Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
09-MMP-B8, Mine Management & Systems Analysis — May 2018 sitting. 3-hour closed-book exam, answer all 4 questions for a total of 100 marks, Appendix A (discounted cash-flow factor tables) attached.
Reference texts. Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (pit optimization, truck/shovel matching, mine scheduling); Hartman & Mutmansky (eds.), SME Mining Engineering Handbook (mine life-cycle, project economics, haulage systems); Blank & Tarquin, Engineering Economy (DCF/NPV/PVR/payback); Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide) (Critical Path Method).
Check: the exam booklet is headed “09-MMP-B8 Mine Management & Systems Analysis”, not Rock Slope Engineering. The content below solves the paper as printed (mine-life/DCF economics, shovel-truck fleet analysis, CPM project scheduling, 2-D pit-limit design), not rock-slope-stability content.
Question 3: Project Scheduling and Analysis (30 marks)
New ore zone development — task list and dependencies
#
Task description
Duration (months)
Depends on task #
1
Drive ramp to base of new zone
11
none
2
Develop/equip new raises for hoisting and ventilation
16
1
3
Develop new u/g exploration drilling gallery
2
1
4
Complete new u/g exploration drilling program
18
3
5
Develop ore body model and mining schedule
2
4
6
Reconfigure mine ventilation system for new zone
4
2
7
Expand u/g diesel powered equipment fleet
4
6
8
Develop upper mining level for new zone
8
7
9
Develop lower mining level for new zone
10
7
10
Develop slot raises for initial stope blocks
2
8, 9
11
Drill open stoping blastholes for initial 2 stopes
1
10, 5
12
First production from stopes in new zone
0 (milestone)
11, 2
Find. (a) a Gantt chart of the schedule; (b) the critical path and the shortest possible project duration.
Approach. Build the activity-on-node network from the given dependencies, run a forward pass to get each task's earliest start/finish (ES/EF), then a backward pass from the project finish to get each task's latest start/finish (LS/LF); the critical path is the chain of tasks with zero total float (LS−ES=0), and the Gantt chart plots every task at its earliest start with float shown for non-critical tasks.
a) Gantt chart
Fig. 3.1 — Gantt chart, each task plotted at its earliest start (ES); dashed tails show total float for non-critical tasks.
b) Critical Path Method
Forward pass (ES/EF). $ES$ of a task is the largest $EF$ among its predecessors ($ES=0$ for Task 1). Task 1: ES 0, EF 11. Task 2 (dep. 1): ES 11, EF 27. Task 3 (dep. 1): ES 11, EF 13. Task 4 (dep. 3): ES 13, EF 31. Task 5 (dep. 4): ES 31, EF 33. Task 6 (dep. 2): ES 27, EF 31. Task 7 (dep. 6): ES 31, EF 35. Task 8 (dep. 7): ES 35, EF 43. Task 9 (dep. 7): ES 35, EF 45. Task 10 (dep. 8, 9): $ES=\max(43,45)=45$, EF 47. Task 11 (dep. 10, 5): $ES=\max(47,33)=47$, EF 48. Task 12 (dep. 11, 2): $$\boxed{ES_{12}=\max(48,27)=48\ \text{months} = \text{project duration}}$$
Backward pass (LS/LF). Starting from $LF_{12}=48$ and working back, $LS$ of a task is the smallest $LS$ among its successors minus its own duration. Task 12: LF 48, LS 48. Task 11 (feeds 12): LF 48, LS 47. Task 2 (feeds 12 and 6): $LF=\min(48,27)=27$, LS 11. Task 10 (feeds 11): LF 47, LS 45. Task 9 (feeds 10): LF 45, LS 35. Task 8 (feeds 10): LF 45, LS 37. Task 7 (feeds 8, 9): $LF=\min(37,35)=35$, LS 31. Task 6 (feeds 7): LF 31, LS 27. Task 5 (feeds 11): LF 47, LS 45. Task 4 (feeds 5): LF 45, LS 27. Task 3 (feeds 4): LF 27, LS 25. Task 1 (feeds 2, 3): $$LF_1=\min(11,25)=11,\qquad LS_1=11-11=0$$
Total float and the critical path. Float $=LS-ES$ for every task: Task 1 float 0; Task 2 float 0; Task 3 float 14; Task 4 float 14; Task 5 float 14; Task 6 float 0; Task 7 float 0; Task 8 float 2; Task 9 float 0; Task 10 float 0; Task 11 float 0; Task 12 float 0. The only zero-float chain is Tasks 1→2→6→7→9→10→11→12: $$\boxed{\text{Critical path: } 1\rightarrow2\rightarrow6\rightarrow7\rightarrow9\rightarrow10\rightarrow11\rightarrow12,\ \ 11+16+4+4+10+2+1=48\ \text{months}}$$
The result again rewards checking the arithmetic rather than the task count: Task 9 (lower-level development, 10 months) is critical while the parallel Task 8 (upper-level development, 8 months, same start) is not — both start together at month 35 once the diesel fleet expansion (Task 7) is done, but Task 9 finishes 2 months later and is the one Task 10 (slot raises) must actually wait for, leaving Task 8 with 2 months of float. Separately, the exploration-drilling branch (Tasks 3→4→5) has a generous 14 months of float even though it includes the single longest individual activity in the network (18 months for Task 4) — it simply starts and can finish well before the raise-development/ventilation/fleet chain that actually paces the project.