NivaarExam PrepOfficial exam papers ↗

24-MMP-A3 Mineral Processing · May 2015

Question 1 of 6: The Bell Concentrator — Flowsheet, Metallurgical Balance and Operating Profit

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Professional Examination 09-MMP-A3 Mineral Processing, May 2015. Closed book, 3 hours, approved Casio or Sharp calculator only. Five problems totalling 100 marks plus a 2-mark bonus: Problem 1 (34), Problem 2 (7), Problem 3 (17), Problem 4 (30, answer any five of nine), Problem 5 (12, answer any six of nine). Every question and every option is worked below, because the set is a study resource rather than a timed sitting.

Reference texts.

Question 1: The Bell Concentrator — Flowsheet, Metallurgical Balance and Operating Profit (34 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(a) Identifying the fourteen unit operations

Given. The printed flowsheet carries fourteen unlabelled blocks (A to H, then J to N and P; the letters I and O are skipped, as is normal on engineering drawings) and four blocks that are already named: primary crusher, primary screen, regrind cyclone and third-stage cleaner flotation cells. The candidate list contains exactly fourteen unit operations, so the answer is a one-to-one assignment.

Find. The unit operation belonging at each lettered position, justified by the stream connections drawn on the flowsheet rather than by guesswork.

Approach. Read the diagram in three blocks — the closed crushing circuit, the closed grinding circuit and the flotation and dewatering train — and in each block use the recycle loops to fix the identity of the equipment, because a closed loop only makes sense for one pairing of machines.

PrimarycrusherPrimaryscreenASecondarycrusherBTertiarycrusherCSecondaryscreenDRod millEHydrocyclonesFBall millGRougherflotation cellsHScavengerflotation cellsRegrindcycloneK1st stage cleanerflotation cellsJRegrindball millL2nd stage cleanerflotation cells3rd cleanerflotation cellsMThickenerNFilterPDryerrecycleoverflowtailsscavenger concentrate2nd cleaner tails3rd cleaner tailsFinal concentrateMill tailingsBell concentrator, 12 000 t/d of copper ore
Figure 1. The Bell concentrator flowsheet with each lettered position identified. The three recycle loops - crusher/screen, cyclone/ball mill and regrind cyclone/regrind mill - are what fix the identifications.

Working from the primary crusher down, the primary screen sends its oversize sideways to A and its undersize downwards. A machine that takes screen oversize and discharges to another screen, C, is a secondary crusher, and the screen it feeds is the secondary screen. That screen's oversize goes right to B and B returns its product to the same screen: a closed-circuit third stage of crushing, so B is the tertiary crusher. The secondary screen's undersize joins the primary screen undersize and passes to the grinding circuit — the standard three-stage crushing arrangement of a 1970s porphyry copper mill.

In the grinding block, D takes the crushing product directly and discharges to E; E splits, sending one stream to F and one stream on to flotation, and F returns to E. Only a classifier can split a stream two ways, so E is the bank of hydrocyclones, F is the ball mill grinding the cyclone underflow, and D, which is fed dry crushed ore and needs no classifier of its own, is the rod mill. The same logic identifies the regrind loop lower down: the regrind cyclone underflow goes to J and J returns to the cyclone feed, so J is the regrind ball mill.

The flotation block is read from the tailings side. G receives the cyclone overflow, which is fresh flotation feed, so it is the rougher flotation cells; its tailing goes to H, whose concentrate returns to the rougher feed and whose tailing leaves as final mill tailings, which is exactly the duty of the scavenger flotation cells. The rougher concentrate is reground and then upgraded in a countercurrent cleaner train, so K and L are the first-stage and second-stage cleaner flotation cells feeding the named third-stage cells. Finally the concentrate is dewatered in three steps of decreasing water content: M is the thickener, N the filter and P the dryer.

