NivaarExam PrepOfficial exam papers ↗

07-Str-B5 · December 2015

Question 2 of 6: Deep Foundations: helical pile group

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format: National Exams, December 2015 — 07-Str-B5 Foundation Engineering. Three hours, open book, any non-communicating calculator permitted. Six questions of equal value (30 marks each); five constitute a complete paper and only the first five in the answer book are marked. All six are solved here. This subject is pure geotechnical engineering.

Reference texts (the books an open-book candidate should have on the desk for this subject):

Check — assumptions adopted across this paper. The examination omits several parameters that a foundation designer must have; each is adopted explicitly here and flagged again where it is used. (1) Question 2 and Question 5 give bulk unit weights but no groundwater table — effective stresses are computed with the quoted unit weights acting as effective weights (i.e. no free water in the profile); if instead the water table stood at ground level the effective stresses roughly halve and the computed consolidation settlements roughly double, and that sensitivity is reported. (2) Question 2 gives no allowable settlement — 50 mm total is adopted, the upper end of the CFEM 4th ed. range for framed structures. (3) Question 4 gives only the submerged unit weight of the foundation sand; the moist unit weight above the water table is taken as 20.0 kN/m3, consistent with the quoted $\gamma^{\prime} = 10.2$ kN/m3. (4) Concrete unit weight is taken as 24 kN/m3 throughout. (5) Where a question states only a factor of safety, the gross definition is used for shallow foundations sized on total load and the net definition where the question separates net pressure, and the convention used is stated in each answer.

Question 2 — Deep Foundations: helical pile group (30 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Twenty-five helical piles, each 18 m long with a 305 mm shaft and two 610 mm helices at 1.22 m spacing, are installed in a uniform slightly overconsolidated clay and capped by a 6 m square cap founded 1 m below ground.

Given data — Question 2
QuantitySymbolValue
Undrained shear strength of the claycu50 kPa
Bulk unit weight, undrained modulus, Poisson ratioγ, Eu, νu20 kN/m3, 50 MPa, 0.5
Compression index, initial void ratioCc, e00.25, 1.20
Shaft diameter, wall thickness, pile lengthd, t, L305 mm, 12.7 mm, 18 m
Helix diameter, number, inter-helix spacingDh, nh, Sh610 mm, 2, 1.22 m
Pile group, spacing, capN, s25 (5 by 5) at 1.2 m, cap 6 m square at 1 m depth
Adhesion factorα0.8
Very dense sand (rigid boundary)—34 m below ground surface

Find. Single-pile ultimate capacity by static analysis in undrained conditions; ultimate group capacity; the factor of safety under a 10 MN centric load with a design comment; and the total settlement by the equivalent-raft method.

ground surface very dense sand, 34 m pile cap 6 m x 6 m at 1 m depth upper helix (16.78 m) lower helix (18 m), 610 mm shaft adhesion 15.78 m equivalent raft at 12.33 m, 5.41 m square 2:1 spread through 21.7 m of clay Cc = 0.25, e0 = 1.20, cu = 50 kPa Section (piles shown schematically; 5 rows of 5 at 1.2 m centres)
Figure 2.1 — Helical pile group: shaft adhesion above the upper helix, a cylindrical shear zone between the two helices, bearing on the lower helix, and the equivalent raft used for the settlement check.

Approach. Because the two helices are spaced at only two helix diameters, the soil between them acts as a plug, so the single-pile capacity follows the cylindrical shear model: end bearing on the lower helix, soil-on-soil shear on the cylinder joining the helices, and $\alpha c_u$ adhesion on the shaft above the upper helix. The group capacity is the lesser of the sum of the single-pile capacities and block failure of the group. Settlement follows from an equivalent raft at two-thirds of the embedded length with a 2:1 stress spread beneath it.

