07-Str-B1 · Undated paper
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Examinations — May 2019 — 07-Str-B1 Geotechnical Design. Three-hour, OPEN-BOOK exam; any calculator is permitted provided the candidate records its make and model. Format: Section A carries five discussion questions of 7 marks each, of which the candidate answers any four; Section B carries four problems of 24 marks each, of which the candidate answers any three (4 × 7 + 3 × 24 = 100 marks). Every question is worked here, because the set is a study resource rather than a marked script.
Reference texts: Das, B.M., Principles of Foundation Engineering (9th ed., Cengage) — SPT-based allowable bearing pressure, Terzaghi bearing capacity, drilled-shaft capacity, retaining walls, sheet-pile walls; Das, B.M., Principles of Geotechnical Engineering (9th ed., Cengage) — effective stress, shear strength, lateral earth pressure; Canadian Geotechnical Society, Canadian Foundation Engineering Manual (CFEM, 4th ed., 2006) — Canadian practice for site investigation, SPT and CPT interpretation, tolerable settlement, raft and deep foundations; Craig, R.F. / Knappett, J.A., Craig's Soil Mechanics (8th ed., CRC Press) — undrained strength, slope stability, anchored sheet-pile design; Reese, L.C. and O'Neill, M.W., Drilled Shafts: Construction Procedures and Design Methods (FHWA) — the alpha method for shafts in clay.
Assumptions declared once, applied throughout. Unit weight of water $\gamma_w = 9.81\ \text{kN/m}^3$; atmospheric reference pressure $p_a = 101.3\ \text{kPa}$; the SPT blow counts quoted in Question 6 are already corrected to $N_{60}$, as the paper states, so no further energy or overburden correction is applied. All wall and sheet-pile results are per metre run of wall. Where the paper says "make suitable assumptions providing justification", the assumption is stated in a highlighted note beside the step that uses it, in the form the exam rubric asks for.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Figure 2 shows a belled (under-reamed) drilled shaft, not a driven pile. Read from the drawing: shaft diameter $D_s = 1.0\ \text{m}$; upper clay layer from the surface to 8.0 m with $c_u = 40\ \text{kPa}$; lower clay layer below 8.0 m with $c_u = 60\ \text{kPa}$; the shaft is embedded a further 4.0 m into the lower layer, so the base sits at $L = 12.0\ \text{m}$; the bell is 1.0 m high with a base diameter $D_b = 2.0\ \text{m}$, giving a splay of one vertical to half a horizontal. A pile cap sits 0.5 m proud of the ground. Factor of safety $FS = 3$.
Find. The ultimate axial compressive capacity $Q_u = Q_p + Q_s$ and the design (allowable) capacity $Q_{all} = Q_u/3$.
[Figure not reproduced: Question 7 (redrawn from Figure 2): the belled shaft, the two clay layers, and the two lengths over which side resistance is discounted. The green band is the only part of the shaft credited with skin friction. See the official exam paper.]
Approach. Use the total-stress (alpha) method for a drilled shaft in clay: the base resistance from the bearing-capacity factor $N_c^* = 9$ applied to the undrained strength at base level over the full bell area, and the side resistance from $\alpha^* c_u$ applied to the straight shaft only, with the Reese and O'Neill exclusion zones removed.
Check: assumes a bored shaft constructed dry or under a temporary casing in a stiff-to-firm clay, so that the standard exclusion zones and the standard adhesion factor apply. If the hole were drilled under bentonite, a further reduction of the order of 20 per cent on the side resistance would be appropriate.
Comment on the result. Three observations belong with the number. The bell is what makes this shaft: a straight 1.0 m shaft to the same depth would develop a base resistance of only $(\pi/4)(1.0)^2(9)(60) = 424\ \text{kN}$, so the under-ream quadruples the base contribution for one extra metre of excavation. Against that, a bell can only be formed in a clay that will stand unsupported for the time the under-reaming tool is at work, it cannot be formed under bentonite, and it cannot be inspected without entering the shaft; the specification must therefore require the base to be cleaned and proved, because debris left at the base is the classic cause of an under-performing belled shaft. Finally, because the design capacity is base-dominated but the working behaviour is friction-dominated, a serviceability check — either an elastic settlement calculation or, better, a static load test on a trial shaft — should accompany the capacity calculation rather than be inferred from the factor of safety of 3.
| Quantity | Value |
|---|---|
| Base area of the bell, $A_p$ | 3.1416 m2 |
| Contributing shaft length, upper clay ($c_u = 40$ kPa) | 6.5 m (1.5 to 8.0 m) |
| Contributing shaft length, lower clay ($c_u = 60$ kPa) | 2.0 m (8.0 to 10.0 m) |
| Adhesion factor $\alpha^*$ | 0.55 |
| Side resistance $Q_s$ | 656.6 kN |
| Base resistance $Q_p$ ($N_c^* = 9$) | 1696.5 kN |
| Ultimate axial capacity $Q_u$ | 2353.1 kN |
| Design axial capacity, $FS = 3$ | 784.4 kN |
| Proportion of $Q_u$ carried by the bell | 72 per cent |