24-Pet-B3 Petroleum Geology · May 2016

Question 14 of 22

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams, May 2016 — 98-Pet-B3, Oil and Gas Evaluation and Economics (3 hours, closed book, approved non-programmable calculator only). The exam's own cover page is titled "Oil and Gas Evaluation and Economics" and every question is property valuation / reserves & production economics / DCF-NPV screening content — no geology anywhere.

Reference texts: Thompson & Wright, Oil Property Evaluation; Canadian Oil and Gas Evaluation Handbook (COGEH), Vol. 1 (Society of Petroleum Evaluation Engineers, Calgary Chapter); National Instrument 51-101, Standards of Disclosure for Oil and Gas Activities (Canadian Securities Administrators); SPE/WPC/AAPG/SPEE Petroleum Resources Management System (PRMS); Economides & Nolte, Reservoir Stimulation; Ahmed, Reservoir Engineering Handbook.

The exam's own instructions ask for only 7 of the 10 short-answer questions and note the Cash-Flow/Future-Value tables are graded by column; for "choose N of M" exams, every item below is answered in full as a study resource. Questions 1–10 correspond to the exam's printed Short-Answer items 1–10; Questions 11–20 correspond to the printed Multiple-Choice items 1–10; Question 21 is the Future Value table; Question 22 is the Cash Flow table.

Question 14

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

a. Only the in-situ bitumen which might be heated
b. Only the bitumen in deposits over 10 m thick
c. Bitumen deposits which have some recovery assigned to them ← correct
d. All bitumen which is in thick zones which cannot be mined
e. Amount of production which can be produced at a SOR < 5

Answer: (c). “Effective” in-place bitumen is the sub-set of the total original bitumen in place (OBIP) to which a recovery process and a recovery factor have actually been assigned (SAGD, CSS, mining, or a resource judged technically/economically recoverable by some method) — it excludes bitumen with no assigned recovery process, regardless of its thickness or heating status.