured.
| Quantity | Symbol | Value |
|---|---|---|
| Ore milled | F | 12 000 t/d |
| Mill feed assay | f | 0.50 % Cu |
| Tailing assay | t | 0.04 % Cu |
| Concentrate assay | c | 28.0 % Cu |
Find. The tonnes per day of copper concentrate produced, and the copper recovery that goes with it.
Approach. Write a solids balance and a copper balance around the whole plant and eliminate the tailing tonnage; this is the two-product formula.
A recovery of just over 92 per cent at a concentrate grade of 28 per cent copper is entirely typical of a British Columbia porphyry copper operation of that era, and the tailing assay of 0.04 per cent copper is the metallurgical evidence for it: only about eight per cent of the contained copper is being lost.
| Quantity | Value |
|---|---|
| Ratio of concentration, K | 60.78 t of ore per t of concentrate |
| Copper concentrate produced | 197.4 t/d |
| Tailing produced | 11 803 t/d |
| Copper recovery to concentrate | 92.13 % |
| Copper in concentrate | 55.28 t/d |
Given. A Bond work index of 16 and electricity at 6 cents per kilowatt hour, applied to the same 12 000 t/d of ore. The feed and product sizes are not stated, so the question asks explicitly for the assumptions to be listed.
Find. The daily cost of the electricity used to crush and grind the ore.
Approach. Bond's third theory gives the specific energy for the whole size reduction from run-of-mine to final grind; multiply by the tonnage and by the tariff.
Check: the assumptions this answer rests on.
If instead the work index is read in its original units of kilowatt hours per short ton, the 12 000 tonnes become 13 228 short tons, the daily energy becomes 167 338 kWh and the cost rises to about 10 040 dollars per day. Either answer is defensible provided the assumption is stated; what would not be defensible is quoting a number without saying which tonne is meant.
| Quantity | Value |
|---|---|
| Specific comminution energy (Bond) | 12.65 kWh/t |
| Energy consumed | 151 810 kWh/d |
| Average comminution power drawn | 6 325 kW |
| Power cost, metric tonne basis | 9 109 dollars per day (0.76 dollars per tonne) |
| Power cost, short ton basis | 10 040 dollars per day |
Given. The concentrate assays 28.0 per cent copper. The only two mineral species present are chalcopyrite, which carries 34.6 per cent copper and has a specific gravity of 4.2, and siliceous gangue of specific gravity 2.7.
Find. The specific gravity of the concentrate.
Approach. Convert the copper assay into a chalcopyrite content by stoichiometry, then combine the two minerals on a volume basis, because it is volumes and not densities that add.
The result sits much closer to the chalcopyrite value than to the gangue value, as it must, because the heavier mineral is also the more abundant one. Note the common trap: a mass-weighted average of the two specific gravities would give $0.8092 \times 4.2 + 0.1908 \times 2.7 = 3.91$, which is nearly 3 per cent high. Densities never average by mass.
| Quantity | Value |
|---|---|
| Chalcopyrite in the concentrate | 80.92 % by mass |
| Siliceous gangue in the concentrate | 19.08 % by mass |
| Specific gravity of the concentrate | 3.80 |
Given. The 197.4 t/d of concentrate calculated in part (b), assaying 28.0 per cent copper, sold on the stated smelter schedule against the stated operating costs.
| Item | Basis | Rate |
|---|---|---|
| Treatment charge | per tonne of concentrate | 100 |
| Payable copper | fraction of contained copper | 90 % |
| LME copper price | per tonne of copper | 2 500 |
| Mining cost | per tonne of ore | 4 |
| Milling cost | per tonne of ore | 3 |
| Freight to smelter | per tonne of concentrate | 30 |
Find. Income minus operating costs, in dollars per day.
Approach. Build the income from the payable copper only, then subtract the two ore-based costs and the two concentrate-based costs. Keeping those two families apart is what prevents the commonest error in this question.
Two features of the answer are worth reading. First, the margin is thin: 14 712 dollars on 124 378 dollars of revenue is a margin of about 12 per cent, or 1.23 dollars per tonne of ore against an operating cost of 9.14 dollars per tonne. Second, mining and milling together are 77 per cent of the total cost, so the plant's profitability is far more sensitive to ore grade and to the mining cost than it is to the smelter terms. A drop of 0.05 percentage points in head grade — from 0.50 to 0.45 per cent copper — would remove roughly 12 400 dollars per day of income and take the operation to break-even. This is exactly why the Bell mine, like most low-grade porphyry operations, lived and died by the copper price.
| Item | Dollars per day |
|---|---|
| Income from payable copper (49.75 t/d at 2 500) | 124 378 |
| Mining cost | 48 000 |
| Milling cost | 36 000 |
| Freight to smelter | 5 923 |
| Treatment charge | 19 742 |
| Total operating cost | 109 665 |
| Net operating profit | 14 712 |
| Net operating profit per tonne of ore | 1.23 |