NivaarExam PrepOfficial exam papers ↗

24-MMP-A3 Mineral Processing · Undated paper

Question 1 of 3: Copper Flotation Circuit – Flowsheet, Metallurgical Balance and Economics

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A3 Mineral Processing (National Exams May 2019). 3 hours duration, closed book; only an approved Casio or Sharp calculator permitted. Three questions constitute a complete exam paper (100 marks total).

Reference texts: Wills & Finch, Wills' Mineral Processing Technology, 8th ed. (comminution and Bond's Third Theory – Ch. 6; classification and hydrocyclones – Ch. 9; froth flotation, cells and flotation columns – Ch. 12; metallurgical balances, recovery/economic efficiency – Ch. 1 & 12; particle characterization, sedimentation and gravity concentration – Ch. 1 & 10); Taggart, Handbook of Mineral Dressing (classical definition of metallurgical/economic efficiency); SME Mining Engineering Handbook, 3rd ed. (porphyry copper mill flowsheets); BC Health, Safety and Reclamation Code for Mines for the Canadian regulatory context.

Question 1: Copper Flotation Circuit – Flowsheet, Metallurgical Balance and Economics (30 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(1) Flow sheet

Approach. Trace the description arrow by arrow: three parallel rougher banks combine on concentrate, feed a closed-circuit regrind mill/cyclone, gravity-feed a column surge tank, then two columns in series with a scavenger stage recycling its own concentrate back to the surge tank ahead of the columns.

Rougher flotation(3 parallel banks,16 Denver 600H each)Regrind ball mill9.5x14 ft, 670 hpRegrind cyclone20 in KrebsColumn surgetankColumn cell 17x40 ftColumn cell 27x40 ftConcentratethickenerScavenger cells16 x 300 ft3 DenverFinal tailingsboxOre feedCombined rougherconcentrateMill dischargeu/f recycleo/f (gravity)pumpedColumn 1 tailColumn 2 tailCol.1 concCol.2 concScav. conc(gravity)Scav. tails(gravity)Final conc.28% CuFinal tailings
Fig. 1 – Copper flotation circuit: three rougher banks combine on concentrate into a closed-circuit regrind mill/cyclone, gravity to a column surge tank, two columns in series to the concentrate thickener, and a scavenger stage recycling its concentrate to the surge tank while its tails report to final tailings.
Check – the source text does not state where rougher-bank TAILINGS report; only rougher CONCENTRATE routing is described. The sketch above follows the only tailings path the text actually specifies (the column-scavenger loop); rougher tailings are the other rejection point in a real circuit of this type and would typically join the same final tailings line.

(2)–(6) Metallurgical balance and economics

Given. Feed grade $f=0.31\%\text{ Cu}$; recovery $R=80\%$; concentrate grade $c=28\%\text{ Cu}$ (stated in the circuit description); mill throughput $30{,}000$ t/d of ore; chalcopyrite CuFeS₂ with atomic masses Cu 63.5, Fe 55.8, S 32; mining $\$3.00$/t ore, milling $\$4.00$/t ore, concentrate freight $\$150$/t, smelting $\$250$/t, 350 operating days/yr, copper payable at $\$7$/kg contained in the concentrate.

Given data
QuantitySymbolValue
Feed grade$f$0.31% Cu
Recovery$R$80%
Concentrate grade$c$28% Cu
Mill throughput$F$30,000 t/d
Atomic massesCu, Fe, S63.5, 55.8, 32
Mining / milling cost\$3.00 / \$4.00 per t ore
Freight / smelting\$150 / \$250 per t conc.
Operating days/yr350
Copper payment\$7/kg contained Cu

Find. (2) tailings grade $t$; (3) concentrate tonnes/day; (4) %Cu in pure chalcopyrite; (5) % chalcopyrite in the concentrate; (6)(i) Economic Efficiency (%); (6)(ii) operating profit ($M/yr).

Approach. Apply the two-product (recovery) formula to get the mass yield and tailings grade, scale by the daily throughput for the concentrate tonnage, use chalcopyrite stoichiometry for the mineral content, then build a full revenue/cost statement and compare it (per Taggart's classical definition) against a theoretically perfect concentration to obtain the Economic Efficiency.

