07-Str-B1 · May 2013
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Examinations — May 2013 — 07-Str-B1 Geotechnical Design. Three-hour, OPEN-BOOK exam; any non-communicating calculator permitted (the candidate must record its make and model). Format: Section A carries five short-answer questions of 7 marks each, of which any FOUR are to be answered; Section B carries the long design questions at 24 marks each, of which any THREE are to be answered. The paper instructs candidates to state any interpretive assumptions and to identify the source of every design chart or assumed value used. Every question in both sections is worked below, because the set is intended as a study resource.
Reference texts: Das, B.M., Principles of Foundation Engineering (9th ed., Cengage) — shallow foundations, consolidation settlement, sheet-pile walls, retaining walls and drilled shafts; Das, B.M., Principles of Geotechnical Engineering (9th ed., Cengage) — method of slices, lateral earth pressure, consolidation theory; Canadian Geotechnical Society, Canadian Foundation Engineering Manual (CFEM, 4th ed., 2006) — Canadian practice for SPT interpretation, pile design, limit-states design and tolerable settlement; Craig, R.F. / Knappett, J.A., Craig's Soil Mechanics (8th ed., CRC Press) — effective stress, shear strength and slope stability; Duncan, J.M., Wright, S.G. & Brandon, T.L., Soil Strength and Slope Stability (2nd ed., Wiley) — choice of strength parameters and factors of safety for short- and long-term analyses.
NOTE 1 — question numbering in the source. The printed paper labels the retaining-wall problem (Figure 4) and the drilled-pier problem (Figure 5) both as "Question 9", while the Section B heading reads "answer any THREE of the following FOUR questions". Section B therefore contains five printed problems under four numbers. They are set out below as Question 9 (retaining wall) and Question 10 (drilled pier) in printed order, so that each can be referred to unambiguously; the marks shown are those printed against each problem.
NOTE 2 — dimensions scaled from Figure 1. Figure 1 is a hand-drawn slope on a 1 m × 1 m grid with no written dimensions other than $R=10$ m. The geometry used in Question 6 was scaled from that grid: slope height 7 m over a 9 m horizontal run, a 3 m thick lower layer, and the centre of the trial circle 1.4 m horizontally beyond the toe and 8.0 m above it. Every one of these values reproduces the drawing to within about 0.2 m (one fifth of a grid square). Check against the original if the paper is used for marking rather than study.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. A belled drilled pier cast through a silty clay layer with its bell founded in sand.
| Quantity | Symbol | Value |
|---|---|---|
| Thickness of the silty clay layer | $L_1$ | 5.0 m |
| Penetration into the sand | $L_2$ | 2.5 m |
| Shaft diameter | $D_s$ | 1.00 m |
| Bell (base) diameter | $D_b$ | 1.8 m |
| Unit weight of the silty clay | $\gamma_c$ | 20 kN/m³ |
| Undrained shear strength of the silty clay | $c_u$ | 30 kN/m² |
| Unit weight of the sand | $\gamma_s$ | 19 kN/m³ |
| Friction angle of the sand (not to be reduced) | $\phi'$ | 37.5° |
| Factor of safety on point bearing | $FS$ | 4 |
| Groundwater | — | Not shown on the figure; total stresses taken as effective |
Find. (a) the net allowable point bearing capacity of the bell with $FS=4$; (b) the skin resistance developed over the top 5 m of shaft in the silty clay; (c) the advantages and disadvantages of drilled piers; (d) an alternative foundation for a heavy structure on this profile.
[Figure not reproduced: Figure 5 (redrawn) — belled drilled pier: 1.00 m shaft through 5.0 m of silty clay, 1.8 m bell bearing 2.5 m into the sand. See the official exam paper.]
Approach. The bell bears in sand, so the point resistance is a deep bearing-capacity problem in a $c'=0$ material driven by the effective overburden at the base and the deep bearing-capacity factor $N_q$; the net capacity subtracts the overburden that was there before the pier was built. The shaft resistance in the clay is a total-stress problem and is taken by the $\alpha$ method with the adhesion factor recommended for drilled shafts.
Advantages. A single drilled pier commonly replaces a group of driven piles together with its pile cap, which removes both the cap and the group-efficiency reduction, and it can be positioned exactly under a column. The excavation can be inspected — visually, by downhole camera, or by a shaft inspection device — so the founding stratum is confirmed rather than inferred, and the length can be adjusted on site to reach it. Very large capacities are available: a belled pier of the kind analysed here offers thousands of kilonewtons, and rock-socketed shafts far more. Construction generates neither the vibration nor the noise of driving, which matters beside existing structures, in urban settings, and in sensitive clays where driving would remould the soil. There is no heave of the surrounding ground or of adjacent piles, no risk of splicing or of damage during driving, and the reinforcement can be tailored for uplift or for lateral load. A bell can be formed in cohesive soil to multiply the base area — as here, where a 1.8 m bell on a 1.0 m shaft triples the bearing area for a modest increase in excavation.
