Question 1 of 7: Plastic design of the steel rigid frame; welded connection at C
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 07-Str-A5 Advanced Structural Design, National Exams, May 2014 — 3 hours, closed book (handbooks and textbooks permitted, no notes on them; Casio or Sharp approved calculator). Seven questions of equal value; any five constitute a complete paper and only the first five presented are marked. All seven are solved here, because the set is intended as a study resource. All loads printed on the figures are unfactored.
Reference texts. CSA S16 Design of Steel Structures with the CISC Handbook of Steel Construction — plastic design (Cl. 8.6, 13.7), lateral–torsional buckling (Cl. 13.6), beam-columns (Cl. 13.8), plate girders (Cl. 14), composite beams (Cl. 17), welded connections (Cl. 13.13, 21); CSA A23.3 Design of Concrete Structures — flexure and shear (Cl. 10, 11), slenderness (Cl. 10.13–10.16), deflection (Cl. 9.8), footings (Cl. 15), prestressed concrete (Cl. 18); NBCC for load combinations; C. G. Salmon, J. E. Johnson & F. A. Malhas, Steel Structures: Design and Behavior; J. G. MacGregor & J. K. Wight, Reinforced Concrete: Mechanics and Design; T. Y. Lin & N. H. Burns, Design of Prestressed Concrete Structures; L. S. Beedle, Plastic Design of Steel Frames.
Check: load factors. The paper states only that the printed loads are unfactored, and gives no dead/live split. Every question below therefore treats each printed concentrated load as specified live load and factors it by $\alpha_L = 1.5$ (NBCC principal case $1.25D + 1.5L$); member self-weight, wherever it matters, is taken from the trial section and factored at $1.25$. A candidate assuming a different split obtains proportionally different sizes; the method is what is examined.
Check: section properties. Every steel section selected below is quoted by its plate dimensions (flange $b \times t$, web $h \times w$) and every property — $A$, $I_x$, $I_y$, $S$, $Z$, $J$, $C_w$, $r_x$, $r_y$ — is computed from those dimensions with root fillets neglected, which is slightly conservative. This makes every line checkable without a handbook; a rolled W-shape of equal or greater properties may be substituted directly.
Check: readings taken from the examination drawing. Three details are shown on the drawing but not stated in the question text. In Figure 1 the bases at A and D carry the fixed-support hatching and the question text says "the frame is fixed at the bases A and D", so both bases are fixed and the frame is three times statically indeterminate. In Figure 4 the 100 kN arrow at D points towards the column, i.e. to the left; A and E both carry pin symbols, making that frame indeterminate to the first degree. In Figure 5 the deck is 3 + 3 = 6 m wide over three beams spaced at 2.5 m, leaving 0.5 m overhangs — the slab-thickness annotation is not legible on the printed figure, so the deck thickness is designed in Question 7 rather than read off.
[Figure not reproduced: Figure 1 as printed on the examination paper: rectangular steel portal, fixed at A and D, beam capacity 1.5 M₊ and column capacity M₊. All loads shown are unfactored. See the official exam paper.]
Question 1: Plastic design of the steel rigid frame; welded connection at C (12 + 8 = 20 marks)
Given. Rectangular portal ABCD, fixed at A and D; column height 8 m, beam span 15 m with the 250 kN load at mid-span (7.5 m each side). Plastic capacities: columns $M_p$, beam $1.5M_p$. Specified loads from Figure 1:
Action
Point of application
Specified
Factored ($\times 1.5$)
Horizontal
joint B
80 kN
$H = 120$ kN
Vertical
joint B
500 kN
750 kN
Vertical
mid-span of BC
250 kN
$W = 375$ kN
Vertical
joint C
500 kN
750 kN
Find. The plastic moment $M_p$ required for collapse under the factored loads, welded I-sections for the beam BC and the column CD that provide it, and a welded moment connection at the knee C.
The three independent collapse mechanisms. Combining (i) and (ii) cancels the hinge at B, which is why the combined mechanism needs less capacity than the beam mechanism alone.
Approach. Apply the kinematic (upper-bound) method to the three independent mechanisms, take the largest $M_p$ they demand, confirm by a static (lower-bound) check that a bending-moment distribution exists everywhere within capacity, then select Class 1 welded sections and detail the knee so that the hinge forms in the member and not in the weld.