  1. Mass yield and tailings grade. Recovery $R=\dfrac{c(f-t)}{f(c-t)}$ rearranges, using the mass-yield form $Y=\dfrac{Rf}{c}$: $$Y=\frac{Rf}{c}=\frac{0.80\times0.31}{28}=0.008857\ (0.886\%\text{ of feed mass})$$ $$t=\frac{f(1-R)}{1-Y}=\frac{0.31(1-0.80)}{1-0.008857}=\boxed{0.0626\%\ \text{Cu}}$$ Cross-check with the standard two-product form $Y=(f-t)/(c-t)=(0.31-0.0626)/(28-0.0626)=0.00886$ – matches.
  2. Concentrate produced per day. $$C=F\cdot Y=30{,}000\times0.008857=\boxed{265.7\ \text{t/d}}$$
  3. %Cu in pure chalcopyrite (CuFeS₂). Molar mass $M=63.5+55.8+2(32)=183.3$ g/mol: $$\%\text{Cu}=\frac{63.5}{183.3}\times100=\boxed{34.64\%}$$
  4. % chalcopyrite in the concentrate. The concentrate assays 28% Cu; if chalcopyrite is the only copper mineral, the concentrate's copper is diluted pure-chalcopyrite: $$\%\text{CuFeS}_2=\frac{c}{\%\text{Cu}_{\text{ccp}}}\times100=\frac{28}{34.64}\times100=\boxed{80.8\%}$$
  5. Revenue and cost statement (actual case). Copper recovered $=R\cdot F\cdot f=0.80\times30{,}000\times0.0031=74.4$ t/d $=74{,}400$ kg/d. $$\text{Revenue}=74{,}400\times\$7=\$520{,}800/\text{d}$$ $$\text{Mining}=\$3.00\times30{,}000=\$90{,}000/\text{d}$$ $$\text{Milling}=\$4.00\times30{,}000=\$120{,}000/\text{d}$$ $$\text{Freight}=\$150\times265.7=\$39{,}857/\text{d}$$ $$\text{Smelting}=\$250\times265.7=\$66{,}429/\text{d}$$ $$\text{Total cost}=90{,}000+120{,}000+39{,}857+66{,}429=\$316{,}286/\text{d}$$ $$\text{Net profit}=520{,}800-316{,}286=\boxed{\$204{,}514/\text{d}}$$
  6. (6)(ii) Operating profit, million \$/yr. $$\$204{,}514/\text{d}\times350\ \text{d/yr}=\$71.58\times10^6/\text{yr}\approx\boxed{\$71.6\ \text{million/yr}}$$
  7. (6)(i) Economic Efficiency (Taggart). E.E. compares the value actually realized per tonne of ore (net of freight and smelting, but not mining/milling, per Taggart's classical definition) against the value obtainable from a theoretically perfect concentration (100% recovery into pure, gangue-free chalcopyrite, same smelter terms). Actual case, per tonne of ore: $$V_{\text{actual}}=\frac{\text{Revenue}-\text{Freight}-\text{Smelting}}{F}$$ $$=\frac{520{,}800-39{,}857-66{,}429}{30{,}000}=\boxed{\$13.82/\text{t ore}}$$ Perfect-concentration case: all 0.31% Cu reports to a pure-chalcopyrite concentrate ($Y_{\text{perfect}}=f/\%\text{Cu}_{\text{ccp}}=0.31/34.64=0.008948$, $C_{\text{perfect}}=30{,}000\times0.008948=268.5$ t/d, Cu recovered $=93.0$ t/d $=93{,}000$ kg/d): $$V_{\text{perfect}}=\frac{93{,}000\times7-150\times268.5-250\times268.5}{30{,}000}=\boxed{\$18.12/\text{t ore}}$$ $$\text{E.E.}=\frac{V_{\text{actual}}}{V_{\text{perfect}}}\times100=\frac{13.82}{18.12}\times100=\boxed{76.3\%}$$
QuantityValue
(2) Tailings grade, $t$0.0626% Cu
(3) Concentrate produced265.7 t/d
(4) %Cu in pure chalcopyrite34.64%
(5) % chalcopyrite in concentrate80.8%
(6)(i) Economic Efficiency76.3%
(6)(ii) Operating profit\$71.6 million/yr
← Paper overview