24-MMP-A4 Mine Valuation and Mineral Resource Estimation · Undated paper
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A4 Mine Valuation and Mineral Resource Estimation, undated sitting. 3 hours duration; one handwritten 8.5×11 in reference sheet permitted (not an open-book exam); only approved Sharp or Casio calculators allowed. Question 1 is compulsory (parts 1.1–1.5); candidates then select THREE of the five optional Questions 2–6 (20 marks each) to complete the paper.
Reference texts: Isaaks & Srivastava, An Introduction to Applied Geostatistics (variogram modelling, anisotropy, volume–variance relations); Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (mine scheduling, NPV/valuation methods, stripping-ratio economics); Gentry & O'Neil, Mine Investment Analysis (Canadian mining taxation, CCA classes, smelter/refining contract terms, net smelter return); SME Mining Engineering Handbook, 3rd ed. (mineral exploration/evaluation stages, ore reserve classification); Guilbert & Park, The Geology of Ore Deposits (volcanogenic massive sulphide genesis); CIM Best Practice Guidelines and NI 43-101 (Canadian Securities Administrators).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Yes — the underlying scheduling logic transfers directly, because both "waste mining" in an open pit and "development" in an underground mine share the same defining feature: non-revenue-generating work that must be completed ahead of and in a fixed ratio to ore production before that ore can be extracted. The open pit's North-West-Corner, quota-driven, "waste-ahead-of-ore" scheduling method maps onto underground development as "development-ahead-of-stope" scheduling: development metres (drifts, ramps, raises, sill/crown pillars) take the place of waste tonnes, and stope/ore tonnes take the place of open-pit ore tonnes, with the same rule that a stope cannot be mined until its access development is complete, exactly as an ore bench cannot be mined until the waste above it is stripped. The specific "development ratio" (development metres per tonne of ore, the underground analogue of the stripping ratio) varies strongly by method: sublevel/longhole open stoping requires comparatively low development intensity per tonne (large stope volumes accessed by relatively few sublevel drifts), similar to a low-stripping-ratio pit year; cut-and-fill and shrinkage stoping require continuous, ongoing development-like access work throughout extraction (backfill/access drives advancing with the stope face), more analogous to a sustained moderate stripping ratio every period rather than a front-loaded one; and block/panel caving requires an unusually large, front-loaded capital development campaign (undercut, drawpoints, extraction level) before any ore is drawn at all, closely analogous to the open pit's heavy pre-production stripping years. In every case, the same fleet-smoothing and priority-sequencing logic from 4.4.1 applies: a planner should sequence development to avoid both idle production capacity (development lagging too far behind) and unnecessarily front-loaded capital spend (development racing too far ahead), just as waste stripping is balanced against ore production in the open pit case.