Part (a) — count the redundancies and list the mechanisms. A portal fixed at both bases has six reaction components and three equations of statics, so it is indeterminate to the third degree; collapse therefore needs four hinges, and there are $n - r = 5 - 3 = 2$ independent mechanisms plus their combination. The two vertical loads at B and C sit directly over the columns and generate no beam bending, so only the 250 kN mid-span load drives the beam mechanism and only the 80 kN load drives sway.
Beam mechanism. Hinges form at B, at mid-span and at C. At B and C the beam offers $1.5M_p$ but the column only $M_p$, so the hinge forms in the column and absorbs $M_p$; the mid-span hinge is in the beam and absorbs $1.5M_p$ through a relative rotation $2\theta$. Equating internal and external work,
$$M_p\theta + 1.5M_p(2\theta) + M_p\theta = W\left(\tfrac{L}{2}\right)\theta \;\Rightarrow\; 5M_p\theta = 375 \times 7.5\,\theta$$
$$\boxed{M_p = \frac{2812.5}{5} = 562.5\ \text{kN}\cdot\text{m}}$$
Sway mechanism. Hinges form at A, B, C and D, all four in columns of capacity $M_p$, each rotating $\theta$ while the storey drifts $h\theta$:
$$4M_p\theta = H h \theta = 120 \times 8\,\theta \;\Rightarrow\; M_p = \frac{960}{4} = 240\ \text{kN}\cdot\text{m}$$
Sway alone is far from critical, as expected for a frame whose horizontal load is only 80 kN against 1250 kN of gravity.
Combined mechanism. Superimposing the two cancels the hinge at B, because the rotations there are equal and opposite; the internal work loses $2M_p\theta$:
$$(5 + 4 - 2)M_p\theta = 7M_p\theta = 2812.5\theta + 960\theta = 3772.5\theta \;\Rightarrow\; M_p = 538.9\ \text{kN}\cdot\text{m}$$
Combining reduces the demand here, so the beam mechanism governs. Taking the largest of the three, the design value is $M_p = 562.5$ kN·m for the columns and $1.5M_p = 843.75$ kN·m for the beam.
Static (lower-bound) check — is that really the collapse load? With hinges at B, mid-span and C the beam is determinate: its end moments are $-562.5$ kN·m and the free moment is $WL/4 = 375 \times 15/4 = 1406.25$ kN·m, so the mid-span value is $1406.25 - 562.5 = 843.75 = 1.5M_p$, exactly at capacity. Sharing the 120 kN storey shear equally between the columns gives base moments
$$M_A = M_D = 562.5 - 60 \times 8 = 82.5\ \text{kN}\cdot\text{m} \;<\; M_p$$
A distribution therefore exists that is everywhere within capacity, so the kinematic and static solutions coincide and $M_p = 562.5$ kN·m is the true collapse value.
Section requirements. For a Class 1 section $M_r = \phi Z F_y$ with $\phi = 0.90$:
$$Z_{\text{col}} \geq \frac{562.5 \times 10^6}{0.9 \times 350} = 1786 \times 10^3\ \text{mm}^3, \qquad Z_{\text{beam}} \geq \frac{843.75 \times 10^6}{0.9 \times 350} = 2679 \times 10^3\ \text{mm}^3$$
Select the beam BC. Try a welded I with flanges $240 \times 16$ and web $560 \times 10$, so $d = 592$ mm and $A = 13\,280$ mm². Its plastic modulus is
$$Z = b t (d - t) + \frac{w h^2}{4} = 240(16)(576) + \frac{10(560)^2}{4} = 2\,211\,840 + 784\,000 = 2996 \times 10^3\ \text{mm}^3$$
$$\boxed{M_r = 0.9 (2996\times10^3)(350) = 944\ \text{kN}\cdot\text{m} \;\geq\; 843.75\ \text{kN}\cdot\text{m}}$$
Class 1 is satisfied: flange $b/t = 7.2 \le 145/\sqrt{F_y} = 7.75$ and web $h/w = 56.0 \le 1100/\sqrt{F_y} = 58.8$.
Select the column CD. Flanges $250 \times 16$, web $370 \times 10$, $d = 402$ mm, $A = 11\,700$ mm²:
$$Z = 250(16)(386) + \frac{10(370)^2}{4} = 1\,544\,000 + 342\,250 = 1886 \times 10^3\ \text{mm}^3$$
$$\boxed{M_r = 0.9(1886\times10^3)(350) = 594\ \text{kN}\cdot\text{m} \;\geq\; 562.5\ \text{kN}\cdot\text{m}}$$
with $b/t = 7.5$ and $h/w = 37.0$, again Class 1. Question 2 revisits this member once the 937.5 kN of axial load is admitted.
