NivaarExam PrepOfficial exam papers ↗

24-MMP-A4 Mine Valuation and Mineral Resource Estimation · May 2017

Question 18 of 18: Net Smelter Return – Simplified Copper-Only Model

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A4 Mine Valuation and Mineral Resource Estimation, 2017-May. 3 hours duration; one handwritten 8.5×11 in reference sheet permitted (not an open-book exam); only approved Sharp or Casio calculators allowed. Question 1 is compulsory (40 marks, parts 1.1–1.6); candidates then select THREE of the five optional Questions 2–6 (20 marks each) to complete the paper.

Reference texts: Isaaks & Srivastava, An Introduction to Applied Geostatistics (variogram modelling, kriging estimators, volume–variance relations); Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (mine valuation, NPV and cut-off grade methodology, mineable reserves); Gentry & O'Neil, Mine Investment Analysis (Canadian mining taxation, smelter/refining contract terms, net smelter return, transportation logistics); SME Mining Engineering Handbook, 3rd ed. (cost-estimating relationships, mineral exploration/evaluation stages, ore reserve classification); Evans, An Introduction to Ore Geology and Guilbert & Park, The Geology of Ore Deposits (ore deposit models); CIM Best Practice Guidelines and NI 43-101 (Canadian Securities Administrators).

Question 6.4: Net Smelter Return – Simplified Copper-Only Model (9 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

ParameterValue
Ore mined1,000 mt/day (mine works 5 days/week; mill runs continuously, 7 days/week)
Mined ore grade2.5% Cu
Unit conversion1 mt = 2205 lb; 1 lb = 0.4536 kg
Mill recovery85%
Concentrate grade21% Cu
Copper price$2.20/lb ($4,850/mt)
Fixed unit deduction1.1 units × 22.05 lb/unit = 24.255 lb/mt conc.
Treatment charge$100/mt concentrate
Transport, loading & representation$50/mt concentrate
Refining charge$0.10/lb payable Cu
Penalties / price participationnone assumed

Find. The full mass-balance and value chain from mined ore through payable metal to the NSR expressed as $/mt of ore, on the basis of the mine's 1,000 mt/day ore production.

Check
The question states the mine produces ore only 5 days/week while the mill runs 7 days/week continuously – this describes a mine/mill throughput mismatch requiring an ore stockpile buffer, but every quantity requested below (6.4.1–6.4.4) is defined on a PER-1,000-MT-OF-ORE basis, which converts directly and consistently to a per-day figure regardless of which day of the week that tonne was mined or milled. The mine/mill schedule detail therefore does not change any of the boxed results below; it is flagged here as a modelling assumption rather than silently ignored.
Ore 1,000 mt/day, 2.5% Cu Mill 85% recovery Concentrate 21% Cu, 101.19 mt/day Smelter -1.1 unit deduction -TC $100/mt, transport $50/mt -RC $0.10/lb payable NSV = $771.47/mt conc. NSR = $78.07/mt ORE
Fig. 6.4 – Mass and value chain: ore → mill (85% recovery) → 21%-Cu concentrate → smelter deductions/charges → net smelter value (per tonne concentrate) → NSR (per tonne ore), all on a 1,000 mt/day ore basis.

Approach. Work the mass balance forward from ore to concentrate (6.4.1), convert to a payable-metal basis per tonne of concentrate after the fixed unit deduction (6.4.2), net off treatment/transport/refining charges to get the net smelter value per tonne of concentrate (6.4.3), then convert back to a per-tonne-of-ORE basis via the concentrate:ore mass ratio to get the NSR (6.4.4).

