NivaarExam PrepOfficial exam papers ↗

23-Chem-B10 Life Cycle Assessment (LCA) · May 2017

Question 2 of 5: Heat Integration – Pinch Analysis & Heat Exchanger Network

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exam 16-Chem-B10, Life Cycle Assessment (LCA) — May 2017. 3 hours, Closed-Book Exam (approved calculator and one double-sided aid sheet permitted). Question 1 is mandatory (28 marks); any three (3) of the remaining four (Questions 2–5) constitute a complete 100-mark paper, and only the first four questions as they appear in the answer book are marked. All five questions are solved below for completeness.

Reference texts: Baumann & Tillman, The Hitch Hiker's Guide to LCA; Graedel & Allenby, Industrial Ecology and Sustainable Engineering; Kemp, Pinch Analysis and Process Integration, 2nd ed.; Mackay, Multimedia Environmental Models: The Fugacity Approach, 2nd ed.; Davis & Cornwell, Introduction to Environmental Engineering.

Question 2: Heat Integration – Pinch Analysis & Heat Exchanger Network (24 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

StreamTypeẓ (kg/s)Cp (kJ/kg·°C)CP (kW/°C)Tin→Tout
H101hot12.02.0024.0195→50°C
C102cold10.04.0040.0100→160°C
C103cold8.02.5020.050→130°C

ΔTmin = 10°C. Utilities: LPS (≈160°C condensing, 2000 kJ/kg), HPS (≈250°C condensing, 1700 kJ/kg), CW (30→45°C, 63 kJ/kg sensible).

Find. (a) Utility type and flow rate per stream with no integration. (b) Pinch temperature and minimum hot/cold utility duties via the problem-table (temperature-interval) method. (c) A feasible heat exchanger network achieving those minimum utility targets.

Approach. Compute each stream's duty CP·ΔT; without integration each stream is served by whichever utility is both hot/cold enough and cheapest, sized by Q = ẓ·ΔH. With integration, shift hot streams down and cold streams up by ΔTmin/2, tabulate the net CP imbalance in each temperature interval between consecutive shifted stream temperatures, cascade the heat downward from zero at the top, and add the minimum heat needed at the top to make every cascade value ≥0 — the point where the cascade first reaches exactly zero is the pinch. A network is then built stream-by-stream honouring the pinch-matching feasibility rule (CPhot ≤ CPcold for any match touching the pinch from above).