  1. Part (a) — choose the helical-pile capacity model. The controlling ratio is the inter-helix spacing divided by the helix diameter: $$\frac{S_h}{D_h} = \frac{1.22}{0.610} = 2.0 \ < \ 3$$ Below about three, the individual bearing surfaces interfere and the soil between the helices fails as a cylinder rather than each helix punching separately. The cylindrical shear method therefore applies, and the pile is idealised as a 610 mm diameter soil cylinder 1.22 m long, capped by the lower helix and connected to the ground surface by the 305 mm shaft.
  2. Part (a) — end bearing on the lower helix. The lower helix bears at 18 m, far deeper than five diameters, so the deep-foundation factor $N_c^{*} = 9$ applies: $$A_h = \frac{\pi}{4}D_h^{2} = \frac{\pi}{4}(0.610)^{2} = 0.29225\ \text{m}^{2}$$ $$Q_b = A_h\,N_c^{*}c_u = 0.29225 \times 9 \times 50 = 131.5\ \text{kN}$$ This is a net capacity, so the buoyant weight of the pile is not deducted separately.
  3. Part (a) — shear on the cylinder between the helices. The failure surface here is soil against soil, so the full undrained strength acts, not the reduced adhesion: $$Q_{cyl} = \pi D_h S_h c_u = \pi \times 0.610 \times 1.22 \times 50 = 116.9\ \text{kN}$$
  4. Part (a) — adhesion on the shaft above the upper helix. The shaft is a steel-to-clay interface, so the adhesion factor $\alpha = 0.8$ applies. The upper helix sits at $18 - 1.22 = 16.78$ m and the cap underside is at 1 m, so the effective shaft length is 15.78 m: $$Q_s = \pi d L_s \alpha c_u = \pi \times 0.305 \times 15.78 \times 0.8 \times 50 = 604.8\ \text{kN}$$
  5. Part (a) — single-pile ultimate capacity. Adding the three contributions, $$\boxed{Q_u = Q_b + Q_{cyl} + Q_s = 131.5 + 116.9 + 604.8 = 853.2\ \text{kN}}$$ Shaft adhesion supplies 71 per cent of the total, which is characteristic of a slender helical pile in uniform clay: the helices contribute usefully but the pile is fundamentally a friction pile.
  6. Part (b) — block failure of the group. A 5 by 5 group at 1.2 m centres spans $4 \times 1.2 = 4.8$ m between outer pile axes; taking the block boundary at the outer edge of the helices gives $$B_g = L_g = 4.8 + D_h = 4.8 + 0.61 = 5.41\ \text{m}$$ The block extends from the cap underside at 1 m to the pile toes at 18 m, so $L_b = 17$ m. Its capacity is perimeter shear at full $c_u$ plus base bearing: $$Q_{blk} = 2(B_g+L_g)L_b c_u + B_gL_g\,N_c^{*}c_u = 18\,394 + 13\,171 = 31\,565\ \text{kN}$$
  7. Part (b) — group capacity. The sum of the individual capacities is $25 \times 853.2 = 21\,330$ kN, which is less than the block value, so individual pile failure governs: $$\boxed{Q_{g(u)} = \min(21\,330,\ 31\,565) = 21\,330\ \text{kN} \quad (\eta = 1.0)}$$ Physically the block is stronger because its 21.6 m perimeter mobilises the full $c_u$ whereas 25 individual shafts mobilise only $0.8c_u$ over 24.0 m, and the block base is 29.3 m2 against 7.3 m2 of helices.
  8. Part (c) — factor of safety under the 10 MN load. Treating the 10 MN as an unfactored working load, $$\boxed{F = \frac{Q_{g(u)}}{Q} = \frac{21\,330}{10\,000} = 2.13}$$
  9. Part (c) — comment on the design. Three observations follow. First, 2.13 falls short of the 2.5 to 3.0 normally required on a pile group designed by static analysis from soil strengths alone, with no load test; the group is under-designed at the ULS. Second, the pile spacing of 1.2 m is only two helix diameters, whereas CFEM and helical-pile practice call for at least three helix diameters (1.83 m here) so that the cylindrical shear zones of neighbouring piles do not overlap. If a Converse-Labarre efficiency is applied on the helix diameter, $\eta = 0.52$ and the group capacity falls to about 11 100 kN, i.e. $F \approx 1.11$ — a spread of results that by itself shows the spacing is too tight to be confident in. Third, the piles stop 16 m above the very dense sand at 34 m, so they are floating piles carrying their load entirely in a compressible clay; part (d) shows this is what actually condemns the design.