  1. 6.4.1.1–6.4.1.5 Ore-to-concentrate mass balance. $$\text{Metal in ore} = 1{,}000 \times 0.025 = \boxed{25.0\text{ mt Cu/day}} \quad (6.4.1.1)$$ $$\text{Metal after mill recovery} = 25.0 \times 0.85 = \boxed{21.25\text{ mt Cu/day}} \quad (6.4.1.2)$$ $$\text{Concentrate tonnage} = \frac{21.25}{0.21} = \boxed{101.19\text{ mt concentrate/day}} \quad (6.4.1.3)$$ Contained metal in concentrate (6.4.1.4) must equal the metal that entered it, 21.25 mt Cu – a useful mass-balance check: 101.19 × 0.21 = 21.25 mt ✓. In pounds (6.4.1.5): $$21.25 \times 2205 = \boxed{46{,}856.25\text{ lb Cu/day}}$$
  2. 6.4.2.1–6.4.2.5 Payable metal, per tonne of concentrate. Re-expressing on a per-mt-of-concentrate basis: contained metal in concentrate (6.4.2.1) restates 6.4.1.4 as an intensity, i.e. the concentrate's own 21% grade. Metal per mt concentrate (6.4.2.2) = grade × 2205 lb/mt = 0.21 × 2205 = 463.05 lb Cu/mt conc. Metal per lb of concentrate (6.4.2.3) is simply the grade fraction itself, 0.21 lb Cu/lb conc. The fixed deduction (6.4.2.4): $$1.1\text{ units}\times 22.05\text{ lb/unit} = \boxed{24.255\text{ lb Cu/mt conc.}}$$ Payable metal (6.4.2.5): $$463.05 - 24.255 = \boxed{438.795\text{ lb payable Cu/mt conc.}}$$
  3. 6.4.3.1–6.4.3.5 Charges, deductions and net value. Refining charge (6.4.3.1), levied on PAYABLE metal only: $$0.1 \times 438.795 = \boxed{\$43.88/\text{mt conc.}}$$ Total value of charges (6.4.3.2) – treatment + transport + refining: $$100 + 50 + 43.88 = \boxed{\$193.88/\text{mt conc.}}$$ Value of the unit deduction itself (6.4.3.3), i.e. the metal the mine is NOT paid for, valued at the copper price: $$24.255 \times 2.2 = \boxed{\$53.36/\text{mt conc.}}$$ Value after deductions and refining, i.e. the net smelter value (6.4.3.4) – gross contained-metal value minus the deduction value minus all charges: $$\underbrace{463.05\times2.2}_{\text{gross }\$1{,}018.71} - 53.36 - 193.88 = \boxed{\$771.47/\text{mt conc. (NSV)}}$$ (Equivalently and consistently: payable metal value minus TC, transport and refining: 438.795×2.2 − 100 − 50 − 43.88 = 965.35 − 193.88 = 771.47.) Converting to a per-tonne-of-ORE basis (6.4.3.5) via the concentrate:ore ratio (101.19 mt conc. / 1,000 mt ore = 0.10119): $$771.47 \times 0.10119 = \boxed{\$78.07/\text{mt ore}}$$
  4. 6.4.4.1–6.4.4.3 NSR factor and NSR revenue. The NSR factor (6.4.4.1) benchmarks the realized ore value against the theoretical GROSS in-situ metal value (no recovery loss, no deductions/charges): gross in-situ value = 0.025 × 2205 × 2.2 = $121.28/mt ore, so $$\text{NSR factor} = \frac{78.07}{121.28} = \boxed{0.644\ (\approx 64.4\%)}$$ – i.e. the mine realizes about 64.4% of the ore's theoretical in-situ copper value once mill recovery, the smelter deduction, and treatment/transport/refining charges are all accounted for. The value per mt of ore (6.4.4.2) is the $78.07/mt ore figure carried forward from 6.4.3.5. The NSR expressed as $ revenue (6.4.4.3), applied to the mine's full 1,000 mt/day ore production: $$78.07 \times 1{,}000 = \boxed{\approx \$78{,}065/\text{day}}$$
QuantityValue
6.4.1.1 Metal in ore25.0 mt Cu/day
6.4.1.2 Metal after mill recovery21.25 mt Cu/day
6.4.1.3 Concentrate tonnage101.19 mt/day
6.4.1.5 Contained Cu in concentrate46,856.25 lb/day
6.4.2.5 Payable metal438.795 lb Cu/mt conc.
6.4.3.4 Net smelter value$771.47/mt conc.
6.4.3.5 / 6.4.4.2 Value per mt ore$78.07/mt ore
6.4.4.1 NSR factor0.644 (64.4%)
6.4.4.3 NSR revenue≈$78,065/day
Back to the paper →