07-Str-B2 · May 2018
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format: National Exams, May 2018 — 07-Str-B2 Management of Construction. Three hours, closed book, one approved Casio or Sharp calculator permitted. Six questions of equal value (20 marks each); any five constitute a complete paper and only the first five that appear in the answer book are marked. All six are worked below so the paper serves as a complete revision set whichever five a candidate elects.
Reference texts: Hegazy, T., Computer-Based Construction Project Management (Prentice Hall) — precedence (activity-on-node) networks with start-to-start lags, forward and backward passes, total and free float, the late bar chart, and contractor cash-flow and overdraft analysis; these chapters carry Questions 1 and 5. Hendrickson, C. & Au, T., Project Management for Construction (2nd ed., Carnegie Mellon) — Chapter 5 (cost estimation and unit-cost data), Chapter 8 (bidding and contract award), Chapter 10 (fundamental scheduling procedures), Chapter 11 (advanced scheduling with lags) and Chapter 12 (cost control and financing of constructed facilities). Halpin, D.W. & Senior, B.A., Construction Management (4th ed., Wiley) — quantity take-off, crew productivity, bidding strategy, bonding and construction safety management. Peurifoy, R.L. & Schexnayder, C.J., Construction Planning, Equipment and Methods (9th ed., McGraw-Hill) — excavation production and the physical determinants of backhoe daily output, behind Question 2. R.S. Means, Building Construction Cost Data (annual) — the anatomy of a unit-price line: crew, daily output, unit, and bare material / labour / equipment / total columns. Sullivan, W.G., Wicks, E.M. & Koelling, C.P., Engineering Economy (17th ed., Pearson) — Chapters 5 and 6, present-worth analysis and the repeatability (least common multiple of lives) assumption for alternatives with unequal lives, used in Question 4. Canadian Construction Documents Committee, CCDC 2 — Stipulated Price Contract (2020), CCDC 220 Bid Bond, CCDC 221 Performance Bond and CCDC 222 Labour and Material Payment Bond, with the BC Builders Lien Act holdback provisions and the Master Municipal Construction Documents (MMCD) — the Canadian tendering and payment machinery behind Questions 3 and 5. WorkSafeBC Occupational Health and Safety Regulation (Parts 8, 11, 12, 13, 18 and 33), CSA Z259 fall-protection and CSA Z94.4 respirator series, and the Transportation Association of Canada Manual of Uniform Traffic Control Devices for Canada — the Canadian rule set behind Question 6.
Check — how the two printed figures on page 2 were read. Network (Question 1): nine activity boxes with seven links — A → D carrying the printed SS = 3 lag (the line leaves A's top-left corner, runs across the top of the sheet and drops into D's top-left corner), then D → H, B → E, B → F, C → G, F → I and G → I, all finish-to-start with zero lag. No further arrows are drawn; A, B and C are the only start activities and E, H and I the only finish activities. Foundation plan (Question 2): an 80 m × 70 m rectangle with a rectangular notch 25 m deep cut into the top edge, one internal trench running the full width 20 m up from the bottom (the 50 m and 20 m dimensions meet on it), and one internal trench dropping from the bottom of the notch to that line. The notch width is not dimensioned on the paper, and Step 1 below shows the total trench length does not depend on it, so nothing is assumed. All plan dimensions are taken as trench centrelines; reading them instead to the outside face of the trench would shorten the total by about 1.6 per cent and change no conclusion.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. The foundation plan, the footing cross-section and the production data reproduced above; work proceeds eight hours per day.
| Item | Value |
|---|---|
| Overall plan dimensions | 80 m wide × 70 m deep (50 m + 20 m) |
| Notch in the top edge | 25 m deep, width not dimensioned |
| Internal trenches | one full-width run 20 m up from the bottom; one run from the notch bottom down to it |
| Footing width | 750 mm |
| Trench width | 300 + 750 + 300 = 1350 mm (300 mm working space each side of the footing) |
| Footing thickness | 450 mm |
| Top of footing below ground level | 600 mm |
| Wall thickness | 200 mm (excluded from this estimate) |
| Excavation output, 0.29 m3 backhoe | 115 m3/day at $4.76/m3 bare |
| Formwork output, two uses | 40.88 m2/day at $25.37/m2 bare |
| Concrete placing rate | 5 m3/h, 8 h/day |
| Concreting cost (material included) | $20,000 |
Find. For each of excavation, formwork and concrete: the take-off quantity in its own unit, the duration in working days at the stated production rate, and the bare cost.
[Figure not reproduced: Foundation plan re-drawn from the paper. The trench runs on every wall line: the full outline including the two 25 m sides of the notch, one internal run across the full width 20 m up from the bottom, and one internal run from the notch bottom down to it. The notch width is not dimensioned on the pa. See the official exam paper.]
Approach. Every quantity on this job is the trench centreline length multiplied by a cross-sectional property, so measure the length once from the plan, take the depth, width and form height off the section, then divide each quantity by its daily output for duration and multiply by its bare unit rate for cost.
Check — the estimating assumptions behind these numbers. Excavation is priced to the printed 1350 mm trench width, which already carries 300 mm of working space either side of the 750 mm footing, with vertical sides and no side slopes or bulking allowance, because the R.S. Means line quoted is a bank-measure trench line; a real bid would add bulking for haul-off, and at 1.05 m the trench is below the depth at which BC's OHSR Part 20 requires shoring or sloping, so no shoring is priced. Formwork is the two vertical faces of the footing only, with no allowance for stop-ends or waste. Plan dimensions are read as trench centrelines. Trench intersections are not deducted; the four T-junctions involved are worth under 4 m3 of double-counted excavation, well inside estimating tolerance. These are bare costs as the question asks — no overhead, profit, bond or escalation is included.
| Task | Quantity | Production rate | Duration | Bare cost |
|---|---|---|---|---|
| Trench excavation (0.29 m3 backhoe) | 645.0 m3 | 115 m3/day | 5.61 days → 6 days | $3,070 |
| Footing formwork (2 uses) | 409.5 m2 | 40.88 m2/day | 10.02 days → 10 days | $10,389 |
| Concreting the footings | 153.6 m3 | 40 m3/day | 3.84 days → 4 days | $20,000 (given) |
| Trench centreline length used throughout | 455 m | — | — | — |
| Total | — | — | 19.5 days if sequential | $33,459 |