Disadvantages. Quality depends entirely on workmanship, and the critical surfaces are the ones nobody can see once concrete is placed. Base cleanliness is the recurring problem: loose spoil or slurry left at the bottom produces a soft toe that destroys the very point resistance the design relies on. Caving soils and water-bearing granular strata require temporary casing or a slurry, and slurry left too long forms a filter cake that reduces shaft friction; withdrawing casing carelessly can neck the shaft. Boring relieves lateral stress in the surrounding soil, so shaft friction is systematically lower than for a displacement pile of the same size. Belling cannot be done at all in cohesionless soil, which will not stand unsupported, or below the water table without dewatering — the bell in this problem is formed in sand and is therefore an idealisation to be questioned on the answer paper. Concrete placement under water or slurry must be by tremie and demands care to avoid segregation or inclusions. Spoil disposal is an issue on contaminated sites, and the whole operation is weather-sensitive and generally more expensive per pier than driven piling where driving is feasible. Finally, integrity testing after the fact — low-strain sonic echo or cross-hole sonic logging — is a check rather than a cure, and remediating a defective shaft is expensive.
Check — the bell in sand, and the source of $N_q$. Two points that a marker would expect to be raised. First, Figure 5 shows the bell formed in the sand layer, but an underream will not stand unsupported in a cohesionless soil; in practice the bell would be formed in the silty clay above, or the pier would be built as a straight shaft, or the base would be enlarged by grouting. Second, the paper's own Note 6 requires the source of every design chart to be identified: the value $N_q=45.8$ used above is the Reissner–Prandtl–Vesic factor computed from the closed-form expression, stated so that it can be checked. Chart values for drilled shafts published by Berezantzev or by Chen and Kulhawy run higher for the same $\phi'$, and would raise $Q_{p(\text{all})}$ in proportion; the calculation should always be reported with the factor and its source together. In any event a capacity of this magnitude would in practice be governed by settlement at the base rather than by bearing failure, and a static load test would be the proper way to confirm it.
The profile is 5 m of soft to firm silty clay ($c_u=30$ kPa) over a dense sand ($\phi'=37.5^\circ$), which is a classic case for transferring load through the weak stratum to the competent one. The natural alternative is a driven pile group with a pile cap — precast concrete or closed-ended steel pipe piles driven 3 to 5 m into the sand. Driving is a displacement process, so it densifies the sand around and beneath the toe and generates far higher shaft resistance in it than boring does; installation is fast, capacity can be verified pile by pile from driving records and dynamic testing, and the sand offers exactly the material in which driving criteria are most reliable. The competing considerations are vibration and noise near existing structures, and the fact that the piles must be designed for downdrag if the silty clay is likely to consolidate under fill.
Other defensible answers, with their conditions: a piled raft, if the structure is a large heavy building — the raft spreads part of the load and the piles control differential settlement, which is usually the governing criterion; a mat (raft) foundation with partial compensation, if the structure has a basement, since excavating 5 m of clay at 20 kN/m³ removes 100 kPa of net pressure and can make the foundation nearly fully compensated; ground improvement — stone columns, deep soil mixing or preloading with wick drains through the silty clay — followed by a conventional raft, where the loads are moderate and programme allows the time; or a group of the drilled piers analysed here, retained on its own merits where vibration must be avoided. A spread footing bearing directly on the silty clay is not a candidate: with $c_u=30$ kPa the net ultimate bearing capacity is only about $5.14(30)\approx154$ kPa, and the consolidation settlement of a heavy structure on 5 m of that clay would be unacceptable long before that pressure was reached.
| Quantity | Value |
|---|---|
| Base area of the bell | $A_p=2.545$ m² |
| Effective vertical stress at the base (7.5 m) | $q'=147.5$ kPa |
| Bearing-capacity factor (Reissner–Vesic, $\phi'=37.5^\circ$) | $N_q=45.8$ |
| Net ultimate point resistance | 16 820 kN |
| (a) Net allowable point bearing capacity ($FS=4$) | $\boxed{Q_{p(\text{all})}\approx4200\ \text{kN}}$ |
| Shaft perimeter and adhesion factor | $p=3.142$ m, $\alpha^{*}=0.4$ |
| (b) Skin resistance over the top 5 m | $\boxed{Q_s=188.5\ \text{kN}}$ |
| (c) Drilled piers | Inspectable, no vibration, high capacity, belling possible; but workmanship-sensitive, soft-toe and caving risk, reduced shaft friction, no belling in sand |
| (d) Alternative foundation | Driven pile group into the dense sand, or a piled raft; a compensated raft if a basement is provided |