NivaarExam PrepOfficial exam papers ↗

24-MMP-A5 Surface Mining Methods and Design · May 2016

Question 9 of 11: Truck–Shovel Cycle Time, Match Factor and Dispatch

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Exams, May 2016 — 09-MMP-A5, Surface Mining Methods and Design. Three hours, closed book; one hand-written, double-sided 8.5×11″ reference sheet and an approved Sharp or Casio calculator are permitted. Question 1 is compulsory (six parts, 40 marks); candidates then choose three of the five optional questions (2–6, 20 marks each) for a 100-mark paper — only the first three optional answers appearing in the answer book are graded. All six parts of Question 1 and all five optional questions are answered here, because this set is a study resource rather than an exam script.

Reference texts. The answers below are keyed to the works normally recommended for this syllabus code:



Question 4: Truck–Shovel Cycle Time, Match Factor and Dispatch (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Load time 3.0 min, haul (loaded, same-side) 12.0 min, dump 1.0 min, empty return (same-side) 8.0 min; the detailed dispatch network additionally offers two short cross-routes: Crusher→Shovel 2 (4.0 min) and Waste Dump→Shovel 1 (3.0 min).

Find. 4.1 theoretical closed-out cycle time and match factor; 4.3 trucks required, closed-out vs. dispatched; 4.4 the more efficient configuration; 4.5 truckloads per 8-hour shift.

Shovel 1(ore)CrusherShovel 2(waste)Waste Dump12 min (ore haul)4 min (short cross-haul)12 min (waste haul)3 min (short cross-haul)Dispatched loop (39 min total): load ore(3) -> haul S1-CR(12) -> dump(1) -> cross CR-S2(4) -> load waste(3) -> haul S2-WD(12) -> dump(1) -> cross WD-S1(3)
The two short cross-routes (green) that make “dispatched” operation possible: a truck dumping ore at the Crusher can cross directly to Shovel 2 (4 min) instead of returning empty to Shovel 1 (8 min); a truck dumping waste at the Waste Dump can cross directly to Shovel 1 (3 min) instead of returning to Shovel 2 (8 min).

Approach. 4.1: sum the four closed-out cycle legs, then use the match-factor identity (number of trucks needed to keep one shovel continuously loaded) $= T_c/T_{\text{load}}$. 4.3: closed-out totals two independent single-shovel fleets; dispatched instead forms one continuous circulating loop through both shovels and both dump points, using the short cross-routes as the return legs, and the number of trucks needed to keep both shovels continuously fed is the loop time divided by the loading interval. 4.5: convert the dispatched loop's per-truck delivery rate to a per-shift total.

  1. 4.1 — closed-out cycle time and match factor. $$T_c = 3.0+12.0+1.0+8.0 = \boxed{24.0\ \text{min}}$$ Match factor $\text{MF}=\dfrac{N_{\text{trucks}}\times T_{\text{load}}}{N_{\text{shovels}}\times T_c}$; for a single shovel, $\text{MF}=1$ (trucks exactly matched to shovel capacity, no truck or shovel queuing) requires $$N_{\text{trucks/shovel}} = \frac{T_c}{T_{\text{load}}} = \frac{24.0}{3.0} = \boxed{8\ \text{trucks per shovel}}$$
  2. 4.3 — closed-out truck requirement. Two independent shovel/dump pairs, each needing 8 trucks at MF$=1$: $$N_{\text{closed-out}} = 2\times 8 = \boxed{16\ \text{trucks}}$$
  3. 4.3 — dispatched loop and truck requirement. Using the short cross-routes, a single truck can serve both shovels in one continuous loop: load ore at S1 (3) → haul to Crusher (12) → dump (1) → cross to S2 (4) → load waste (3) → haul to Waste Dump (12) → dump (1) → cross back to S1 (3). $$T_{\text{loop}} = 3+12+1+4+3+12+1+3 = \boxed{39.0\ \text{min}}$$ With $N$ trucks evenly spaced around this shared loop, the interval between successive trucks passing any fixed point (in particular, each shovel) is $T_{\text{loop}}/N$; setting this equal to the 3.0-min load time (so neither shovel ever waits) gives $$N_{\text{dispatched}} = \frac{T_{\text{loop}}}{T_{\text{load}}} = \frac{39.0}{3.0} = \boxed{13\ \text{trucks}}$$
  4. 4.4 — which is more efficient. Dispatched needs only 13 trucks (vs. 16 closed-out) to keep both shovels continuously loaded, because the two short cross-routes (4 and 3 min) replace the long same-side empty returns (8 min each) that closed-out trucks would otherwise run empty — a 19 % fleet reduction for the same production.
  5. 4.5 — truckloads per 8-hour shift (dispatched, the more efficient configuration). Each of the 13 trucks completes one full 39-min loop delivering exactly one ore load (to the crusher) and one waste load (to the dump): $$\text{loads/min} = \frac{13}{39} = 0.3333, \qquad \text{loads in an 8-h shift} = 0.3333\times(8\times60) = \boxed{160\ \text{truckloads}}$$ (160 to the crusher and 160 to the waste dump, since every loop delivers one of each.)
QuantityResult
4.1 Closed-out cycle time24.0 min
4.1 Trucks/shovel at MF = 18
4.3 Closed-out fleet16 trucks
4.3 Dispatched loop time / fleet39.0 min / 13 trucks
4.4 More efficient configurationDispatched (19% fewer trucks for equal production)
4.5 Truckloads per 8-h shift160 to crusher, 160 to waste dump
Check: the 160-loads-per-shift figure assumes zero queuing, breakdown or shift-change loss and perfectly even truck spacing around the loop — a real operation typically achieves 80–90 % of this theoretical maximum once spotting variability, weather and maintenance are included, and would carry a small spare-truck allowance above the theoretical 13.