Assignment of the fourteen lettered positions
PositionUnit operationThe connection that proves it
ASecondary crusherTakes primary screen oversize, discharges to a screen
BTertiary crusherClosed with C: takes its oversize, returns its product
CSecondary screenSplits crusher product; undersize joins the mill feed
DRod millFirst grinding stage on dry crushed ore, open circuit
EHydrocyclonesTwo-way split: overflow to flotation, underflow to F
FBall millClosed with E, grinding the cyclone underflow
GRougher flotation cellsFed by cyclone overflow, the fresh flotation feed
HScavenger flotation cellsFed by rougher tails; concentrate recycles, tails leave
JRegrind ball millClosed with the named regrind cyclone
K1st stage cleaner flotation cellsFed by regrind cyclone overflow
L2nd stage cleaner flotation cellsBetween the first and third cleaner stages
MThickenerFirst dewatering step on final concentrate
NFilterSecond dewatering step, thickener underflow
PDryerLast step before the concentrate leaves the plant

(b) Tonnes per day of copper concentrate

Given. The mill treats a fixed tonnage of ore and produces one concentrate and one tailing, with all three copper assays measured.

Given data, Problem 1(b)
QuantitySymbolValue
Ore milledF12 000 t/d
Mill feed assayf0.50 % Cu
Tailing assayt0.04 % Cu
Concentrate assayc28.0 % Cu

Find. The tonnes per day of copper concentrate produced, and the copper recovery that goes with it.

Approach. Write a solids balance and a copper balance around the whole plant and eliminate the tailing tonnage; this is the two-product formula.

  1. Write the two balances around the plant. Solids in equals solids out, and copper in equals copper out: $$\begin{aligned} F &= C + T \\ Ff &= Cc + Tt \end{aligned}$$ where $F$, $C$ and $T$ are the tonnages of feed, concentrate and tailing.
  2. Eliminate the tailing tonnage. Substituting $T = F - C$ into the copper balance and collecting the terms in $C$: $$Ff = Cc + (F-C)t \;\Longrightarrow\; C(c-t) = F(f-t)$$ which rearranges to the two-product formula $$\frac{C}{F} = \frac{f-t}{c-t}$$
  3. Substitute the assays. The numerator is the upgrade the plant has to achieve and the denominator is the upgrade one tonne of concentrate represents: $$\frac{C}{F} = \frac{0.50 - 0.04}{28.0 - 0.04} = \frac{0.46}{27.96} = 0.016452$$ so one tonne of concentrate is made from just over sixty tonnes of ore. The ratio of concentration is $K = 1/0.016452 = 60.78$.
  4. Scale to the daily tonnage. Multiplying by the ore rate: $$C = 12\,000 \times 0.016452 = 197.4\ \text{t/d}$$ $$\boxed{C = 197.4\ \text{tonnes per day of copper concentrate}}$$
  5. Check by recovery. Copper recovery to the concentrate follows from the same three assays, and it is the number a metallurgist would quote to check the answer: $$R = \frac{c(f-t)}{f(c-t)} \times 100 = \frac{28.0 \times 0.46}{0.50 \times 27.96} \times 100 = 92.13\ \%$$ Recomputing it from the tonnages instead, $197.4 \times 28.0 / (12\,000 \times 0.50) = 92.13\ \%$, gives the same figure, which confirms the arithmetic.

A recovery of just over 92 per cent at a concentrate grade of 28 per cent copper is entirely typical of a British Columbia porphyry copper operation of that era, and the tailing assay of 0.04 per cent copper is the metallurgical evidence for it: only about eight per cent of the contained copper is being lost.

Results, Problem 1(b)
QuantityValue
Ratio of concentration, K60.78 t of ore per t of concentrate
Copper concentrate produced197.4 t/d
Tailing produced11 803 t/d
Copper recovery to concentrate92.13 %
Copper in concentrate55.28 t/d

(c) Comminution power cost by Bond's equation

Given. A Bond work index of 16 and electricity at 6 cents per kilowatt hour, applied to the same 12 000 t/d of ore. The feed and product sizes are not stated, so the question asks explicitly for the assumptions to be listed.

Find. The daily cost of the electricity used to crush and grind the ore.

Approach. Bond's third theory gives the specific energy for the whole size reduction from run-of-mine to final grind; multiply by the tonnage and by the tariff.

Check: the assumptions this answer rests on.