  1. (a) Utility duties without heat integration. Each stream's total duty: $$Q_{H101}=24.0\times(195-50)=3480\ \text{kW},\quad Q_{C102}=40.0\times(160-100)=2400\ \text{kW},\quad Q_{C103}=20.0\times(130-50)=1600\ \text{kW}$$ C102's target (160°C) requires a utility temperature of at least 160+10=170°C to hold a 10°C approach, which LPS ($\approx$160°C condensing) cannot supply, so C102 must be served by HPS; C103's target (130°C) needs only $\ge$140°C, comfortably below LPS's ceiling, so the cheaper LPS serves it; H101 needs only sensible cooling well within the CW range, so CW serves it. Sizing each from ẓ = Q/|ΔH|: $$\dot m_{HPS}=\frac{2400}{1700}=\boxed{1.412\ \text{kg/s}},\qquad \dot m_{LPS}=\frac{1600}{2000}=\boxed{0.800\ \text{kg/s}},\qquad \dot m_{CW}=\frac{3480}{63}=\boxed{55.24\ \text{kg/s}}$$
  2. (b) Shifted temperatures and the problem-table cascade. Shift the hot stream down 5°C and the cold streams up 5°C (half of ΔTmin) onto a common scale: H101*: 190→45°C; C102*: 105→165°C; C103*: 55→135°C. The six distinct shifted temperatures (190, 165, 135, 105, 55, 45) bound five internal intervals; in each interval, net = (ΣCPhot − ΣCPcold)×ΔT of the streams spanning it: $$[190,165]:\ (24-0)(25)=+600 \quad [165,135]:\ (24-40)(30)=-480 \quad [135,105]:\ (24-40-20)(30)=-1080$$ $$[105,55]:\ (24-20)(50)=+200 \quad [55,45]:\ (24-0)(10)=+240$$ Cascading from Q=0 at the top gives running totals 0, 600, 120, −960, −760, −520 — the most negative value is −960 kW, so adding QH,min = 960 kW at the top makes every value ≥0. The re-cascaded values are 960, 1560, 1080, 0, 200, 440 — the cascade hits exactly zero at shifted T*=105°C, which is the pinch (actual hot-stream pinch temperature 110°C, actual cold-stream pinch temperature 100°C), and the final value, QC,min = 440 kW, is the minimum cold utility. $$Q_{H,min}=\boxed{960\ \text{kW (above pinch)}}\qquad Q_{C,min}=\boxed{440\ \text{kW (below pinch)}}$$
  3. Energy-balance check. Total process heating demand minus total cooling demand (2400+1600−3480 = 520 kW) must equal QH,min−QC,min = 960−440 = 520 kW — confirmed. Heat integration recovers 3040 kW of process-to-process exchange (versus 4000+3480 = 7480 kW of total utility duty with no integration at all), a 81.3% reduction in total utility load.
Problem-Table Cascade (shifted T*, ΔTmin=10°C)T* (°C)Interval net (kW)Cascade (kW)190960165156013510801050← PINCH5520045440+600-480-1080+200+240QH,min = 960 kW (top) QC,min = 440 kW (bottom) Pinch: hot 110°C / cold 100°C
Fig. 1 — Temperature-interval (problem-table) cascade. The cascade first touches zero at shifted T*=105°C (actual pinch 110°C hot / 100°C cold), fixing QH,min=960 kW and QC,min=440 kW.
  1. (c) Heat exchanger network design. Above the pinch there is one hot stream (H101, CP=24) and two cold streams (C102, CP=40; C103's above-pinch segment, CP=20); since Nhot (1) ≤ Ncold (2) above the pinch, no stream split is required. Checking the pinch-matching feasibility rule (CPhot≤CPcold for any match touching the pinch), H101 (CP=24) can only be matched against C102 (CP=40≥24) at the pinch — matching directly against C103's above-pinch segment (CP=20<24) would violate the rule and cause the approach temperature to shrink below 10°C moving away from the pinch. C102's cold inlet (100°C) sits exactly at the cold-pinch temperature, so E1 is the pinch match: running H101 the full length of its above-pinch range (110→195°C) into C102 transfers $$Q_{E1}=24\times(195-110)=\boxed{2040\ \text{kW}}\ \Rightarrow\ C102: 100^\circ\text{C}\rightarrow\left(100+\frac{2040}{40}\right)=151^\circ\text{C}$$ (feasible: 10°C approach at the pinch end, 44°C at the hot end). C102's remaining duty up to its 160°C target, $$Q_{E2}=2400-2040=\boxed{360\ \text{kW}}=Q_{H,min}-Q_{E3},$$ must be supplied by HPS (360/1700 = 0.212 kg/s), since 160°C is beyond LPS's reach. C103's above-pinch segment (100→130°C, CP=20) is not touched by H101 at all (H101 is fully committed to C102 above the pinch), so it is heated entirely by LPS: $$Q_{E3}=20\times(130-100)=\boxed{600\ \text{kW}}\qquad(0.300\ \text{kg/s LPS})$$ confirming $Q_{E2}+Q_{E3}=360+600=960\ \text{kW}=Q_{H,min}$. Below the pinch, only H101 (CP=24) and C103's below-pinch segment (50→100°C, CP=20) remain (Ncold=1≤Nhot=1, CPhot≥CPcold as required below the pinch), forming the second process match, E4: $$Q_{E4}=20\times(100-50)=\boxed{1000\ \text{kW}}\ \Rightarrow\ H101: 110^\circ\text{C}\rightarrow\left(110-\frac{1000}{24}\right)=68.3^\circ\text{C}$$ (feasible: 10°C approach at the pinch end, 18.3°C at the cold end). H101's remaining duty down to its 50°C target, $$Q_{E5}=24\times(68.3-50)=\boxed{440\ \text{kW}}=Q_{C,min},$$ is removed by CW (440/63 = 6.98 kg/s), confirming the below-pinch target. This 5-exchanger network (E1, E2-heater, E3-heater, E4, E5-cooler) achieves both minimum utility targets exactly, with no stream split anywhere in the design.
PINCHH101 195°C50°CE1110°C (pinch)E468.3°CE5CW 440 kWC102 100°C (in)160°C (out)E1151°CE2HPS 360 kWC103 50°C (in)130°C (out)E4100°C (pinch)E3LPS 600 kWDuties: E1=2040 kW (pinch match) E2(HPS)=360 kW E3(LPS)=600 kW E4=1000 kW (pinch match) E5(CW)=440 kW
Fig. 2 — Grid diagram of the integrated heat exchanger network. H101 (top, flowing left to right) is cooled by E1 (against C102, the above-pinch match) then continues through the pinch to E4 (against C103's below-pinch segment) before a CW trim cooler E5; C102 finishes against an HPS heater E2 above the pinch, and C103's above-pinch segment is heated entirely by an LPS heater E3.
QuantityValue
(a) No integration — HPS for C1021.412 kg/s (2400 kW)
(a) No integration — LPS for C1030.800 kg/s (1600 kW)
(a) No integration — CW for H10155.24 kg/s (3480 kW)
(b) Pinch temperature110°C (hot) / 100°C (cold)
(b) QH,min (above pinch)960 kW
(b) QC,min (below pinch)440 kW
(c) Network dutiesE1=2040 kW, E2(HPS)=360 kW, E3(LPS)=600 kW, E4=1000 kW, E5(CW)=440 kW
(c) Integrated utility flowsHPS 0.212 kg/s; LPS 0.300 kg/s; CW 6.98 kg/s