NivaarExam PrepOfficial exam papers ↗

24-MMP-A5 Surface Mining Methods and Design · December 2014

Question 9 of 13: Truck-Shovel Dispatch – Closed Out vs. Dispatched

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A5 Surface Mining Methods and Design, 2014-Dec. 3 hours duration, closed book; one hand-written 8.5×11 inch reference sheet and an approved Casio or Sharp calculator permitted. Question 1 is compulsory (40 marks, all seven parts 1.1–1.7); a candidate then selects THREE of Questions 2–7 (each worth 20 marks).

Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (dragline stripping systems, truck-shovel productivity, mine dewatering, mine cost estimation); Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design, 3rd ed. (block-model economics, floating/moving-cone algorithm, the Lerchs–Grossmann graph-theoretic pit-optimization method); Kennedy, B.A. (ed.), Surface Mining, 2nd ed., SME (dragline range-diagram geometry, stripping methods); Lerchs, H. & Grossmann, I.F. (1965), “Optimum Design of Open-Pit Mines,” CIM Bulletin, 58, 47–54; Mular, A.L. & Poulin, R. (1998), CapCosts: A Handbook for Estimating Mining and Mineral Processing Equipment Costs, CIM Special Volume 47 (parametric open-pit capital-cost formulae used throughout Question 7).

Question 3: Truck-Shovel Dispatch – Closed Out vs. Dispatched (20 marks, optional)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Load (incl. positioning) 3.0 min; loaded haul 12.0 min (both ore and waste); backup+dump 1.0 min; empty return 8.0 min. Full routing set: Shovel 1 (ore)→Crusher 12 min, Crusher→Shovel 1 8 min; Shovel 2 (waste)→Waste Dump 12 min, Waste Dump→Shovel 2 8 min; Crusher→Shovel 2 4 min; Waste Dump→Shovel 1 3 min; load at Shovel 1 3 min, dump ore at Crusher 1 min; load waste at Shovel 2 3 min, dump at Waste Dump 1 min.

Find. The theoretical cycle time and match factor (3.1), the closed-out and dispatched truck requirements (3.4), which is more efficient (3.5), and the resulting loads delivered in an 8-hour shift (3.6).

Approach. A closed-out loop sizes independently off its own cycle time; a dispatched fleet instead shares the whole pool around ONE combined circuit built from the SHORTER cross-legs (Crusher→Shovel 2, Waste Dump→Shovel 1), so both are found from cycle-time÷load-time, just applied to a different loop.

  1. 3.1 – Theoretical cycle time and match factor. $$T_c=3.0+12.0+1.0+8.0=\boxed{24.0\text{ min}}$$ The theoretical (matched) truck count for one shovel is $N=T_c/T_{load}=24/3=8$; substituting into $MF=N\,T_{load}/(N_{shovels}T_c)$ at that count gives $$MF=\dfrac{8\times3.0}{1\times24.0}=\boxed{1.0}$$ – the textbook definition of a theoretically matched fleet.
3.2 Closed-out (dedicated loops) Shovel 1 (ore) Crusher Shovel 2 (waste) Waste Dump Dispatched (shared loop, cross-links) Shovel 1 Crusher Shovel 2 Waste Dump
Fig. 3.2 – closed out keeps each truck on one dedicated loop; dispatched shares the fleet on one loop using the Waste Dump→Shovel 1 (3 min) and Crusher→Shovel 2 (4 min) cross-links.
  1. 3.4 – Closed-out truck requirement. Each dedicated loop uses the SAME per-loop cycle time as 3.1 (load+haul+dump+return, here 24 min for either shovel): trucks per shovel $=24/3=8$; with two independent loops, $$N_{closed}=8+8=\boxed{16\text{ trucks}}$$
  2. Dispatched supercircuit. Using the cross-links, one shared circuit delivers ONE ore load and ONE waste load: Load@S1(3)+S1→Crusher(12)+DumpOre(1)+Crusher→S2(4)+LoadWaste@S2(3)+S2→WasteDump(12)+DumpWaste(1)+WasteDump→S1(3): $$T_{circuit}=3+12+1+4+3+12+1+3=\boxed{39\text{ min for 2 loads}}$$
  3. 3.4 – Dispatched truck requirement. A truck must arrive at whichever shovel is due every $T_{load}=3$ min to keep BOTH shovels saturated: $$N_{dispatched}=T_{circuit}/T_{load}=39/3=\boxed{13\text{ trucks}}$$

3.5 – Which is more efficient. Dispatched needs only 13 trucks against 16 for closed out to keep both shovels at maximum production – a saving of $$\left(1-\dfrac{13}{16}\right)\times100=\boxed{18.75\%\text{ fewer trucks}}$$ so the dispatched configuration is more efficient: it exploits the shorter cross-legs (4 and 3 min) in place of a second full dedicated loop, sharing the whole fleet across both shovels instead of splitting it 8/8.

3.6 – Loads per 8-hour shift, dispatched configuration. $$\text{circuits per truck}=\left\lfloor\dfrac{8\times60}{39}\right\rfloor=\lfloor12.31\rfloor=12$$ Each circuit delivers one ore load and one waste load, so with 13 trucks: $$\text{total loads}=12\times13\times2/2=\boxed{156\text{ loads/shift (78 to the crusher, 78 to the dump)}}$$ This is a theoretical ceiling that assumes zero queuing delay, perfectly timed arrivals and no breakdowns, shift-change, blast or weather delays; a real 8-hour shift typically achieves 60–85% of the theoretical figure once those losses are included, so roughly 95–130 combined loads (not 156) is a more realistic expectation, though the theoretical value remains the correct basis for fleet sizing.

Final results – Question 3
ItemValue
3.1 Theoretical cycle time24.0 min
3.1 Match factor at theoretical fleet1.0
3.4 Trucks – closed out16
3.4 Trucks – dispatched13 (supercircuit 39 min)
3.5 More efficient configurationDispatched (18.75% fewer trucks)
3.6 Theoretical loads/8 h shift (dispatched)156 (78 ore + 78 waste); realistically ~95–130
Check: this data set (load 3.0/haul 12.0/backup+dump 1.0/return 8.0 min; here the SAME leg times instead form a two-shovel, two-DIFFERENT-dump network (ore to the crusher, waste to the dump), so the dispatched supercircuit correctly carries one load of EACH material per circuit (39 min, not 36), giving 13 trucks rather than 12 – the two problems share input data but are not the same optimization and must not be answered identically.