  1. The comminution duty runs from run-of-mine ore to flotation feed, taken as $F_{80} = 150\,000$ micrometres (80 per cent passing 150 mm from the pit) and $P_{80} = 150$ micrometres, a normal primary grind for a porphyry copper ore of this vintage.
  2. The work index of 16 is treated as 16 kWh per tonne. Bond defined the work index in kilowatt hours per short ton; the short-ton reading is worked out at the end of this part and changes the answer by about 10 per cent.
  3. All the Bond efficiency factors EF1 to EF8 (wet or dry grinding, open circuit, oversize feed, fineness of grind, mill diameter) are taken as unity.
  4. Bond's energy is power at the mill pinion; motor and drive losses are neglected, so the purchased energy is taken equal to the pinion energy. A real plant would add roughly 5 to 8 per cent for these.
  5. The plant runs 24 hours a day at the stated 12 000 t/d, and no allowance is made for conveying, pumping, blowers or other ancillary power — the question asks for comminution only.
  1. State Bond's third theory of comminution. The energy needed is proportional to the difference of the reciprocal square roots of the product and feed sizes: $$W = 10\,W_i\left(\frac{1}{\sqrt{P_{80}}} - \frac{1}{\sqrt{F_{80}}}\right)$$ with $W$ in kWh per tonne, $W_i$ the work index and both sizes in micrometres.
  2. Evaluate the two size terms separately. Keeping them apart makes the structure of the answer obvious — almost all of the energy is spent making fines: $$\begin{aligned} \frac{10 W_i}{\sqrt{P_{80}}} &= \frac{160}{\sqrt{150}} = \frac{160}{12.247} = 13.064\ \text{kWh/t} \\ \frac{10 W_i}{\sqrt{F_{80}}} &= \frac{160}{\sqrt{150\,000}} = \frac{160}{387.30} = 0.4131\ \text{kWh/t} \end{aligned}$$ The feed term is only about 3 per cent of the product term, which is why crushing is cheap and grinding is not.
  3. Take the difference to get the specific energy. Subtracting: $$W = 13.064 - 0.4131 = 12.65\ \text{kWh per tonne of ore}$$ $$\boxed{W = 12.65\ \text{kWh/t}}$$
  4. Scale to the plant and to money. Multiplying by the daily tonnage gives the energy, and by the tariff the cost: $$\begin{aligned} E &= 12.65 \times 12\,000 = 151\,810\ \text{kWh/d} \\ \text{cost} &= 0.06 \times 151\,810 = 9\,109\ \text{per day} \end{aligned}$$ $$\boxed{\text{power cost} \approx 9\,100\ \text{dollars per day, or } 0.76\ \text{dollars per tonne of ore}}$$ Spread over 24 hours this is an installed comminution draw of about 6 325 kW, which is a sensible figure for a 12 000 t/d rod-mill and ball-mill plant and is a useful sanity check on the whole calculation.

If instead the work index is read in its original units of kilowatt hours per short ton, the 12 000 tonnes become 13 228 short tons, the daily energy becomes 167 338 kWh and the cost rises to about 10 040 dollars per day. Either answer is defensible provided the assumption is stated; what would not be defensible is quoting a number without saying which tonne is meant.

Results, Problem 1(c)
QuantityValue
Specific comminution energy (Bond)12.65 kWh/t
Energy consumed151 810 kWh/d
Average comminution power drawn6 325 kW
Power cost, metric tonne basis9 109 dollars per day (0.76 dollars per tonne)
Power cost, short ton basis10 040 dollars per day

(d) Specific gravity of the copper concentrate

Given. The concentrate assays 28.0 per cent copper. The only two mineral species present are chalcopyrite, which carries 34.6 per cent copper and has a specific gravity of 4.2, and siliceous gangue of specific gravity 2.7.

Find. The specific gravity of the concentrate.

Approach. Convert the copper assay into a chalcopyrite content by stoichiometry, then combine the two minerals on a volume basis, because it is volumes and not densities that add.

  1. Convert the copper assay to a mineral assay. All the copper reports to chalcopyrite, so the mass fraction of chalcopyrite in the concentrate is the copper assay divided by the copper content of pure chalcopyrite: $$x_{cp} = \frac{28.0}{34.6} = 0.8092$$ That is 80.92 per cent chalcopyrite. The balance, $x_g = 0.1908$ or 19.08 per cent, is siliceous gangue. This is worth a moment: a 28 per cent copper concentrate is a 81 per cent chalcopyrite concentrate, which is a much better result than the copper number alone suggests.
  2. Combine the minerals on a volume basis. One kilogram of concentrate occupies the sum of the volumes of its two components, and dividing through by that kilogram gives the reciprocal-density rule: $$\frac{1}{\rho_c} = \frac{x_{cp}}{\rho_{cp}} + \frac{x_g}{\rho_g}$$
  3. Substitute and evaluate. Working the two contributions separately: $$\begin{aligned} \frac{x_{cp}}{\rho_{cp}} &= \frac{0.8092}{4.2} = 0.19268 \\ \frac{x_g}{\rho_g} &= \frac{0.1908}{2.7} = 0.07065 \\ \frac{1}{\rho_c} &= 0.19268 + 0.07065 = 0.26333 \end{aligned}$$ Inverting, $$\rho_c = \frac{1}{0.26333} = 3.797$$ $$\boxed{\text{SG of the copper concentrate} = 3.80}$$