Bracing required by the plastic method. The paper's note about lateral support at joints and load points is not enough. CSA S16 Cl. 13.7 limits the unbraced length beside a hinge to $L_{cr} = (25\,000 + 15\,000\kappa)r_y/F_y$; with $\kappa = 0$, $r_y = 52.7$ mm for the beam and 59.7 mm for the column,
$$L_{cr,\text{beam}} = \frac{25\,000 (52.7)}{350} = 3766\ \text{mm}, \qquad L_{cr,\text{col}} = \frac{25\,000(59.7)}{350} = 4264\ \text{mm}$$
so the beam must be braced at its quarter points (3.75 m) and each column at mid-height (4.0 m). State this as part of the design; without it the assumed mechanism cannot form.
Part (b) — forces the knee at C must carry. The connection transmits the hinge moment $M_p = 562.5$ kN·m together with the beam end shear $V = W/2 = 187.5$ kN. Taking the moment as a flange couple over the beam depth less one flange,
$$T = \frac{M_p}{d - t} = \frac{562.5\times10^6}{592 - 16} = 977\ \text{kN}$$
Flange welds. Use complete-joint-penetration groove welds with matching E49XX electrode, so the joint develops the flange itself:
$$T_r = \phi A_f F_y = 0.9 (240 \times 16)(350) = 1210\ \text{kN} \;\geq\; 977\ \text{kN}$$
A CJP weld of matching electrode needs no separate weld-metal calculation — it is the base metal that governs, which is exactly what plastic design requires.
Web welds. The flange couple already carries the whole moment, so two fillet welds along the 560 mm web need only take the shear. For a 6 mm fillet (the CSA S16 Table 3 minimum against 16 mm plate), with $X_u = 490$ MPa, $\phi_w = 0.67$ and $\theta = 0$,
$$V_r = 0.67\phi_w A_w X_u = 0.67(0.67)(0.707 \times 6 \times 2 \times 560)(490) = 1045\ \text{kN} \gg 187.5\ \text{kN}$$
$$\boxed{\text{6 mm fillet welds, both sides of the web, full depth}}$$
Panel-zone shear — the check that actually bites. The knee panel must carry $T$ less the column shear, $916.6$ kN. The Question 1 column web offers
$$V_r = \phi (0.66F_y) w d_c = 0.9(0.66 \times 350)(10)(402) = 836\ \text{kN} \;<\; 917\ \text{kN}$$
so a diagonal stiffener is needed. Across a panel $402 \times 592$ mm the diagonal is 715.6 mm long and inclined so that $\cos\theta = 402/715.6 = 0.562$; the shortfall of 80.8 kN requires a diagonal force of $80.8/0.562 = 143.8$ kN, i.e. an area of $143.8\times10^3/(0.9 \times 350) = 456$ mm².
$$\boxed{\text{diagonal stiffener: pair of } 10 \times 90\ \text{mm plates} = 1800\ \text{mm}^2}$$
With the heavier column adopted in Question 2 ($w = 12$ mm, $d_c = 440$ mm) the panel resistance rises to 1098 kN and the diagonal is no longer needed — a good reason to settle the beam-column check first.
Continuity stiffeners. The 977 kN flange force delivered into the column web would yield it locally, since $B_r = \phi_{bi} w (N + 10t)F_y = 0.80(10)(16 + 160)(350) = 493$ kN. A pair of $100 \times 12$ mm stiffeners in line with each beam flange adds $0.9(2400)(350) = 756$ kN, giving $756 + 493 = 1249$ kN ≥ 977 kN.
Welded knee at C: complete-joint-penetration groove welds develop both beam flanges, fillet welds carry the web shear, and a diagonal stiffener makes up the panel-zone shortfall in the Question 1 column.
Quantity
Result
Governing mechanism
beam mechanism (hinges at B, mid-span, C)
Required $M_p$ (columns)
562.5 kN·m
Required $1.5M_p$ (beam)
843.75 kN·m
Member BC
welded I, flanges $240 \times 16$, web $560 \times 10$, $d = 592$ mm; $M_r = 944$ kN·m
Member CD
welded I, flanges $250 \times 16$, web $370 \times 10$, $d = 402$ mm; $M_r = 594$ kN·m
Bracing
beam at 3.75 m centres, columns at mid-height (Cl. 13.7)
Connection at C
CJP flange groove welds; 6 mm web fillets; $2/100 \times 12$ continuity stiffeners; $2/10 \times 90$ diagonal