  10. Part (d) — locate the equivalent raft. For friction piles in a uniform clay the load is treated as applied at two-thirds of the embedded length, over the plan area of the group: $$z_{raft} = 1.0 + \tfrac{2}{3}(17) = 12.33\ \text{m},\qquad 5.41 \times 5.41\ \text{m}$$ The pressure on that raft is $q_r = 10\,000/5.41^{2} = 341.7$ kPa.
  11. Part (d) — consolidation settlement below the raft. The compressible clay runs from 12.33 m to the dense sand at 34 m, a thickness of 21.67 m, with $C_c/(1+e_0) = 0.25/2.20 = 0.1136$. Spreading the load at 2:1 below the raft gives, at depth $z$ below it, $$\Delta\sigma = \frac{Q}{(B_g+z)(L_g+z)},\qquad \sigma^{\prime}_{v0} = 20\,z_{abs}$$ Summing $s_c = \sum [C_c/(1+e_0)]\Delta z\log_{10}[(\sigma^{\prime}_{v0}+\Delta\sigma)/\sigma^{\prime}_{v0}]$ over 0.36 m sublayers gives $s_c = 178$ mm, three quarters of it in the first 4 m below the raft where $\Delta\sigma$ is still of the order of 200 kPa.
  12. Part (d) — immediate settlement and the verdict. Treating the equivalent raft as rigid on an elastic layer with $E_u = 50$ MPa, $\nu_u = 0.5$ and $I_p = 0.82$ gives $s_i = 341.7 \times 5.41 \times 0.75 \times 0.82/50\,000 = 0.023$ m, so $$\boxed{s_{tot} = 23 + 178 = 200\ \text{mm}}$$ Against the 50 mm total settlement adopted here (CFEM's upper bound for a framed structure), the serviceability limit state is not satisfied, and by a factor of four. The remedy is not more piles of the same length: extending the piles 16 m to end-bear in the very dense sand at 34 m would transfer the load below the compressible clay and reduce the settlement to elastic shortening plus a few millimetres of toe movement. Widening the cap and increasing the spacing to three helix diameters would also spread the equivalent raft and lower $q_r$, but the floating-pile geometry remains the fundamental problem.
Check — assumptions in Question 2. (1) No groundwater table is given. Effective stresses are computed with the quoted bulk unit weight acting as an effective weight, $\sigma^{\prime}_{v0} = 20z$. If the water table stood at ground surface, $\sigma^{\prime}_{v0} = 10.19z$ and the consolidation settlement would rise from 178 mm to 305 mm, so the conclusion (SLS badly violated) is unchanged and in fact strengthened. (2) No allowable settlement is given; 50 mm total is adopted, the upper end of the CFEM range for framed structures. (3) The clay is "slightly over-consolidated" but no preconsolidation pressure or recompression index is supplied, so the full $C_c$ is used throughout, which is conservative. (4) The equivalent raft is placed at $2L/3$ with the group plan dimensions and a 2:1 spread below it, following Das and Tomlinson; the variant that spreads at 1:4 from the cap down to the raft would give a wider raft and a smaller settlement, so this answer is on the safe side.
Final results — Question 2
QuantityResult
Model selected (Sh/Dh = 2.0 < 3)cylindrical shear
(a) End bearing on lower helix131.5 kN
(a) Cylindrical shear between helices116.9 kN
(a) Shaft adhesion over 15.78 m604.8 kN
(a) Single-pile ultimate capacity853 kN
(b) Sum of 25 single piles21 330 kN
(b) Block failure capacity (5.41 m square, 17 m deep)31 565 kN
(b) Ultimate group capacity21 330 kN
(c) Factor of safety at 10 MN2.13 (below the usual 2.5 to 3.0)
(d) Equivalent raft5.41 m square at 12.33 m, q = 342 kPa
(d) Immediate and consolidation settlement23 mm + 178 mm = 200 mm
(d) Serviceability verdictnot satisfied against a 50 mm criterion