The result sits much closer to the chalcopyrite value than to the gangue value, as it must, because the heavier mineral is also the more abundant one. Note the common trap: a mass-weighted average of the two specific gravities would give $0.8092 \times 4.2 + 0.1908 \times 2.7 = 3.91$, which is nearly 3 per cent high. Densities never average by mass.

Results, Problem 1(d)
QuantityValue
Chalcopyrite in the concentrate80.92 % by mass
Siliceous gangue in the concentrate19.08 % by mass
Specific gravity of the concentrate3.80

(e) Net operating profit

Given. The 197.4 t/d of concentrate calculated in part (b), assaying 28.0 per cent copper, sold on the stated smelter schedule against the stated operating costs.

Given data, Problem 1(e), all money in dollars
ItemBasisRate
Treatment chargeper tonne of concentrate100
Payable copperfraction of contained copper90 %
LME copper priceper tonne of copper2 500
Mining costper tonne of ore4
Milling costper tonne of ore3
Freight to smelterper tonne of concentrate30

Find. Income minus operating costs, in dollars per day.

Approach. Build the income from the payable copper only, then subtract the two ore-based costs and the two concentrate-based costs. Keeping those two families apart is what prevents the commonest error in this question.

  1. Find the copper actually in the concentrate. At 28.0 per cent copper: $$m_{Cu} = 197.4 \times 0.280 = 55.28\ \text{t/d of contained copper}$$
  2. Apply the payable term. The smelter pays for only 90 per cent of the contained copper; the remaining 10 per cent is the smelter's deduction and is simply lost to the mine: $$m_{pay} = 0.90 \times 55.28 = 49.75\ \text{t/d of payable copper}$$
  3. Value the payable copper at the LME price. Multiplying by 2 500 dollars per tonne of copper: $$\text{income} = 49.75 \times 2\,500 = 124\,378\ \text{dollars per day}$$
  4. Build the cost side. Mining and milling are charged on the ore fed to the plant, while freight and treatment are charged on the concentrate shipped: $$\begin{aligned} \text{mining} &= 4 \times 12\,000 = 48\,000 \\ \text{milling} &= 3 \times 12\,000 = 36\,000 \\ \text{freight} &= 30 \times 197.4 = 5\,923 \\ \text{treatment} &= 100 \times 197.4 = 19\,742 \end{aligned}$$ Adding the four gives a total operating cost of $48\,000 + 36\,000 + 5\,923 + 19\,742 = 109\,665$ dollars per day.
  5. Take the difference. Income less operating cost: $$\text{profit} = 124\,378 - 109\,665 = 14\,712\ \text{dollars per day}$$ $$\boxed{\text{net operating profit} \approx 14\,700\ \text{dollars per day}}$$

Two features of the answer are worth reading. First, the margin is thin: 14 712 dollars on 124 378 dollars of revenue is a margin of about 12 per cent, or 1.23 dollars per tonne of ore against an operating cost of 9.14 dollars per tonne. Second, mining and milling together are 77 per cent of the total cost, so the plant's profitability is far more sensitive to ore grade and to the mining cost than it is to the smelter terms. A drop of 0.05 percentage points in head grade — from 0.50 to 0.45 per cent copper — would remove roughly 12 400 dollars per day of income and take the operation to break-even. This is exactly why the Bell mine, like most low-grade porphyry operations, lived and died by the copper price.

Results, Problem 1(e)
ItemDollars per day
Income from payable copper (49.75 t/d at 2 500)124 378
Mining cost48 000
Milling cost36 000
Freight to smelter5 923
Treatment charge19 742
Total operating cost109 665
Net operating profit14 712
Net operating profit per tonne of ore1.23
← Paper overview